Decision The report presented a summary of the 2015/16 outturn position (actual income and expenditure) for services within the Housing Revenue Account, compared to the current budget for the year. Decision of Executive Councillor for Housing Agreed that the following proposal be submitted for consideration by the Executive Councillor for Finance and Resources at the Strategy and Resources Scrutiny Committee on 4 July 2016: i. Proposed carry forward requests in revenue funding from 2015/16 to 2016/17, as detailed in Appendix C of the officer’s report , noting that none are proposed for this portfolio on this occasion. ii. Proposed carry forward requests of £210,000 in capital resources from 2015/16 to 2016/17 to fund rephased net capital spending, as detailed in Appendix D of the Officer’s report . Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Business Manager/Principal Accountant (Shared Housing Finance Team). The Committee made the following comments in response to the report: i. The empty homes loans budget appeared quite large for a limited return. Could better use be found for the funds? ii. Agreed that all homes should be lived in. iii. Supported the efforts of officers to return properties to us. The Business Manager/Principal Accountant (Shared Housing Finance Team) u ndertook to provide estimated numbers of empty homes in Cambridge. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor for Housing approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report presents, for the General Fund Housing Portfolio :
a) A summary of actual income and expenditure compared to the final budget for 2015/16 (outturn position)
b) Revenue and capital budget variances with explanations
c) Specific requests to carry forward funding available from budget underspends into 2016/17.
Recommendations
Members of the Scrutiny Committee are asked to consider and make known their views on the following proposals for consideration by the Executive Councillor for Finance and Resources at the Strategy and Resources Scrutiny Committee on 4 July 2016:
a) Proposed carry forward requests in revenue funding from 2015/16 to 2016/17, as detailed in Appendix C, noting that none are proposed for this portfolio on this occasion.
b) Proposed carry forward requests of £210,000 in capital resources from 2015/16 to 2016/17 to fund rephased net capital spending, as detailed in Appendix D.
Background
Revenue Outturn
3.1The overall revenue budget outturn position for the General Fund Housing Portfolio is given in the table below. Detail, by service grouping, is presented in Appendix A.
Report Page No: 1 2014/15 General Fund Housing Portfolio 2015/16 % Final £’000 Revenue Summary £’000 Budget
3,469 Original Budget 3,330 98.0
- Adjustment – Prior Year Carry Forwards 67 2.1
- Adjustment – Service Restructure Costs (2) (0.1)
- Adjustment – Earmarked Reserves (13) (0.3)
- Adjustment – Capital Charges 9 0.3
- Adjustment – Central & Support 1 0 reallocations
6 Other Adjustments 0 0
3,475 Final Budget 3,392 100.0
3,186 Outturn 3,310 97.6
(289) Variation - (Under)/Overspend for the (82) (2.4) year
67 Carry Forward Requests 0 0.0
(222) Resulting Variance (82) (2.4)
3.1Appendix A shows original and final budgets for the year (with the movements summarised in the above table) and compares the final budget with the outturn position for this portfolio for 2015/16. The original revenue budget for 2015/16 was considered by the Executive Councillor for Housing on 14 January 2015.
3.2Appendix B provides brief explanations of the main variances.
3.3Appendix C lists any revenue carry forward requests, with none requested on this occasion.
3.4Net underspending of £82,391 was predominantly due to a lower than anticipated recharge from the HRA for shared amenities and staffing underspends in both the Development and Housing Standards Teams due to vacancies within the teams There is no request to carry forward any of the underspend into 2016/17.
Capital Outturn
3.5The overall capital budget outturn position for the General Fund Housing Portfolio is given in the table below. Appendix D shows the outturn position by scheme and programme with explanations of variances.
Report Page No: 2 2014/15 General Fund Housing Portfolio 2015/16 % Final £’000 Capital Summary £’000 Budget
83 Final Budget 316 100.0
177 Outturn 49 15.5
94 Variation - (Under)/Overspend for the (267) 84.5 year
(2) Rephasing Requests 210 66.5
92 Variance (57) 18.0
3.6Resource of £200,000 to create an Empty Homes Loans Fund was not utilised in 2015/16 due to a combination of delays in implementation, with the need to recruit to a post to facilitate the scheme, and the nature of the scheme itself, which intends to recycle the £200,000 in the form of loans awarded and later repaid. The budget is requested as a carry forward into 2016/17 to allow progression of the scheme.
3.7The projects to make improvements to the Buchan Street shops area and to upgrade facilities at 125 Newmarket Road are both complete, bar the need to conclude any residual payments due to or from the authority. A request to carry forward £10,000 of resource into 2016/17, for the final contractual sums due in respect of the works to 125 Newmarket Road, is made.
4. Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.