Decision In July 2014, the Executive Councillor for Housing approved a three year rolling programme of housing sites in the Council’s ownership for consideration for development, redevelopment or disposal. The report provided a review of the programme and specifically sought approval of a revised Three Year Rolling programme that included sites to be investigated in 2016/17 to 2018/19. Decision of Executive Councillor for Housing i. Approved revisions made to produce the 3 Year Rolling Programme 2016/17 to 2018/19 in the context of the wider . Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Managing Director, Housing Development Agency . He confirmed that any funds delivered by devolution needed to be spent within five years. This was agreed to mean starts on site rather than completed projects. The Managing Director, Housing Development Agency asked the Committee to note that there were no sites added to the programme this year. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
In July 2014, the Executive Councillor for Housing approved a three year rolling programme of housing sites in the Council’s ownership for consideration for development, redevelopment or disposal.
This report provides a review of the programme and specifically seeks approval of a revised Three Year Rolling programme that includes sites to be investigated in 2016/17 to 2018/19.
The report sets this request for approval to the revised three year programme in the context of; the new Council Social Housing Programme the Housing and Planning Act 2016 o Starter Homes o Vacant High Value Local Authority Housing Welfare Reform and Work Act 2016 o 1% rent reductions
Recommendations
The Executive Councillor is recommended:
To approve revisions made to produce the 3 Year Rolling Programme 2016/17 to 2018/19 in the context of the wider Social Housing Programme. Report Page No: 1 3. Background
As the main provider of housing in Cambridge, the reasons why the Council has its own programme are as follows;
Provide additional social housing to meet the shortfall in Cambridge and to replace the loss of social housing through the Right to Buy.
Replace some of the Council’s existing housing that no longer meets current day standards and is becoming less popular with residents.
Build new house types that will better meet the overall mix of social housing needed in the future.
Improve the energy efficiency of the Council’s housing.
Social Housing Programme
Cambridge City Council has been directly delivering social housing since 2010. This programme has delivered 131 units thus far and is set to deliver another 164 units in the next year alone. This has been achieved through Housing Revenue Account funding, Homes and Communities Agency grant and Right to Buy receipts. More recently the General Fund has bought stock for Cambridge City Housing Company to supply sub market rental properties.
There has been a tremendous amount of change from central Government in the social housing sector over the last 12 months. The 1% rent reduction for four years has severely impacted the HRA and the Social Housing Programme the Council can pursue. Officers are investigating innovative ways of working to enable the delivery of housing that is affordable but the pace of the Social Housing Programme through the HRA has slowed due to the lack of certainty with regards to funding. Therefore the proposed three year rolling programme in Appendix 2 has no further HRA sites added.
The Housing Development Agency (HDA) is project managing the development of some General Fund land, which means social housing will continue to be directly delivered by the Council, but a minority will be on HRA land over the next 4 years.
A separate report to this Committee called ‘New Social Housing on Housing Revenue Account Infill Sites’ requests approval of the Executive Councillor for Housing to progress a few more small HRA sites. These are sites we are
Report Page No: 2 able to fund with the money committed in the budget to match fund Right To Buy receipts.
Three Year Rolling Programme
This annual review keeps members apprised of progress with sites and offers the opportunity to introduce new sites for investigation.
Appendix 1 provides an update of the schemes within the three year rolling programme that are already under investigation.
Appendix 2 is the revised three year rolling programme that is requested to be re-approved with the only addition being Akeman Street. This site gained Executive Councillor for Housing approval to be included in the three year rolling programme at the January 2016 Committee and therefore residents have previously been notified of its inclusion. A final scheme will be brought to Housing Scrutiny Committee for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.