2015/16 Revenue and Capital Outturn, Carry Forwards and Significant Variances - Communities Portfolio
ApprovedScrutiny1 paper
Community Services Scrutiny Committee approved this item on Thursday 30 June 2016. Below is the council's own wording, with the papers it was decided on.
Decision The Officer’s report presented for the Communities Portfolio: a) A summary of actual income and expenditure compared to the final budget for 2015/16 (outturn position). b) Revenue and capital budget variances with explanations. c) Specific requests to carry forward funding available from budget underspends into 2016/17. Decision of Executive Councillor for Communities The Executive Councillor requested that the Executive Councillor for Finance and Resources approved the following at the Strategy and Resources Scrutiny Committee on 4 July 2016: a) Carry forward requests totalling £60,000 revenue funding from 2015/16 to 2016/17, as detailed in Appendix C of the Officer’s report. b) Carry forward requests of £5,991,000 capital resources from 2015/16 to 2016/17 to fund rephased capital spending as detailed in Appendix D. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The committee made no comments in response to the report from the Principal Accountant (Services). The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report presents, for the Communities Portfolio :
a) A summary of actual income and expenditure compared to the final budget for 2015/16 (outturn position)
b) Revenue and capital budget variances with explanations
c) Specific requests to carry forward funding available from budget underspends into 2016/17.
Recommendations
The Executive Councillor is recommended to request that the Executive Councillor for Finance and Resources, at the Strategy and Resources Scrutiny Committee on 4 July 2016, approves the following:
a) Carry forward requests totalling £60k revenue funding from 2015/16 to 2016/17, as detailed in Appendix C
b) Carry forward requests of £5,991k capital resources from 2015/16 to 2016/17 to fund rephased capital spending as detailed in Appendix D.
Background
Revenue Outturn
3.1The overall revenue budget outturn position for the Communities Portfolio is given in the table below. Detail, by service grouping, is presented in Appendix A.
- Adjustment – Service Restructure Costs (3) (0.0)
- Adjustment – Earmarked Reserves (5) (0.1)
- Adjustment – Capital Charges 199 2.6
- Adjustment – Central & Support (654) (8.6) reallocations
1,067 Other Adjustments 0 0.0
8,092 Final Budget 7,613 100.0
7,956 Outturn 7,440 97.7
(137) (Under) / Overspend for the year (173) (2.3)
162 Carry Forward Requests 60 0.8
25 Resulting Variance (113) (1.5)
3.2Appendix A shows original and final budgets for the year (with the movements summarised in the above table) and compares the final budget with the outturn position for this Portfolio for 2015/16. The original revenue budget for 2015/16 was approved by the Executive Councillor for Communities on 15 January 2015.
3.3Appendix B provides explanations of the main variances.
3.4Appendix C lists revenue carry forward requests.
Capital Outturn
3.5The overall capital budget outturn position for the Communities Portfolio is given in the table below. Appendix D shows the outturn position by scheme and programme with explanations of variances.
2014/15 Communities Portfolio 2015/16 % Final £’000 Capital Summary £’000 Budget
5,548 Final Budget 10,520 100.0
1,693 Outturn 4,566 43.4
(3,855) (Under)/Overspend for the year (5,954) (56.0)
3.6The majority of the rephasing (£5,782,000) relates to Clay Farm Community Centre - Phase 2 (Construction).
4. Implications
4.1The net variance from the final budget (see above), as most of the variances relate to schemes funded from developer contributions (S106), would result in an increased use of General Fund reserves of £4,000 only, offset by a £14k managed underspend on revenue to cover this.
4.2A decision not to approve a carry forward request may impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equality and poverty, environmental, procurement, consultation and communication and/or community safety implications.
Background papers
Closedown Working Files 2015/16 Directors’ Variance Explanations – March 2016 Capital Monitoring Reports – March 2016 Budgetary Control Reports to 31 March 2016
6. Inspection of papers
To inspect the background papers or if you have a query on the report please contact:
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.