Grand Arcade Deck Coating and Drainage Repairs/Replacement

Approved Scrutiny 1 paper

Environment Scrutiny Committee approved this item on Tuesday 17 January 2017. Below is the council's own wording, with the papers it was decided on.

Item17/7/Env

Resolved

Decision The Executive Councillor was asked to approve a project to procure and award a contract, subject to budget approval, to replace the worn deck coating on the outside exposed parking decks and review and upgrade the drainage system at the Grand Arcade car park. Decision of Executive Councillor for Planning Policy and Transport i. Approved carrying out the procurement and contract award for a project to review and upgrade the drainage system and replace the worn deck coating at the Grand Arcade car parks. a. Drainage system improvements and new deck coating work to be funded as part of an overall capital bid of £1.6 million; to meet these and other proposed works at the multi storey car parks in 2017/18. b. Subject to: If the quotation or tender sum exceeds the estimated contract value by more than 10% then the permission of the Executive Councillor and Strategic Director would be sought prior to proceeding. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Commercial Operations Manager . Work would be undertaken in Summer 2017. The Commercial Operations Manager updated his report by correcting a typographical error on P33. The figure should be £1.6m not “capital bid of £1.4 million”. The Committee unanimously resolved to endorse the recommendations as amended. The Executive Councillor approved the recommendations as amended. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Recommendations

The Executive Councillor is recommended:

2.1To approve the carrying out the procurement and contract award for a project to review and upgrade the drainage system and replace the worn deck coating at the Grand Arcade car parks.

Drainage system improvements and new deck coating work is to be funded as part of an overall capital bid of £1.4 million. This is so as to meet these and other proposed works at the multi storey car parks in 2017/18.

Report Page No: 1 2.2 Subject to: If the quotation or tender sum exceeds the estimated contract value by more than 10% then the permission of the Executive Councillor and Strategic Director will be sought prior to proceeding.

Background

The Grand Arcade car park is now coming up to 10 years old. It is recognised that deck coating has a life expectancy of approx. 10 years and as a result of higher than average usage the deck coating now needs urgent replacement. There is also a requirement to review the existing drainage at this car park and to action repairs and/or replacements to ensure it remains fully operational.

The works required are:

a) to replace the waterproof deck coating

b) to conduct repairs and/or replacements works to the existing drainage

This is to prevent water ingress into the structure and protect the long term operations of the car park. Failure to do this will result in corrosion and possible structural weakening caused by water pooling and subsequent water ingress, both of which could result in the open areas of the car park needing to be closed for prolonged periods. The new deck coating system will be required to cover or seal the new or improved drainage and therefore these 2 projects have been amalgamated.

Carrying out these works will ensure we maintain revenue streams to the Council, accessibility to the historic city centre core and meet our lease obligations as part of our operational deliverables of this car park.

Investigative works are continuing to establish exactly the extent of the drainage repairs and their associated costs.

Litigation has been explored and discounted on advice from specialist construction solicitors

4. Implications

(a) Financial Implications The funding for these projects is to be funded as part of an overall capital bid of £1.4 million. This is so as to meet these and other proposed works at the multi storey car parks in 2017/18. Report Page No: 2 The financial implications are set out in the separate parking services appendix 1

These costs are based upon initial estimates from works specialists. Accurate costs will be known when quotes have been received from suppliers as part of the procurement exercise.

The new deck coating will be expected to last up to 10 years therefore protecting both revenue and reputation to the Council

Failure to carry out the works will result in localised flooding and pooling of water resulting in water ingress into the structure. Over time this could result in the Council being responsible for expensive structural repairs.

There are no adverse VAT implications for undertaking the works at the Grand Arcade Car Park

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Grand Arcade Deck Coating and Drainage Repairs/ReplacementReport 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
CP
Councillor Charlotte PerryChair, apologies
NG
Councillor Nigel GawthropeVice-Chair, apologies, sent representative
MS
Councillor Mike SargeantCo-Chair, present
DA
Councillor Donald AdeyCommittee Member, present as substitute
TB
Councillor Tim Bick Lib Dem Spokes for Planning Policy & TransportCommittee Member, present
MG
Councillor Markus Gehring Lib Dem Spokes for Environmental Services and City CentreCommittee Member, apologies, sent representative
DR
Councillor Dan RatcliffeCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present as substitute

On this subject at Cambridge

Search all
  1. Grand Arcade Deck Coating and Drainage Repairs/ReplacementThis decision
  2. Grand Arcade and Queen Anne Terrace Car Parks Sprinkler System ReplacementApproved
  3. Topographical Surveys for Grafton East, Queen Anne Terrace and Grand Arcade Multi Storey Car ParksRefused
  4. Capital Project to Relocate/Amalgamate Car Park Control Room and Shopmobility Office at Grand Arcade Car ParkApproved
  5. Replacement of Car Park Management System at Grand Arcade Car ParkRefused

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies