Housing Scrutiny Committee approved this item on Wednesday 18 January 2017. Below is the council's own wording, with the papers it was decided on.

Item17/5/HSC

Resolved

Decision The report proposed a joint procurement exercise with South Cambridgeshire District Council, to provide a Housing Management Information System for both authorities. The Housing Services would remain distinct, with two instances of the new system provided, but recognised that moving to the use of a single provider would make it easier for the two Councils to share some or all of their housing services in the future. Decision of Executive Councillor for Housing i. Approved a capital budget of £500,000 for Cambridge City Council’s share of the up-front costs of jointly procuring a new Housing Management Information System with South Cambridgeshire District Council. The cost is to be fully met from existing repairs and renewals funds. ii. Noted the current annual support and maintenance revenue budget of £75,000. iii. Recognised the procurement benefits of undertaking this project now, in partnership with South Cambridgeshire District Council. iv. Approved that the authority proceeds with this joint procurement exercise, and that following a compliant competitive process, the Strategic Director is given delegated authority to tender and award a contract on behalf of Cambridge City Council. Reason for the Decision To procure a modern, fit for purpose housing and property management system for the HRA, the wholly owned housing company and any other assets held by the Council which require management activity to be undertaken a s set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Business Manager/Principal Accountant. The Committee made the following comments in response to the report: i. Welcomed the information regarding home ownership. ii. Suggested that tenant and leaseholder representative could be used as part of the consultation process. The Business Manager/Principal Accountant stated the following in response to Members’ questions: i. The joint project board would develop a communications strategy. ii. The full tender would include a requirement for other providers to share the service in future. iii. No additional maintenance budget would be agreed until the system was in place. Cost would vary depending on what host system was selected. iv. Cost would be shared across the authorities proportionally, based on the number of properties under management and the number of users of the system. v. The system would be flexible enough to cope with any impact of devolution. The Committee resolved unanimously to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

This report proposes a joint procurement exercise with South Cambridgeshire District Council, to provide a Housing Management Information System for both authorities. The Housing Services will remain distinct, with two instances of the new system provided, but recognising that moving to the use of a single provider would make it easier for the two Councils to share some or all of their housing services in the future.

Recommendations

2.1The Executive Councillor is recommended:

 To approve a capital budget of £500,000 for Cambridge City Council’s share of the up-front costs of jointly procuring a new Housing Management Information System with South Cambridgeshire District Council. The cost is to be fully met from existing repairs and renewals funds.  To note the current annual support and maintenance revenue budget of £75,000.  To recognise the procurement benefits of undertaking this project now, in partnership with South Cambridgeshire District Council.  To approve that the authority proceed with this joint procurement exercise, and that following a compliant competitive process, the Strategic Director is given delegated authority to tender and award a contract on behalf of Cambridge City Council.

Report Page No: 1 3. Background

3.1South Cambridgeshire District Council’s current contract for their Housing Management system with Orchard is over 20 years old, and their procurement advice is that a full tendering exercise is required in order to comply with EU procurement regulations. South Cambridgeshire District Council’s Executive Management Team has approved a full OJEU procurement exercise to secure a new Housing Management Information System.

3.2Although Cambridge City Council has a further 2 years before the agreed review date for the continued use of the Orchard software, the likely timescale of a full OJEU tender, procurement and implementation means that a joint project would fit well with the need for Cambridge City Council to re-procure these services.

Objectives and desired outcomes

3.3The objectives of the project for Cambridge City Council are as follows:

 To procure a modern, fit for purpose housing and property management system for the HRA, the wholly owned housing company and any other assets held by the Council which require management activity to be undertaken.  To provide a fully integrated housing management, rents, repairs, planned maintenance, asset and land management system  To provide a system that successfully interfaces with other key systems deployed by the Council, with the Financial Management System being of the key applications to interface effectively.  To realise time and cost efficiencies with business process management and time management.  To ensure continued and expanded mobilisation of the workforce, with a flexible and adaptable mobile working solution.  To expand the opportunities for engagement with customers through channel shift, to improve the digital offer so that customers can access key parts of our housing services such as checking rent accounts and ordering and tracking repairs.

3.4A Project Board containing representatives from both authorities and project managed by 3C ICT, will be responsible for the delivery of the project objectives, following a recognised project management framework.

Report Page No: 2 3.2 Expected Benefits

3.2.1. The benefits that will be realised by Cambridge City Council as a result of this project are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of a new Housing Management Information SystemReport 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, present
NA
Councillor Nicholas Avery Lib Dem SpokesCommittee Member, present
NG
Councillor Nigel GawthropeCommittee Member, present
MH
Councillor Marie-Louise Holland Independent/Green Group SpokesCommittee Member, present
RM
Councillor Rosy MooreCommittee Member, present
JP
Councillor Jennifer Page-CroftCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present
JM
John Marais Tenant RepresentativeCo-Optee, present

All 14 on the meeting page

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies