Decision The report provided an update relating to an infill site which was granted scheme specific approval as part of a group of small infill sites at Housing Scrutiny Committee in June 2016. The site was to be brought forward in the Council’s social housing programme, to be included in the Housing Revenue Account (HRA) garage and small infill sites development. The report requests approval to an updated capital budget for the HRA in relation to the site at Hills Avenue, Queen Edith. Decision of Executive Councillor for Housing i. Approved the site to continue to be investigated to be developed for housing . ii. Allocated the capital budget of £249,216 from existing new build budget. iii. Approved that delegated authority be given to the Strategic Director to enable the site to be developed through Cambridge Investment Partnership (CIP) Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Managing Director, Housing Development Agency regarding Options for the Land at Hills Avenue. The Committee regretfully accepted that the site context and location made it more suitable for a three bed house than smaller units. The Managing Director, Housing Development Agency, undertook to provide Committee Members with more details on the planned delivery of smaller properties. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
This scheme includes an area of vacant land that was separated from the existing garden when the property at 39 Hills Avenue was re-let, having been identified as a potential development site by City Homes Staff.
There are no existing properties on this site.
2. Reason for Investigation:
When properties become void and are re let, City Homes assess gardens associated with the property, and its potential for redevelopment if sufficiently size. This land at Hills Avenue was deemed to have suitable amenity space for the existing house whilst allowing potential development of the remaining separated land.
As the Council looks to provide more affordable housing across the City, it is small infill sites such as this that present good potential opportunities for development.
This scheme was included in the Council’s three year rolling programme of sites to investigate further the feasibility and viability of development following committee approval in June 2016.
3. Engagement with Existing Residents
This development does not include the replacement of existing housing.
However, due to the proximity to existing properties, we have written to the neighbouring residents at 38 and 39 Hills Avenue and 11 and 12 Baldock Way to notify them that the Council is investigating the potential of the land for development of affordable housing. Minimal response was received from residents in relation to the letter. A further letter was sent informing residents that the Council would be erecting hoarding to the site boundary to minimise the risk of fly tipping occurring. There was no further correspondence following the issue of this letter.
Should this scheme receive approval to proceed at committee, then the Housing Development Agency (HDA) will continue to work closely with neighbouring residents to ensure they are involved and informed on the development of the vacant land.
4. Feasibility:
The Site
The below plan shows the area for the proposed scheme:
The table below shows the proposed mix approved of new homes for the site. Option Scheme Proposal 1 1 x 3B5P Flat
Site Constraints
Advice was sought from planning consultants in relation to the planning opportunities and constraints on this site including, but not limited to flood risk, highways, residential amenity and heritage considerations.
Some conclusions to the planning appraisal undertaken are noted below:
Site is within close proximity to neighbouring property at 39 Hills Avenue. Protected trees located on site frontage
Therefore proposed design will need to minimise impact on the protected trees and the neighbouring property from an overlooking perspective and the proposed layout plan included in the appendix of this document is indicative only, of what could be accommodated on the site.
Local Housing Need
There is a recognised need for more affordable housing across the city. The table below demonstrates the number of households on the Housing Needs Register. There are currently 235 households in need of a 3 bedroom property, and the progression of this scheme would help in meeting the needs of those on the list.
Cambridge 1bed 2 bed 3 bed 4 bed City 1746 734 235 51
5. Proposed scheme The indicative redevelopment scheme proposed for this site is as follows:
1no. 3 bed 5 person house
6. Costs, Funding and Viability
The Housing Revenue Account (HRA) Business Plan already allows for the spending of Right to Buy Receipts and funding the balance of costs to be met by Devolution grant.
As with all new build developments as details are progressed they will only proceed if they can be funded within borrowing and capital funding parameters in the HRA 30 Business Plan. If a final scheme cannot be delivered within the budget requested then a revised approval will need to be brought back to Committee for scrutiny.
Capital Costs
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.