Cambridge City Council
Housing Scrutiny Committee, Tuesday 20 June 2017 at 5.30pm

Development Options for Land at Queens Meadow

Approved Scrutiny 2 papers

Housing Scrutiny Committee approved this item on Tuesday 20 June 2017. Below is the council's own wording, with the papers it was decided on.

Item17/34/HSC

Resolved

Decision The report provided an update relating to an infill site which was granted scheme specific approval as part of a group of small infill sites at Housing Scrutiny Committee in June 2016. The site was to be brought forward in the Council’s social housing programme, to be included in the Housing Revenue Account (HRA) garage and small infill sites development. The report requested approval to an updated capital budget for the HRA in relation to the site at Queen’s Meadow, Cherry Hinton. Decision of Executive Councillor for Housing i. Approved the site to continue to be investigated to be developed for housing . ii. Approved the allocation of the capital budget of a maximum of £447,809 for the development from existing newbuild budget. iii. Noted the proposed indicative unit type and approve that this be progressed for planning approval. iv. Approved that delegated authority be given to the Strategic Director to enable the site to be developed through Cambridge Investment Partnership (CIP). Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Managing Director, Housing Development Agency, regarding Land at Queen’s Meadow . The Committee welcomed the proposals. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Summary

This scheme includes an area of previous garden land that was separated from the tenancy when the property at 1 Queens Meadow was re-let, having been identified as a potential opportunity by City Homes staff.

There are no existing properties on this site.

2. Reason for Investigation:

When properties become void and are re let, City Homes assess garden land associated with the property, and it’s potential for redevelopment if sufficiently sized. This garden at Queens Meadow was deemed to have suitable amenity space for the existing house whilst allowing potential development of the remaining separated land.

As the Council looks to provide more affordable housing across the City, it is similar infill sites such as this that present good potential opportunities for development.

This scheme was included in the Council’s three year rolling programme of sites to investigate further the feasibility and viability of development following committee approval in June 2016.

3. Engagement with Existing Residents

This development does not include the replacement of existing housing.

However, due to the proximity to existing properties, we have written to the neighbouring residents at 1 Queens Meadow and 3 Queens Meadow to notify them that the Council is investigating the potential of the land for development of affordable housing. No response from residents was received in relation to the letter. A further letter was sent informing residents that the Council would be erecting hoarding to the site boundary to minimise the risk of fly tipping occurring. Again, there has been no communications received from neighbours following the issue of this letter.

Should this scheme receive approval to proceed at committee, then the Housing Development Agency (HDA) will continue to work closely with neighbouring residents to ensure they are involved and informed on the development of the vacant land.

4. Feasibility:

The Site

The below plan shows the area for the proposed scheme:

The table below shows the proposed mix approved and the floor areas of new homes of the two site options proposed. Option Scheme Proposal 1 3 x 1B2P Flat 2 2 x 2B4P Houses

Site Constraints

Advice was sought from planning consultants in relation to the planning opportunities and constraints on this site including, but not limited to flood risk, highways, residential amenity and heritage considerations.

Some conclusions to the planning appraisal undertaken are noted below:

 Site option 1, which is inclusive of 3 nr 1B2P properties does not include much residential amenity space for the proposed occupants  Site option 2, no specific issues identified

Therefore, as we have been made aware of potential planning constraints in relation to site option 1, we have included for site option 2 within this report as well. Option 1 is more financially viable as it includes for 1 extra unit which will provided increased rental income. However, the proposed total scheme cost for Option 2 is lower and no specific planning issues have been raised on this site layout option.

Local Housing Need

There is a recognised need for more affordable housing across the city, and in particular one and two bedroom homes. Both scheme options would be acceptable in terms of addressing these needs.

The table below shows the number of households on the Housing Needs Register, with preference for a property located within Cherry Hinton. Cherry 1bed 2 bed 3 bed 4 bed 5 bed Hinton 502 235 90 11 4

The second table below demonstrates the number of households on the Housing Needs Register who are in need of 1 bed and 2 bed properties in total across Cambridge City, which is inclusive of Cherry Hinton Ward

Cambridge 1bed 2 bed City 1746 734

5. Proposed scheme

Two indicative redevelopment schemes have been produced for the site as follows:

Option 1

3No. 1 Bed 2 Person Flats

Option 2

2No. 2 Bed 4 Person Houses

6. Costs, Funding and Viability

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2017.06.05 Final Apendix 2 Project Appraisal Queens Meadow May 2017 /34/HSCReport 335 KB DownloadRead as text
PDF
Development Options for Land at Queens MeadowReport 152 KB Download

At this meeting

Whole meeting

Who was there

12 of 14 attended
MT
Councillor Mike Todd-JonesChair, present
DB
Councillor Dave BaigentCommittee Member, present
GB
Councillor Gerri BirdVice-Chair, present
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
NG
Councillor Nigel GawthropeCommittee Member, present
MH
Councillor Marie-Louise Holland Independent/Green Group SpokesCommittee Member, present
JP
Councillor Jennifer Page-CroftCommittee Member, apologies
PS
Councillor Patrick SheilCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present
JM
John Marais Tenant RepresentativeCo-Optee, apologies

All 14 on the meeting page

On this subject at Cambridge

Search all
  1. Development Options for Land at Queens MeadowThis decision
  2. Housing Development - Options for Homeless PeopleApproved
  3. Development Options for Land at Hills AvenueApproved

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies