Cambridge City Council
Strategy and Resources Scrutiny Committee, Monday 3 July 2017 at 5.00pm

Office Accommodation Strategy

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 3 July 2017. Below is the council's own wording, with the papers it was decided on.

Item17/23/SR

Resolved

Decision The report presented the outcomes of the design and procurement scheme at Mandela House for the . It outlined the capital funding requirements of the scheme and the proposals for award of contract. The additional funding requirements related to essential maintenance requirements at Mandela House. It was essential to progress the Mandela House project in order to meet the timescales to vacate Hobson House by 31 March 2018. Decision of Executive Councillor for Finance and Resources: i. Approved the scope of the refurbishment schemes, subject to approval of Capital Funding by Council, for Mandela House. ii. Recommended to Council the additional capital funding for the scheme which would be funded from reserves. iii. Subject to the agreed funding from Council approved the award of Contract for Mandela House and furniture as described in the exempt appendix 1. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Estates. The Committee made the following comment in response to the report: i. Commented that the amount of money being invested into Mandela House queried whether it was the intention for it to be used by the council for a long time. Asked what the officer view was on the length of time that they were likely to be based there. The Head of Estates and Facilities said the following in response to Members’ questions: i. The work carried out on Mandela House would have a minimum life span of ten years. There was no guarantee that the council would continue to base itself at Mandela for ten years but the improvements gave the council time to make future decisions. The refurbishment also added value to the building in the event that a decision to sell or let was made. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor stated that the ruling group was committed to retaining the Customer Service Centre at a city centre location which Mandela House provided especially as it is close to the bus interchange area, and approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Recommendations

The Executive Councillor is recommended to:

Report Page No: 1 2.1 Approve the scope of the refurbishment schemes, subject to approval of Capital Funding by Council, for Mandela House. 2.2 Recommend to Council the additional capital funding for the scheme which would be funded from reserves.

2.3Subject to the agreed funding from Council approve the award of Contract for Mandela House and furniture as described on the exempt appendix 1.

Background

3.1The Office Accommodation Strategy (OAS) was presented to Strategy and Resources Committee on 18 January 2016. The Executive Councillor approved the short to medium term aims to consolidate administrative offices into The Guildhall, Mandela House and 171 Arbury Road and the relocation of operational, depot-based services to two sites at Cowley Road. This will be achieved by the refurbishment of retained buildings to create suitable and flexible workspaces, consolidation of desk and floor space to maximise use and the introduction of SMART working practices such as shared office spaces and flexible working arrangements.

3.2The OAS seeks to significantly reduce the overall office accommodation by releasing Hobson House, Mill Road Depot and 89 Cherry Hinton Road from operational use thereby reducing operating costs and producing additional income and capital receipts. A lease of smaller operational (depot management) premises has also been taken on at 130 Cowley Road.

3.3Mill Road Depot is to be used for housing development and Hobson House (which is being sold by Cambridge United Charities) are scheduled to be vacated by end March 2018. This is contingent upon the Mandela House, 130 Cowley Road and The Compound Cowley Road schemes being completed in time.

3.4Our ability to vacate Hobson House by March 2018 is contingent on the Mandela House scheme being approved and progressing to timescale. Staff currently located at Hobson House are scheduled to transfer into Mandela House upon completion of the refurbishments. Our occupancy at Hobson House has been extended to 31 March 2018 by agreement with Cambridge United Charities but it is unlikely that a further extension will be forthcoming as the Charity now has a viable offer for the sale of the premises. The estimated Report Page No: 2 time required for works at Mandela House is five to six months from start on site which means that the contract will need to be awarded by no later than mid-August to allow sufficient provision for any constructional delays and for the re-location of staff to the converted Mandela House offices on completion.

3.5In addition to the final refurbishment and refurnishing schemes developed for the OAS for Mandela House other corporate objectives are being met including:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Office Accommodation StrategyAppendix 403 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
SB
Councillor Sophie BarnettChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy & TransformationCommittee Member, present
RC
Councillor Rod Cantrill Lib Dem Spokes for Finance and ResourcesCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, apologies, sent representative
AS
Councillor Ann SinnottCommittee Member, present
MA
Councillor Margery AbbottReserve, present as substitute

On this subject at Cambridge

Search all
  1. Office Accommodation StrategyThis decision
  2. Council Office Accommodation - Approval of Capital Funding (Executive Councillor for Finance & Resources)Approved
  3. Office Accommodation Strategy Projects at 130 Cowley Road, Cowley Road Compound and Mandela HouseApproved
  4. Office Accommodation StrategyApproved

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies