Guildhall Energy Efficiency Works

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 3 July 2017. Below is the council's own wording, with the papers it was decided on.

Item17/24/SR

Resolved

Decision In December 2015, the Council appointed an external contractor (Bouygues Group PLC) to identify energy efficiency projects within the Council’s buildings and estate. Following extensive investigations, Bouygues have identified a package of proposed measures to significantly reduce energy consumption and carbon emissions from the Guildhall and deliver ongoing financial savings for the Council. The report outlined the proposed measures. The budget for these works was approved at Council on 23 February 2017 as part of the Budget Setting Report for 2017/18. As it was anticipated that the value of these capital works would exceed £300,000, delegated approval was sought for the Strategic Director to award a contract for the works up to the value agreed at Council. Decision of Executive Councillor for Finance and Resources: i. Gave delegated approval for the Strategic Director to award a contract for energy efficiency works, renewable energy works and associated roofing works at the Guildhall up to the value agreed in the Budget Setting Report at Council on 23 February 2017. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Asset Manager. The Committee made the following comment in response to the report: i. In welcoming the proposals commented that modernising systems should reduce the council’s carbon footprint. ii. Asked if officers had a view on how these works could be impacted by future changes created by the Office Accommodation Strategy. The Asset Manager said that the office accommodation work was ongoing but there was no indication that this would have a detrimental impact on the energy efficiency works. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1In December 2015, the Council appointed an external contractor (Bouygues Group PLC) to identify energy efficiency projects within the Council’s buildings and estate. Following extensive investigations, Bouygues have identified a package of proposed measures to significantly reduce energy consumption and carbon emissions from the Guildhall and deliver ongoing financial savings for the Council.

1.2The proposed measures include: a solar photovoltaic (PV) installation; LED lighting; a Combined Heat and Power (CHP); improved heating control systems; mechanical works to the heating and hot water systems; and associated roofing works. Some of these measures were identified in the Council’s current Carbon Management Plan, but others are new projects identified by the contractors. In addition to the anticipated energy savings and carbon emission reductions, it is expected that some of the measures will improve comfort for users of the building.

1.3The budget for these works was approved at Council on 23 February 2017 as part of the Budget Setting Report for 2017/18. As it is anticipated that the value of these capital works will exceed £300,000, delegated approval is sought for the Strategic Director to award a contract for the works up to the value agreed at Council.

Report Page No: 1 2. Recommendations

2.1The Executive Councillor is recommended:

 To give delegated approval for the Strategic Director to award a contract for energy efficiency works, renewable energy works and associated roofing works at the Guildhall up to the value agreed in the Budget Setting Report at Council on 23 February 2017.

Background

3.1On 18 January 2016, the Executive Councillor for Finance and Resources approved the Council’s current Carbon Management Plan. The plan provides the blueprint for reducing energy and fuel consumption and carbon emissions across the Council’s estate and activities between 2016/17 and 2020/21. The plan identified 22 carbon reduction projects for delivery during this period.

3.2In December 2015, the Council signed access agreements to allow it to make use of the Greater London Authority’s (GLA) RE-FIT framework agreement. This allowed the Council to access Bouygues Group PLC as a contractor to identify and deliver energy efficiency projects. The principle benefit of this arrangement is it operates on an energy performance contracting basis. This means that Bouygues will guarantee the energy savings predicted for projects that they deliver for the Council (subject to the new equipment being managed within defined limits). If the projects do not deliver the predicted savings, Bouygues would be liable for financial penalties under the terms of the contract.

3.3During 2016, Bouygues successfully delivered two major projects included in the Carbon Management Plan: installation of LED throughout the Grand Arcade Car Park and Grafton East Car Park. Under the terms of the RE-FIT framework agreement, Bouygues have guaranteed that these two projects will reduce total energy consumption at the two car parks by more than 40%, which will reduce carbon emissions by an estimated 280 tonnes per year and save the Council an estimated £46,000 per year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Guildhall Energy Efficiency WorksReport 209 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
SB
Councillor Sophie BarnettChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy & TransformationCommittee Member, present
RC
Councillor Rod Cantrill Lib Dem Spokes for Finance and ResourcesCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, apologies, sent representative
AS
Councillor Ann SinnottCommittee Member, present
MA
Councillor Margery AbbottReserve, present as substitute

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies