CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Environment Scrutiny Committee, Tuesday 3 October 2017 at 5.30pm

Withdrawal of Community Infrastructure Levy Draft Charging Schedule

Approved Scrutiny 1 paper

Environment Scrutiny Committee approved this item on Tuesday 3 October 2017. Below is the council's own wording, with the papers it was decided on.

Item17/32/Env

Resolved

Decision of Executive Councillor for Planning Policy & Transport i. Resolved to approve the activation of Regulation 18 of the Community Infrastructure Levy Regulations 2010 (amended) and withdraw the Council’s submitted CIL draft charging schedule. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Planning Consultant, Environment, which referred to the proposed CIL draft charging schedule that was submitted to the Planning Inspectorate (PINS) in March 2014 in accordance with Regulation 19 of the Community Infrastructure Regulations 2010 (as amended). Since the draft charging schedule was submitted, there had been a number of factors which would have a detrimental effect on the likely success of the CIL examination and future operation of the proposed CIL. The Planning Consultant and the Senior Planning Policy Officer said the following in response to Members’ questions: i. Once CIL had been introduced there was an allowance for the local authority to make a year on year increase based on the rate of inflation. ii. S106 monies could be required from developments for matters to be put in place that would make it possible to approve a planning proposal that might not otherwise be acceptable in planning terms; collecting up to a maximum of five contributions towards a particular piece of infrastructure, such as funding to improve an access road to a site, to ensure that access would be safe once the development was completed. iii. CIL monies was a general levy (worked out per square meter of the development) held in a ‘central pot’ which was for the charging authority to determine what those contributions could be spent on, generally as a result of an increase in development in the area. iv. It was not possible to spend contributions from CIL and S106 on the same piece of infrastructure. v. The requirement for the introduction of CIL was to have an up-to-date Local Plan where the infrastructure requirements could be calculated, the cost of delivery to assess the viability of the project. The Committee resolved (unanimously) to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

1.1The proposed Community Infrastructure Levy (CIL) draft charging schedule was submitted to the Planning Inspectorate (PINS) in March 2014 in accordance with Regulation 19 of the Community Infrastructure Regulations 2010 (as amended). The charging schedule was to be examined by the same Planning Inspector as has been examining the Cambridge and South Cambridgeshire Local Plans and was to take place following the conclusion of the local plan examinations.

1.2Page Report Since No: 1 the draft charging schedule was submitted, there have been a number of factors which would have a detrimental effect on the likely success of the CIL examination and future operation of the proposed CIL. These factors can be summarised as follows:

1. Proposed modifications in relation to Local Plan site allocations; 2. Infrastructure evidence and its relevance; 3. Viability evidence and its relevance; 4. The emergence of the Combined Authority; 5. Government approach to further amendments of the CIL Regulations; and 6. Emerging joint planning service with South Cambridgeshire Council 1.3 In particular, given the time that it has taken to complete the local plan examination hearings, it is considered that the draft charging schedule submitted for public examination in March 2014 is no longer fit for purpose due to a number of factors as highlighted throughout this report. As such, it is recommended that the Council should formally withdraw the draft charging schedule from examination and reassess its CIL position following the Government’s Autumn 2017 Budget Statement, recognising the closer working opportunities with South Cambridgeshire District Council and, in particular, the emerging Shared Planning Service.

Recommendations

2.1This report is being submitted to the Environment Scrutiny Committee for prior consideration and comment before decision by the Executive Councillor for Planning Policy and Transport. 2.2 The Executive Councillor is recommended: To approve the activation of Regulation 18 of the Community Infrastructure Levy Regulations 2010 (amended) and withdraw the Council’s submitted CIL draft charging schedule. 3. Background

3.1The Planning Act 2008 gave way to the Community Infrastructure Levy Regulations that were introduced in 2010 as the Governments preferred mechanism for securing infrastructure contributions from new developments. In order to be brought into operation, local planning authorities had to have the draft CIL charging schedule independently examined and approved by a Planning Inspector. Report Page No: 2 3.2 The public consultation on the preliminary draft charging schedule took place between 18 March and 29 April 2013.

3.3Cabinet approved the draft charging schedule for consultation on 8 October 2013 and gave authorisation to submit this (and associated evidence including the Regulation 123 infrastructure list) for public examination.

3.4The public consultation on the draft charging schedule took place between 28 October and 9 December 2013.

3.5The draft charging schedule was submitted to PINS for independent examination on 28 March 2014. The examination was to follow the Cambridge Local Plan examination with the same planning inspector being assigned to both.

3.6To inform the charging schedule the Council required infrastructure evidence to demonstrate the extent of a funding gap (to justify the principle of a CIL charge being introduced) and viability evidence (to support the rates and types of development that are proposed being charged a CIL).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Withdrawal of Community Infrastructure Levy Draft Charging ScheduleReport 313 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
NG
Councillor Nigel GawthropeChair, present
GB
Councillor Gerri BirdVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Planning Policy & TransportCommittee Member, apologies, sent representative
DR
Councillor Dan RatcliffeCommittee Member, present
MS
Councillor Mike SargeantCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
DT
Councillor Damien Tunnacliffe Lib Dem Spokes for Environmental Services and City CentreCommittee Member, present
DA
Councillor Donald AdeyReserve, present as substitute
RM
Councillor Rosy Moore Executive Councilor for Environmental Services and City CentreExecutive Councillor

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies