CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Environment Scrutiny Committee, Tuesday 3 October 2017 at 5.30pm

Cycleways Capital Programme

Noted Scrutiny 3 papers

Environment Scrutiny Committee noted this item on Tuesday 3 October 2017. Below is the council's own wording, with the papers it was decided on.

Item17/31/Env

Resolved

Decision of Executive Councillor for Planning Policy & Transport i. Noted the progress and achievements of the (PV007). ii. Supported the expenditure of capital funds up to 2019 as outlined in the Officer’s report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Project Manager, Environment, which referred to the City Council’s joint working with Cambridgeshire County Council on developing and promoting cycling. The work included the introduction of new facilities and the improvement of existing facilities used by cyclists. The Project Manager and Cycling Officer said the following in response to Members’ questions: i. There had been an under spend in the capital cost which had been rephased in to this financial year, in addition to the budget, therefore there was additional funds to be spent. ii. The bulk of Cambridgeshire County Council’s spending on cycling was now funded through the Greater Cambridge Partnership. This allowed projects that had previously been postponed to take place in partnership working with the City Council such as the work to Cherry Hinton high street. iii. The County Council had completed the first phase of the Arbury Road cycling corridor with the second phase due to start. iv. The County Council were also completing Hills Road and Trumpington Road. v. A small proportion of the annual budget was allocated for minor schemes which might include follow up work on completed projects if required following the standard review process. vi. Noted the comments regarding safety on the Green Dragon Bridge. The restriction of the space available had proved difficult to make further adaptations so improvements had been made to visibility. Further funding could be considered if required. vii. The installation of a new bridge proposed further up the river from the Green Dragon Bridge should reduce the volume of cyclists. viii. As schemes were developed, dedicated Officer resources were allocated to scrutinise the proposals whether they were led by City or the County Council to ensure that they met the same standards. ix. Noted the safety concerns to cyclists at the double roundabouts by the Royal Cambridge Hotel. There had not been a viable solution agreed over the years on the best solution to this problem. This matter would be considered by the Greater Cambridge Partnership. x. Two thirds of the commitment to install 1000 cycle parking spaces had been met. However no agreement had been reached with the magistrate courts to give permission for access to the proposed remaining spaces. xi. The proposal to install further bike parks would be investigated by the Greater Cambridge Partnership as part of the City access plan. xii. The installation of the solar studs on Midsummer Common had been County Council lead and could not comment on the consultation (if any) that took place. The Committee resolved (unanimously) to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted ) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Item Cycleways Capital Programme

To: Environment Scrutiny Committee 3 October 2017 Report by: Joel Carre, Head of Environmental Services Tel: 01223 458201 Email: [email protected] Wards affected: All

Cllr Kevin Blencowe, Executive Councillor for Planning Policy & Transport

Key Decision: No

1. Executive Summary 1.1 This report outlines the principle achievements of the Cycleways Capital Programme since it was last considered by Environment Scrutiny Committee in October 2014; along with forward investment proposals for the 2017-18 and 2018-19 years.

2. Recommendations The Executive Councillor is recommended to: 1. Note progress and achievements of the Cycleways Capital Programme (PV007). 2. Support forward expenditure of capital funds up to 2019 as outlined in this report.

Report page no. 1 Agenda page no. 3. Background 3.1. The City Council works jointly with Cambridgeshire County Council on developing and promoting cycling. The work includes the introduction of new facilities and the improvement of existing facilities used by cyclists. A jointly funded programme commenced in 2002 to which the County and City Councils contributed 50:50 to an annual budget of £50,000 per annum over the period 2002-05. This was subsequently increased to a combined annual budget of £100,000 from 2005, and further supplemented by the City Council with a one-off allocation from savings of £250,000 in 2009. 3.2 The initial programme focus was on radial routes in and out of the city, although the completion of improvements to the Madingley Road corridor was deferred due to complexities around future bus priority work. A prioritisation method for schemes was agreed by the (then) Cambridge Traffic Management Area Joint Committee (AJC) in April 2006. Scheme suggestions were considered and approved by AJC on a rolling basis up to its disbanding in 2012 (priorities have since been determined by the Members Cycling & Pedestrian Steering Group) and further supported by Environment Scrutiny Committee. Approved schemes included The Tins, Downham’s Lane and Radegund Road/ Perne Road roundabout improvements. 3.3 On 11 January 2011, Environment Scrutiny Committee approved an extension to the programme to 2014-15 in order to enable these projects to be completed. This included the carry forward of then unspent cycleway programme budget (£138,000), plus a further allocation of £50,000 per annum for four years to match funding available from the County Council, giving a total programme budget of £538,000. 3.4 Environment Scrutiny Committee considered a programme update on 17 October 2014 that set out proposals for further forward spending by the Council of up to £50,000 per year; subject to annual budget setting. This included the completion of schemes already committed; including Radegund Road/ Perne Road roundabout, Jesus Green path widening, a contribution towards Fen Road and Water Street (Chesterton) traffic calming, and the improvement of Green Dragon bridge; alongside a programme of more minor improvements.

Report page no. 2 Agenda page no. 4. Review of Principal Achievements

4.1Whilst the County Council has continued to fund improvements to cycling facilities in Cambridge in recent years (via programmes including the Cycling Ambition Grant, and Greater Cambridge Partnership/ City Deal), there have been no direct contributions to the jointly funded cycleways programme in Cambridge since 2014-15. The City Council has, however, continued to make capital provision of £50,000 per annum available to the programme (PV007 – 39023), with a provisional allocation up to 2018-19 year (subject to annual budget setting).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EqIA Cycleways Capital Programme: ESC 3 Oct 2017 /31/EnvAppendix B 250 KB Download
PDF
Cycleways Capital ProgrammeReport 470 KB DownloadRead as text
PDF
Final Appendix A: Priority List Cycleways Capital Programme: ESC 3 Oct 2017 /31/EnvAppendix 128 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
NG
Councillor Nigel GawthropeChair, present
GB
Councillor Gerri BirdVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Planning Policy & TransportCommittee Member, apologies, sent representative
DR
Councillor Dan RatcliffeCommittee Member, present
MS
Councillor Mike SargeantCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
DT
Councillor Damien Tunnacliffe Lib Dem Spokes for Environmental Services and City CentreCommittee Member, present
DA
Councillor Donald AdeyReserve, present as substitute
RM
Councillor Rosy Moore Executive Councilor for Environmental Services and City CentreExecutive Councillor

On this subject at Cambridge

Search all
  1. Cycleways Capital ProgrammeThis decision
  2. Joint Capital Cycleways Programme ReviewNoted
  3. Joint Capital Cycleways Programme Prioritised Project ListApproved
  4. Cycleways Joint Capital Programme ReviewRefused

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open