Arbury Court Local Centre Improvements

Approved Scrutiny 1 paper

Community Services Scrutiny Committee approved this item on Thursday 5 October 2017. Below is the council's own wording, with the papers it was decided on.

Item17/27/Comm

Resolved

Decision The Officer’s report detailed the development, proposed improvements and completed consultation for Arbury Court Local Centre Project. The scheme involved soft and hard landscaping, upgraded crossing point across Arbury Road, improved lighting and public realm in and around Arbury Court. The City Council part of the project has been developed as part of the Local Centres Improvement Programme, for which approval was granted by the Executive Councillor for City Centre and Public Places in October 2014, to improve two local centres (Cherry Hinton High Street and Arbury Court) with a third to be determined. Decision of Executive Councillor for Streets and Open Spaces i. Noted the results of public consultation on improvements to Arbury Court as set out in Appendix A of the Officer’s report. ii. Noted that the scheme was being proposed for funding through the Mid-Year Financial Review (MYFR), following Capital Programme Board approval 04/07/2017. iii. Supported the proposed improvements to Arbury Court Local Centre as illustratively set out in Appendix B of the Officer’s report for further development and implementation. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Project Officer . The Committee made the following comments in response to the report: i. Expressed concern that opening up Arbury Court ( eg removing planters) may lead to safety concerns if cyclists used it as a thoroughfare, which may result in collisions with pedestrians. ii. Sought clarification on the type of trees proposed for the area, their suitability and impact on residents’ light levels. The Project Officer said the following in response to Members’ questions: i. Trees were chosen to ensure they had appropriate height/foliage so they had the least impact on residents’ light. ii. Planters were removed as they were a maintenance issue, in need of refurbishment and to fit in with a modern urban design. iii. Trees would act as discreet barriers to prevent the court becoming a cyclist thoroughfare. Some drop bollards would be in place too. Cyclists currently passed through and only irresponsible ones caused a danger to the pedestrianized area, so the new proposal should not worsen residents’ safety. Physical barriers to improve safety for pedestrians against irresponsible cyclists would be extensive and very intrusive on the space. iv. The amount of cycle parking facilities was not being reduced, the parking bays were being moved to the edges of the Court (from the middle) to discourage cycling in the Court. The number of useable cycle parking bays would increase overall. v. Following concerns raised in consultation feedback an improved seating area was proposed nearer Arbury Road, outside the Library and Gurdwara , rather than the central square of Arbury Court. A number of the seats would have arms. vi. Undertook to review seat location with the designer to determine if seats could be located to act as discreet barriers to discourage high speed cycling in the Court. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Community Services Scrutiny Committee

Recommendations

2.1The Executive Councillor is recommended to: a) Note the results of public consultation on improvements to Arbury Court as set out in Appendix A.

b) Note that the scheme is being proposed for funding through the Mid-Year Financial Review (MYFR), following Capital Programme Board approval 04/07/2017.

c) Support the proposed improvements to Arbury Court Local Centre as illustratively set out in Appendix B for further development and implementation.

Report Page No: 1 3.0 Background

Local Centres Improvement Programme 3.1 The Local Centres Improvement (LCI) Programme was agreed initially by resolution of full Council in February, 2014, for targeted improvements to select local centres, for 3 Local Schemes of between £200,000 and £340,000 to 2019/20. At Community Services Scrutiny Committee (CSSC) July 2014 a proposed approach to the LCI programme was agreed for the years 2014 to 2020 with an audit criteria and approach for selection of local centres to be presented to the next CSS. Then at CSSC in October 2014 a phased-in budget of £635,000 for the targeted three projects, specifically Cherry Hinton High Street, Arbury Court and Mitcham’s Corner pending design was approved. However following this budget approval the funding was reserved and an indicative value of £635,000 was placed on the Projects under Development list.

3.2In addition at the meeting of the CSSC on October 16, 2014, the Executive Councillor for City Centre and Public Places approved a detailed audit of Local Centres and the recommendations were as follows: i. the selection of Cherry Hinton High Street and Arbury Court centres for inclusion in the Local Centre Improvement Programme for the reasons set out in the officer’s report; ii. the retention of a third priority project to be added to the programme, after debate at scrutiny committee, at a later date pending the outcome of progress with planned work related to the Mitcham’s Corner District Centre as part of City Deal implementation; and iii. that the detailed funding, design and delivery of improvements to Cherry Hinton High Street and Arbury Court be the subject of Project Appraisals to be approved by the Executive Councillor for City Centre and Public Places at a future committee meeting.

3.3The third resolution above notes the need for the approval of a “Project Appraisal” the Part B project appraisal went to Capital Programme Board and was approved 04/07/2017. The resolution also required the same to be approved by the Executive Councillor at a future committee meeting, in essence this meeting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Arbury Court Local Centre ImprovementsReport 809 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
DR
Councillor Dan RatcliffeChair, present
AS
Councillor Ann SinnottVice-Chair, present
MA
Councillor Margery AbbottCommittee Member, present
YA
Councillor Ysanne Austin Lib Dem Spokes for Streets and Open SpacesCommittee Member, present
SB
Councillor Sophie BarnettCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
OG
Councillor Oscar Gillespie Independent/Green Spokes for Streets and Open Spaces / CommunitiesCommittee Member, present
ZO
Councillor Zoe O'Connell Lib Dem Spokes for CommunitiesCommittee Member, present

On this subject at Cambridge

Search all
  1. Arbury Court Local Centre ImprovementsThis decision
  2. Councillor Dalzell: Securing Arbury Court's Future as a Thriving Community HubApproved
  3. 12/1428/FUL - 16-18 Arbury CourtApproved
  4. 11/1501/FUL - The Grove, Arbury Court, CambridgeApproved

More from Cambridge Community Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Mar 2018 Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a... Refused Open
15 Mar 2018 Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover... Approved Open
15 Mar 2018 Annual Update on the Work of our Strategic Partnerships - Communities PortfolioDecision The Officer’s report provides an update on the work of the Health and Wellbeing Board and Children’s Trust a... Agreed Open
18 Jan 2018 Policy for Use of Events on Parks and Open SpaceDecision The hosting of events on city parks and open spaces had become increasingly popular with both local and nati... Approved Open
18 Jan 2018 S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ... Noted Open