Strategy and Resources Scrutiny Committee agreed this item on Monday 13 November 2017. Below is the council's own wording, with the papers it was decided on.

Item17/52/SR

Resolved

Agreed the need to provide disabled, visitor and car club spaces. ii. Queried why he had not received a response regarding the price of providing parking or on his proposed amendments. The Executive Councillor for Strategy and Transformation responded: i. Stated that the evidence base would form part of the planning application. ii. Disagreed that residents should be denied the right to park. iii. Confirmed that the comments were welcomed and would be considered. 2. John Preston raised the following points: i. Asked whether the full planning application would consider the whole depot site inclusive of access, the YMCA and former library building. ii. Special regard needed to be taken to the library because of its listed status. Queried whether Historic England had been contacted regarding the library. iii. Asked why the library had been neglected from the proposals so far. iv. Stated that it would be prudent to postpone the planning application until a transport assessment had been carried out, access issued had been looked at and YMCA proposals had been fully considered. The Executive Councillor for Strategy and Transformation responded: i. Agreed that the interaction with the library needed to be considered and Historic England would be contacted. ii. A transport assessment would be undertaken to look at the junctions and how to minimise impact. iii. The planning application for the majority of the site was due to be submitted in December. The YMCA would have a separate planning application. iv. Confirmed that he was happy to respond to other questions in writing. John Preston raised the following points as a supplementary question: i. Stated that at every stage of the consultation process so far he had felt the need to request further information about access arrangements to the site rather than it being readily available. The Executive Councillor for Strategy and Transformation responded: i. Highlighted that the site had been used by vehicles for the last 100 years. ii. Other permeable factors needed to be considered such as the impact of the Chisholm Trail, which ran through parts of the site. 3. John Franks, Chair of Petersfield Area Community Trust (PACT) raised the following points: i. PACT sought a charitable objective and raised concern about how the proposals were going to be incorporated with the wider existing community. ii. Queried accesses to the site, the proposals were unclear and needed to be integrated with the surrounding area more effectively. iii. The provision of green space appeared fragmented which limited the usable open space. iv. PACT had received information that the community space would be developed in conjunction with YMCA, however, early indicators suggested that community use would be limited. v. Requested that community facility funding should not go to the YMCA owned buildings, it needed to provide dedicated community provision. The Strategic Director responded: i. Confirmed that the Chisholm Trail provided north to south access of the site. ii. Referred to section 3.2.4 of the Supplementary Planning Document (SPD) which outlined how the green space was designed to accommodate four different activities. There was also an S106 requirement to accommodate for the needs of the wider community. iii. Welcomed the contribution made by PACT and encouraged a broader discussion on provision and how this could be provided. 4. Jannie Brightman raised the following points: i. Requested more clarity within the development. There appeared to be lots of overlapping area which impact one another between the SPD, consultations, committee meetings and planning applications. Many new stages were starting before others had been completed which meant that the situation had become confusing. ii. Referenced the YMCA and asked how land could be transferred to CIP if they did not know what would be on it yet without receiving a detailed plan first. iii. Queried what commitment had been made to the YMCA. The Executive Councillor for Strategy and Transformation responded: i. The YMCA had provided lots of information and had committed to providing community space. ii. No firm proposals had been received for the Gate House. iii. The YMCA would not be included in the first planning application because the proposals had only recently been submitted. The Council did not want to rush the detail; it needed careful consideration to be beneficial in delivering on wider objectives for both parties. Jannie Brightman raised the following points as a supplementary question: i. Stated that the decision to include the YMCA appeared to be a done deal. Many other suggestions had been submitted throughout this project but none had been considered as thoroughly as this one. ii. Petersfield has been crying out for more community facilities, asked if they could hope to receive some which were run by the Council. The Executive Councillor for Strategy and Transformation stated that it had not yet been agreed who would run and own the facilities provided. The Strategic Director responded: i. Confirmed that the agreement in place saw CIP proposals go before the Board before they came to committee. The YMCA proposals would include a lot more detail. ii. They intended to preserve the old library so discussion with the County Council was needed. iii. Clarified that the project plan wasn’t conditional to the consultation on 2 November but was based upon the indicative project plan. iv. The consultation was open until 20 November; so far 70 responses had been received. 5. Stephen Hewitt raised the following points: i. Asked what price the Council would achieve when it transferred the Mill Road Depot land into the CIP. ii. Queried if the amount received was best value. iii. Sought clarification whether the transferred land would be freehold or leasehold. The Strategic Director responded: i. Confirmed that an independent valuation had been undertaken to establish the current value of the land. The amount was estimated at £11million. ii. The land would be leasehold. If issues arose there was a break clause in the lease. Matter for Decision The principles which govern the progression of sites with development opportunities through CIP were approved at Strategy & Resources Scrutiny Committee on 9th October 2017. Mill Road Depot was the first General Fund asset to be developed using these approved principles. The CIP Investment Team had developed a strategic Project Plan for the site incorporating a clear development brief to meet the Council’s key objectives following public consultation and in line with planning policy and the supplementary planning document for the site agreed in March 2017. CIP Board approved this Project Plan on 3rd November 2017. In accordance with the principles set out and the CIP Board approval of the Project Plan, this report outlined the key elements of the Plan, including a summary investment plan, and identified alternative options considered to inform the agreed strategic objectives. The paper made recommendations for transfer of the site to CIP for the Investment Partnership to take the site forward for development as part of an overall programme to deliver the 500 new Council homes. Decision of Executive Councillor for Strategy and Transformation i. Approved the transfer of the land known as Mill Road Depot, shown edged red on the attached plan in Appendix 1, to Cambridge Investment Partnership (CIP) for redevelopment in accordance with the approved Supplementary Planning Document. This transfer would be at a value provided by an independent valuer , which had been approved by CIP Board as detailed in the Project Plan. ii. Noted that, following transfer of the land, there would be two planning applications submitted by CIP to develop the land for housing and the YMCA in accordance with the Council’s strategic and corporate objectives and with the output from the public consultation and pre application planning process. iii. Noted also that the proposed commercial in confidence investment plan for the project in Appendix 5 would be confirmed subject to the outcomes of the public consultation on 2 November and the determination of the CIP’s planning applications. The relevant investment requirements would be subject to the appropriate Council investment decisions. iv. Approved further work on the provision and management of community facilities in discussion with the local community, local councillors and the YMCA. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Director . The Committee made the following comments in response to the report: i. Referred to the first recommendation and asked what written agreement was in place between Cambridge City Council, CIP and YMCA. ii. Queried whether the Council should wait until a proper agreement with the YMCA was in place before transferring the land given that it was a key part of the package. iii. Asked how the financial relationship with the YMCA been agreed. iv. Asked who was undertaking the negotiation within the tripartite relationship. The Strategic Director said the following in response to Members’ questions: i. The Council had received a commitment from YMCA. A draft Memorandum of Understanding (MoU) had committed the YMCA and CIP to work together for the relocation. Once an agreement had been concluded a contract would follow. ii. The relocation of the YMCA was a recent proposal. If the whole development waited until an agreement was reached with the YMCA it would delay the whole project significantly. In order to make progress the first application would cover the wider site and the YMCA would follow. iii. Confirmed that the financial relationship was based on best estimates at this stage. iv. Highlighted that it was inappropriate to transfer the land in two separate transactions to accommodate the YMCA agreement. The MoU ensured the best outcome from all parties and a break clause gave assurances. v. Affirmed that the negotiation was undertaken on a tripartite basis between the City Council, YMCA and Hill Residential, the City Council’s planning department were offering advice. Councillor Baigent referred to the concern raised by the public speakers regarding community facilities and suggested an amendment to the recommendations. Councillor Baigent proposed an additional recommendation as an amendment to the Officer’s recommendation : · Approved further work on the provision and management of community facilities in discussion with the local community, local councillors and the YMCA. The Committee unanimously approved the additional recommendation. Councillor Cantrill proposed the following amendment to the Officer’s recommendation : Deleted wording struck through , additional wording underlined: ii. Noted that, following transfer of the land, there would be two planning applications submitted by CIP to develop the land for housing and the YMCA in accordance with the Council’s strategic and corporate objectives and with the output from the public consultation and pre application planning process. ii. The transfer of the land would be subject to the following conditions: a) That the level of social housing on the site would be no less than 59% of the total number of homes (currently 187) b) That the Council would receive a rate of interest (on a combination of current and rolled up basis) on the value of the instrument issued in relation to the transfer of the land into the CIP c) That the provision of community facilities would be managed on a joint basis between the Council (and/or an appropriate residents forum from the development) and the YMCA (in a joint venture vehicle) d) That the social housing, when acquired by the HRA, following the development of the site, would be rented on a Local Authority Rent basis e) That the Council commits to acquire a further 20% (37 units of the market homes) through the Cambridge Housing Company, that it would rent on a Local Living Rent basis ( ie one third of income of the household) To the extent that one or a number of the conditions a) to c) were not satisfied then the Council would have the option to trigger the right for the land to revert back to the Council Councillor Cantrill requested that part C of the amendment be voted on separately. The Committee rejected part C of the additional recommendation by 4 votes to 2. The Committee rejected the remainder of the amendment by 4 votes to 2. Opposition Councillors made the following comments in response to the amendments: i. Stated that although parts of both amendments were similar in terms of the focus on community facilities the Liberal Democrat amendment was broader overall. ii. They wanted guarantees that the joint venture with the CIP would ensure the interests of both parties. A mechanism needed to be in place which enabled the Council to retrieve the land if the promised features were not delivered. iii. Asserted that Councillor Baigent’s amendment was too vague. Joint venture management regarding the community facilities required clearly defined aims and objectives to negotiate effectively. iv. Stated the belief that the Council should receive a return on the land. The Strategic Director said the following in response to Members’ questions: i. The initial brief for the site was for a minimum of 40% social rented housing, this has been exceeded already. If the number was increased to 59% the project funding gap would put significant pressure on the Council. ii. To change the levels of social rented housing on the site could have significant implications for the CIP agreement. The Committee agreed that in order to discuss the detail and financial implications of Councillor Cantrill’s amendment the meeting would have to exclude the press and public. The Scrutiny Committee resolved to exclude members of the public from the meeting on the grounds that, if they were present, there would be disclosure to them of information defined as exempt from publication by virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972. Members of the public were excluded at 21:15 Members of the public were readmitted at 21:50 Councillor Bick referred to the future purchase of housing on the site and suggested an amendment to the recommendations. Councillor Bick proposed the following amendment to the Officer’s recommendation: v. Agreed to investigate a potential future purchase of market homes on this site for letting at Local Living Rent The Committee rejected the amendment by 4 votes to 2. The Committee resolved by 4 votes to 2 to endorse the officer recommendations. The Executive Councillor approved the recommendations as amended. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1A core objective for Cambridge City Council is in tackling the housing crisis in Cambridge. The City Council has worked to deliver affordable housing in this area with high housing market values and private rents, for many years in partnership, with significant levels of new provision already completed, for example on sites in Trumpington. There are currently, however, still 2500 applicants on the housing register.

1.2The City Council has agreed a devolution deal with government to deliver 500 new Council homes over 5 years. The programme for

Report page no. 1 Agenda page no. delivery of these will focus on social rented homes (defined locally as rents at no greater than Local Housing Allowance levels). The new housing will be owned and managed through the Council’s Housing Revenue Account (HRA) and will be let as secure local authority tenancies.

1.3The Mill Road Depot site comprises 2.7ha adjacent to Mill Road bridge and has served as the main site for Cambridge City Council Services since the 1990s. In 2015 the Exec Cllr approved the initiation of a development brief for the site in order to maximise the use of Council assets to deliver much needed housing.

1.4The General Fund development programme was approved by the Executive Councillor for Finance and Resources at the Strategy & Resources Scrutiny Committee in January 2016. This is a ten year programme of potential development and investment opportunities for General Fund sites, of which Mill Road Depot is the largest.

1.5In 2016 the Strategy and Resources Scrutiny Committee approved the setting up of the Cambridge Investment Partnership (CIP) as a mechanism for the Council to bring forward assets for development to provide sites for the delivery of new homes. This partnership brings with it the advantage of the experience and resources of the development partners, which is seen as especially beneficial on large and complex sites which includes the Mill Rd Depot site. The CIP was established in January 2017.

1.6The principles which govern the progression of sites with development opportunities through CIP were approved at Strategy & Resources Scrutiny Committee on 9th October 2017. Mill Road Depot is the first General Fund asset to be developed using these approved principles.

1.7The CIP Investment Team has developed a strategic Project Plan for the site incorporating a clear development brief to meet the Council’s key objectives following public consultation and in line with planning policy and the supplementary planning document for the site agreed in

Report page no. 2 Agenda page no. March 2017. CIP Board approved this Project Plan on 3rdnd November 2017.

1.8In accordance with the principles set out in clause 1.6 above, and the CIP Board approval of the Project Plan, this report outlines the key elements of the Plan, including a summary investment plan, and identifies alternative options considered to inform the agreed strategic objectives. The paper makes recommendations for transfer of the site to CIP for the Investment Partnership to take the site forward for development as part of an overall programme to deliver the 500 new Council homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2017 11 03: Appendix 3 Mill Road CIP Presentation Boards /52/SRAppendix 14 MB Download
PDF
2017.11.01: Appendix 2 Mill Road EqIA /52/SRAppendix 257 KB Download
PDF
Strategic Site Development of Mill Road DepotReport 930 KB DownloadRead as text

At this meeting

Whole meeting
17/50/SRPublic QuestionsAgreed 17/51/SRStrategic Site Development of Park Street Car ParkApproved
17/52/SRStrategic Site Development of Mill Road DepotThis decision

Who was there

6 of 7 attended
SB
Councillor Sophie BarnettChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy & TransformationCommittee Member, present
RC
Councillor Rod Cantrill Lib Dem Spokes for Finance and ResourcesCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, present
AS
Councillor Ann SinnottCommittee Member, present
RD
Councillor Robert DrydenCommittee Member, in attendance

On this subject at Cambridge

Search all
  1. Strategic Site Development of Mill Road DepotThis decision
  2. Strategic Development of Mill Road Depot SiteNoted
  3. Strategic Site Development of Park Street Car ParkApproved
  4. Cb1 station area redevelopment - discharge of strategic planning condition 7 - site wide public realm and landscape strategyDecided
  5. Cb1 station area redevelopment - discharge of strategic planning condition 24 – site wide ecological conservation management planDecided
  6. Cb1 station area redevelopment - discharge of strategic planning condition 61 – site wide traffic management design strategyDecided

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies