Housing Scrutiny Committee, Thursday 27 September 2018 at 5.30pm

Strategic Development of Mill Road Depot Site

Noted Scrutiny 1 paper

Housing Scrutiny Committee noted this item on Thursday 27 September 2018. Below is the council's own wording, with the papers it was decided on.

Item18/45/HSC

Resolved

Decision of Executive Councilor for Housing i. Noted the updated Phase 1 development which will be delivered at the back of the site as shown on the plan in Appendix 1 of the Officer’s report. ii. Approved the strategic brief for the front part of the site following the withdrawal of YMCA Trinity Group. Development of this land will form Phase 2 of the development and will primarily be a housing development with the affordable units contributing to the Devolution Programme target. Phase 2 would also deliver the in perpetuity council owned community facility, delivery of which will be funded through S106 contributions. iii. Approved the proposal for a second planning application for the front of the site. The development proposal on which the planning application will be based will meet the strategic brief outlined in paragraph 4.8 and the Council’s strategic and corporate objectives for the site. It would be informed by the output from the public consultation and pre- application planning process. Submission of the final planning application to be delegated for approval by Board and Strategic Director and the Cambridge Investment Partnership (CIP) Board. iv. Approved to delegate authority for agreement of the final mix of affordable housing to the Strategic Directors in consultation with the Executive Councillor for Housing. Note that the scheme is still indicative and authorise the Strategic Directors in consultation with the Executive Councillor to approve variations to the scheme including the number of units and mix of property types and sizes outlined in this report in line with Council strategic objectives and housing requirements. Decision of the Executive Councillor for Finance and Resources i. Approve the indicative proposed investment plan for Phase 2 of the development as outlined in confidential Appendix 4 of the Officer’s report with the high level commitments associated with the General Fund and HRA. The investment plan would be refined in line with final project plans post planning permission determination and approval by the CIP Board, with the Council’s funding built in to the relevant Budget Setting Report. Reason for the Decision As set out in the officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Director which referred to the transfer of the land known as Mill Road Depot to CIP for redevelopment; in December 2017 the land was transferred to CIP. In response to Member’s questions the Strategic Director and Executive Councillor for Housing said the following: i. Agreed it was unfortunate the YMCA Trinity had been withdrawn from the development. ii. A significant number of viability assessments had been undertaken and believed the plans for both phase 1 and 2 was the best approach for the development. iii. Phase 2 would allow the Council to deliver an additional 20 council houses on the site which was a welcome contribution. iv. The site had been developed in line with the sustainable housing guide, as were all Council build programmes. v. There were a number of factors that contributed to the cost of development of affordable housing on site and why the Council choose to maintain 50% of affordable housing on site: · For the scheme to be viable and to be deliverable, subsidies from the sale of private housing were needed to contribute to affordable housing · The higher the number of affordable housing the bigger the impact on the funding available. · When clustering high levels of affordable housing on site, there was a need to consider whether it could be supported from a community and sociable point of view to have increased levels of affordable housing in one place, such as at the front of the site. · To increase the number of council homes would unfortunately decrease the value of the individual market units. It was not simply a case of requiring additional funding to increase the number of council houses. An additional increase would decrease the income gained from the sale of the private houses, thus losing income. vi. Many developments in the City had less than 40% affordable housing on site, therefore 50% was an achievement the Council should be proud of. vii. The Council planned to purchase 20 of the market units for sub market rent; the level of rent had not yet been agreed. viii. Phase 2 would deliver in perpetuity council owned community facility which would be at the front of the site. ix. It had been proposed to have one larger community facility shared by the Cromwell Road and Mill Road development, located in the centre of the two, within a 15 minute walk. x. Possible community space available in the evenings for community activity on the Cromwell Road development. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor for Housing and the Executive Councillor for Finance and Resources approved the recommendations.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

1.1A core objective for Cambridge City Council is tackling the housing crisis in Cambridge. As the main provider of social and affordable

Report page no. 1 Agenda page no. housing in Cambridge, the Council has established a new build programme to:

a) Provide additional social housing to meet housing needs in Cambridge and replace social housing lost through Right to Buy.

b) Replace existing council social housing that no longer meets current standards or is becoming less popular with residents due to factors relating to space and the impact of fuel poverty.

c) Build new house types that will better meet the overall mix of future Affordable Housing needs.

d) Improve the energy efficiency of the Council’s housing stock.

1.2The Devolution Programme was agreed as part of the Cambridgeshire and Peterborough devolution settlement in 2016/17. The settlement included allocation of £70 million to build 500 new affordable homes within the City of Cambridge starting on site within a 5 year period between April 2017 and March 2022. The deal also includes match funding utilising Council Right to Buy Receipts and other Council resources to provide a total funding envelope of approximately £100 million. 1.3 The programme for delivery of these homes will focus on Council rented homes (defined locally as rents at no greater than Local Housing Allowance levels). The new housing stock will be owned and managed through the Council’s Housing Revenue Account (HRA) and will be let as secure local authority tenancies.

1.4In 2015 the Executive Councillor for Finance & Resources approved the preparation of a strategic development brief for the Mill Road Depot site for the delivery of housing. In January 2016 the Executive Councillor approved the General Fund development programme - a ten year programme identifying potential sites for development which present investment opportunities for the General Fund. Mill Road Depot is the largest development site in the programme.

1.5In 2016 the Strategy and Resources Scrutiny Committee approved setting up the Cambridge Investment Partnership (CIP) as a

Report page no. 2 Agenda page no. mechanism for the Council to bring forward assets for development including sites for the delivery of new homes. The CIP was established in January 2017. The partnership brings with it the advantage of the experience and resources of the development partners which is beneficial on large and complex sites such as the Mill Rd Depot site.

1.6The principles governing the approvals process for sites which are developed with CIP were approved at Strategy & Resources Scrutiny Committee on 9th October 2017 and are set out in Appendix 4. Mill Road Depot is the first General Fund asset to be developed using these approved principles.

1.7The CIP Investment Team developed a Project Plan for the site which was approved by CIP Board on 3rd November 2017. The Project Plan incorporates a strategic development brief which meets the Council’s key objectives for the site and which were identified following public consultation during 2015. The brief for the site which was agreed in March 2017.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic Development of Mill Road Depot SiteReport 653 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, apologies
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
NM
Councillor Nicky MasseyCommittee Member, apologies
CM
Councillor Colin McGertyCommittee Member, present
CO
Carina O’ReillyCommittee Member, present as substitute
CP
Councillor Cheney PayneCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present

All 17 on the meeting page

On this subject at Cambridge

Search all
  1. Strategic Development of Mill Road Depot SiteThis decision
  2. Strategic Site Development of Park Street Car ParkApproved
  3. Strategic Site Development of Mill Road DepotAgreed
  4. CB1 Station Area Redevelopment - Discharge of Strategic Condition 48 - Detailed Scheme for Alterations to Station Road/Southern Access Road JunctionRefused
  5. Cb1 station area redevelopment - discharge of strategic planning condition 7 - site wide public realm and landscape strategyDecided
  6. Cb1 station area redevelopment - discharge of strategic planning condition 24 – site wide ecological conservation management planDecided

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies