Decision This report provided an up-date on the sites in the Council’s New Build Housing Programme – whether recently completed; under construction or being assessed in terms of feasibility and viability for development. The latter is known as the Rolling Programme. Decision of Executive Councillor for Housing The Executive Councillor noted the up-dated position of schemes. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Director (Fiona Bryant). The Committee made the following comments in response to the report: i. Sought clarification regarding the status of funding if projects were suspended. ii. Sought clarity on staffing structures and the differing roles of the two Strategic Directors. The Strategic Director said the following in response to Members’ questions: i. Clarified the term windfall sites as being sites not currently in council ownership which could be brought forward for development in partnership with other parties. ii. Confirmed that scheme proposals moved on an off the list. Funding for suspended schemes was retained in the central pot. The Committee and the Executive Councillor noted the report.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
This report provides an up-date on the sites in the Council’s New Build Housing Programme – whether recently completed; under construction or being assessed in terms of feasibility and viability for development. The latter is known as the Rolling Programme.
2. Recommendations The Executive Councillor is recommended to note the up-dated position of schemes.
Table 1 provides details of the schemes which have been completed since the last Housing Scrutiny Committee in June 2017. A total of 134 Social Housing and Shared Ownership Units were completed and handed over to Cambridge City Council in the period between June and 30th November 2017.
Table 1 Contractor Date Social Percentage Comments Schemes Completed Housing / Social SO Units Housing on Site Water Lane Keepmoat September 14 61% Scheme in (Jolley Ford 2017 defects Court) period
Clay Farm Hills June – 104 50% Scheme in (Virido) October defects 2017 period
Ekin Road Keepmoat October 6 100% Scheme in (Ekin 2017 defects Close) period TOTAL 124 new Units
3.2Schemes Under Construction
A number of schemes that were reported to HSC June 2017 as “schemes in progress”, remain under construction and are currently being progressed towards completion.
Table 2 provides details of these schemes which, once completed and handed over, will provide an additional 79 Social Housing and Shared Ownership Units.
Table 2 Contractor Expected Social Percentage Comments Schemes Completion Housing / Social Date SO Units Housing on Site
Fulbourn Keepmoat January 8 100% Preparing for Road 2018 handover by February 2018 based on current programme
Ditchburn Cocksedge September 51 total 100% Refurbishment Place 2019 refurbished project of of which 6 existing are facilities and replacements new build TOTAL 68
3.21Keepmoat Programme
The sites which are part of the Keepmoat programme of delivery are expected to be completed by the end of February 2018. The HDA team is holding weekly programme review meetings with Keepmoat to review progress against Keepmoat’s Completions Programme and to discuss any particularly challenging site issues. The HDA team is being supported by the team from AECOM, Cambridge City Council’s appointed Cost Consultants. The team at City Homes is being updated regularly to ensure all stakeholders are receiving timely communications regarding progress.
3.22Ditchburn Place Refurbishment Scheme
The contract for the refurbishment work is split into 5 phases with Phase 1 of the contract works tendered as a fixed price; this phase of the work started on site in April 2017 and is due to be completed in April 2018. The works which will be completed as Phase 1 works include the provision of 6 new build flats which will replace the 6 flats lost as a consequence of the remodeling and refurbishment work The remaining Phases 2-5 have been covered by provisional sums which are yet to be formally instructed under the contract. The full scheme is due to be completed and handed over in September 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.