Cabinet Report: Update on New Build Council Housing Delivery July 2025
1 Background and key updates 1.1 This is a regular quarterly report showing progress on the City Council’s housing delivery and development programme. 1.2 1145 new homes have been completed across 28 sites under the City Council programmes, with 690 being net new Council homes, 24 of which acquisitions of existing market stock. 1.3 Since the last update five schemes have started on site, Including Fanshawe Road (45 council and 39 market), ATS/Murketts (28 council and 42 market), Newbury Farm (60 council and 90 market) and East Barnwell (120 council). All above schemes are being delivered through the Cambridge Investment Partnership (CIP). At Kendal Way, groundworks have commenced through a directly tendered contract. 1.4 Following announcement of bridge funding between Affordable Housing CME Programmes, a funding submission of c £1m has been made to Homes England for 11 eligible homes at Fanshawe Road. 1.5 Hoarding has been completed around Stanton House, ahead of demolition works targeted for August 2025
2 Delivery programme 2.1 The current delivery programme confirms: 2.2 the 500 devolution programme, consisting of 931 (including market sale) homes, of which 537 are net new affordable homes. 2.2.1 Final handovers are two blocks at the Meadows (56 council) and one accessible home at Kendal Way. 2.2.2 Refer Appendix 2 for detailed programme Information.
2.3the 10-year New Homes Programme, consisting of 1172 homes with scheme approval. These include: 2.3.1 Schemes on site: 433 (253 council homes), as listed in 1.3 above. 2.3.2 Schemes Approved and in the planning process. Subject to final design and review ahead of formal planning submissions, this is made up of: Hanover and Princess (138 (82 council); Ekin Rd (131 (64 council); Davy Rd (90 (45 council); Stanton House (29 council); Paget Rd (4 council); Eddeva Park (32 council); 2.3.3 4 market acquisitions for Refugee and Temporary accommodation use are included in the programme, with 3 purchases now complete and 1 remaining which is proceeding through Legal process.
3 Programme Pipeline 3.1 Cambridge North Framework for Change 3.1.1 Consultation has finished and a cabinet report for October 2025 is planned following briefings Ward Councillors, senior Officers and Cabinet members. The report will outline the recommendations for the next steps, including potential investment. 3.2 Given the ongoing financial pressures with the HRA, officers continue to review opportunities and constraints around funding models for affordable housing, as well alternatives to market sale housing including Build to Rent and Co-Living. 3.3 Officers are continuing to develop a pipeline programme in anticipation of a bid to Homes England to secure funding from the Affordable Homes Programme (AHP). Appendix 3 outlines the current working Programme Portfolio and Delivery targets to 2032.
4 Homes England Update 4.1 Eamon Boyle, interim CEO of Homes England has stated that the prospectus for the new Affordable Homes Programme will be, at the earliest, available in September 2025 with bidding open by the end of the calendar year. Homes England have indicated that funding will be via the Cambridge and Peterborough Combined Authority (CPCA), with a specific focus on social rents. 4.2 Preparation for a Strategic Partnership bid has started and officers are working with the CPCA and Homes England.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 12c. 20250715 Cabinet: Appendix 1 (Programme): New Build Update /21/CabaAppendix | 393 KB | Download |
PDF |
Item 12c. 20250715 Cabinet: Appendix 2 (Scheme Details): New Build Update /21/CabaAppendix | 746 KB | Download |
PDF |
Item 12c. 20250715 Cabinet: Appendix 3 (Portfolio): New Build Update /21/CabaAppendix | 457 KB | Download |
PDF |
Item 12c. 20250715 Cabinet: Appendix 4 (Risk Register): New Build Update /21/CabaAppendix | 226 KB | Download |
PDF |
New Build UpdateReport | 118 KB | DownloadRead as text |
Follow Cabinet at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jul 2026 | Greater Cambridge Local Plan: Proposed Submission (Regulation 19) publicationAgreed the Proposed Submission Greater Cambridge Local Plan (Regulation 19) (Appendix A), and Proposed Submission Pol... | Agreed | Open |
| 7 Jul 2026 | Homelessness and Rough Sleeping Strategy 2021 – 2028Agreed that homelessness was a complex area, covering statutory duties and a range of support services. Confirmed tra... | Agreed | Open |
| 24 Mar 2026 | Consultation on the establishment of a centrally led Urban Development Corporation for Greater CambridgeAgreed that the main concerns related to the proposed removal of plan‑making and development‑management powers and re... | Agreed | Open |
| 24 Mar 2026 | Local Nature Reserve Designations in Cherry HintonAgreed that creating biodiversity corridors was essential and had agreed to speak residents in Coleridge ward about l... | Agreed | Open |
| 25 Nov 2025 | Suspension of Standing OrdersResolved by Cambridge City Council Cabinet Members. i. To suspend it’s standing orders for the duration of the meetin... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.