Conversion of Ditchburn Day Centre

Approved Scrutiny 1 paper

Housing Scrutiny Committee approved this item on Thursday 27 September 2018. Below is the council's own wording, with the papers it was decided on.

Item18/43/HSC

Resolved

Decision of Executive Councilor for Housing i. Approved inclusion of a capital budget of £125,000 to meet the land acquisition costs, recognising the transaction was carried out under delegated authority earlier in 2018/19. ii. Approved the indicative capital budget for the conversion of £207,000 to cover all of the construction costs, professional fees and associated fees to deliver the extra units. iii. Approved the addition of the works to create the 2 units to the existing build contract with Cocksedge Building Contractors Ltd. This contractor was currently on site working on the larger refurbishment scheme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Development Manager, Housing Development Agency. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor for Housing approved the recommendations.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

1.1This report proposes the conversion of Ditchburn Place day centre into 2No. one bedroom self-contained sheltered accommodation flats. This possibility to provide two additional affordable rented units has arisen because Cambridgeshire County Council has returned the unused day centre to the City Council. The 2 units will be in addition to the current 51 unit refurbishment of Ditchburn Place.

1.2The report also requests approval for a capital budget for the HRA and Devolution grant expenditure covering costs for their conversion

Recommendations

The Executive Councillor is recommended to:

Report page no. 1 Agenda page no. 2.1 Note the indicative mix of the proposed scheme to include:

2No. One Bedroom Flats

2.2Approve inclusion of a capital budget of £125,000 to meet the land acquisition costs, recognising the transaction was carried out under delegated authority earlier in 2018/19.

2.3Approve the indicative capital budget for the conversion of £207,000 to cover all of the construction costs, professional fees and associated fees to deliver the extra units

2.4Approve the addition of the works to create the 2 units to the existing build contract with Cocksedge Building Contractors Ltd This contractor is currently on site working on the larger refurbishment scheme

Background

3.1The Day Centre was originally leased on a long lease to Cambridgeshire County Council at a peppercorn rent with a side management agreement that allowed Cambridge City Council to recover management and service costs only. Following a review of their Day Centre Provision in 2015, the County Council took the decision to move the service users to other local day centres and close the service at Ditchburn Place. 3.2 The area has remained unoccupied since then and following negotiations with Cambridgeshire County Council, the lease has now been surrendered and the area handed back to Cambridge City Council. 3.3 The architect working on the current Ditchburn Place refurbishment has advised that the area is sufficient to create 2 additional one bedroom flats that would form part of the main building at Ditchburn Place. The provision of these two additional units of affordable housing is welcomed and any increase in units in an extra care scheme will make the delivery of care more financially viable for a prospective care provider as there will be

Report page no. 2 Agenda page no. more residents to share the fixed costs associated with managing a care scheme and providing a 24 hour presence 3.4 In view of the closure of the Day Centre and the need for additional extra care housing it is proposed that this would be the best use of space for that section of the building.

4. Site Details

Appendix 1 Shows the Location plan for the Ditchburn Place. Appendix 2 Shows the Layout as existing showing area to be converted to provide 2 additional units.

5. Implications

Financial implications

The total capital budget required is £332,000. This comprises £125,000 in land acquisition costs to terminate the lease of the day centre to the County Council and an indicative capital budget for the conversion to two new homes of £207,000.

The indicative budgets provided above are fully inclusive of works costs and all associated professional fees. As conversion is subject to planning application, the costs presented for this scheme are indicative.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Conversion of Ditchburn Day CentreReport 574 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, apologies
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
NM
Councillor Nicky MasseyCommittee Member, apologies
CM
Councillor Colin McGertyCommittee Member, present
CO
Carina O’ReillyCommittee Member, present as substitute
CP
Councillor Cheney PayneCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present

All 17 on the meeting page

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open