Estates & Facilities Service Review and Compliance Update

Noted Scrutiny 1 paper

Housing Scrutiny Committee noted this item on Thursday 24 September 2020. Below is the council's own wording, with the papers it was decided on.

Item20/31/HSC

Resolved

Decision The report provided an update on the Estates & Facilities Service Review and information on compliance related work within the service, including a summary on gas servicing, electrical testing, recent audit actions and fire safety. Decision of Executive Councillor for Housing i. Noted the progress of the service review and compliance related work detailed within the officer’s report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Maintenance and Assets The Committee made the following comments in response to the report: i. Noted the importance of the programme in relation to fire door installation and noted that Housing Associations were also doing electrical testing, so everyone was in the same position regarding tenant works following the covid-19 lockdown. ii. Noted that some leaseholders had replaced their front doors themselves which may have been compliant with fire regulations at the time they were installed and queried whether these would be ok or if they would need to be replaced. iii. Asked whether priority was being given to those tenants who had previously been required to shield to undertake their outstanding gas servicing. iv. Asked if leaseholders refused to upgrade their fire doors would that adversely affect/negate their contents insurance. v. Asked whether the fire safety works would be completed on time given the delays incurred as a result of lockdown and asked whether a wider pool of contractors were required in order to get the works completed on time. The Head of Housing Maintenance and Assets said the following in response to Members’ questions: i. Leaseholders had been contacted regarding fire door replacements and they had the ability to be able to order a replacement as part of the programme if they wanted. 12% of leaseholders had asked for a quote and 20% of leaseholders had said that they did not require a quotation. Once the details of the new Fire Safety Bill have been approved we will be in a better position to understand the changes to requirements and enforcement powers. ii. There were 87 people who required a gas service. The Council did not hold information about whether these tenants have a requirement to shield or self-isolate and officers were contacting all residents to try and work through the outstanding services and arrange an appointment. Officers were working to Government guidance and would make every effort to be able to access properties and would keep records / risk assessments if they were unable to gain access to a property. iii. Officers agreed to investigate what the position would be if leaseholders refused to upgrade their fire doors and the impact on their insurance. iv. Confirmed that works were programmed until March 2021 and the current contractors had indicated they have capacity to undertake the fire safety work and any delays would be because of either a further lockdown or the ability to be able to access properties. The Committee resolved unanimously to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Item Estates & Facilities Service Review and Compliance Update To:

Councillor Richard Johnson, Executive Councillor for Housing Housing Scrutiny Committee 24 September 2020 Report by: Lynn Thomas, Head of Housing Maintenance and Assets Tel: 01223 457831 Email: [email protected] Wards affected: All Wards

This report is for information and not for decision. 1. Executive Summary

The report provides an update on the Estates & Facilities Service Review and information on compliance related work within the service, including a summary on gas servicing, electrical testing, recent audit actions and fire safety. 2. Recommendations

The Executive Councillor is recommended to note the progress of the service review and compliance related work detailed within the report.

3. E&F Service Review Update

This is a further to that provided during the last Housing Scrutiny Committee.

The service review has consisted of more than the restructure of staff, we identified 6 themes from a series of consultation and work shop events with the staff within the service, tenants reps, and colleagues across the

Report page no. 1 Agenda page no. organisation that we work closely with, based around the 4 guiding principles of:  Customers  Business  Value  Risk

These themes were:

 Structure  Responsibility and Accountability  Efficiency & Effectiveness  Performance Management  Risk Management  Communication and Engagement

Within these themes we identified action plans to achieve the transformation required within our service delivery and behavioral and cultural change of staff to achieve the improvements within the service in the six identified themes that underpins my mission for the service, “To be a customer focused and business-like Estates & Facilities Service that manages and maintains the Council’s housing stock and other buildings in a safe, efficient and financially sustainable manner.” There have been 74 actions identified, me and the Estates & Facilities Service Managers have been working on these actions during the past year and so far we have completed 52% of them.

The staffing restructure proposed and consulted earlier this year which provided staff with the opportunity to comment and give feedback has received the necessary approvals for implementation and the restructure is now in progress in line with the published implementation paper. We have a phased approach to the recruitment of new and vacant posts and recruitment to several posts are already in progress. Where required the notice of redundancy has been issued to those staff affected and appropriate support is being given.

4. Compliance Progress report

4.1Gas Servicing

Mears are contracted to complete our gas servicing and maintenance. The table below shows their performance since January 2020 and prior to January they have constantly achieved 100% compliance. From the month of

Report page no. 2 Agenda page no. April includes the change of approach for gaining access in line with the Covid-19 Guidance issued to take in consideration those tenants that were self-isolating and shielding. Now that the shielding has been paused by the Government, we are planning to return to our usual approach in obtaining access for gas servicing and in the process of designing the communication to be issued to tenants with Mears.

Jan Feb Mar Apr May June July 20 20 20 20 20 20 20 Services 686 803 642 605 625 781 851 completed service 100% 100% 100% 99% 99% 99% 99% compliance overdue 0 0 0 2 56 74 56 within month

4.2Electrical Testing

All properties that are planned for electrical testing this financial year have been ordered with our contractor TSG Building Services. Due to Coronavirus the start of work was postponed until 1/8/20. Work has now started on site but it is too early to supply performance figures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Estates & Facilities Service Review and Compliance UpdateReport 391 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 15 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, present
GH
Councillor Grace HadleyCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
CM
Councillor Colin McGertyCommittee Member, present
AM
Councillor Anthony MartinelliCommittee Member, present
KP
Councillor Katie PorrerCommittee Member, present
RJ
Councillor Richard JohnsonExecutive Councillor, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
CA
Christabella Amiteye Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. Estates & Facilities Service Review and Compliance UpdateThis decision
  2. Estates & Facilities Compliance UpdateNoted
  3. Estates & Facilities Compliance DataRefused
  4. Estates & Facilities Compliance DataRefused
  5. Estates & Facilities Compliance DataNoted
  6. Estates & Facilities Service Review and Compliance UpdateNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies