Decision This report provides an update on the programme to deliver 500 Council homes with funding from the Combined Authority. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the Combined Authority programme. ii. Noted the funding structure for the Combined Authority programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Development. The Committee made the following comments in response to the report: i. There was usually a shortage of accessible homes so they were pleased that 5% of houses would be accessible homes. The Committee resolved by 5 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the programme to deliver 500 Council homes with funding from the Combined Authority.
1.280 Homes have now been completed across 8 sites under the City Council programme. 27 of these have replaced homes demolished to accommodate redevelopment, with the further 53 being net new Council homes.
1.3The Council currently has 270 Council rented homes being built on site, with a further 193 starts expected by the 2020/21 financial year end.
1.4542 new Council homes have now gained Planning Approval, reaching and exceeding the goal of 500 homes target as part of the devolution deal.
Report page no. 1 Agenda page no. 1.5 Recovery from the delays caused by Covid -19 pandemic has been swift, and programme timeline is an average one month behind original scheduled dates. Social distancing requirements on sites remain in place as well as outbreak planning for individual sites.
1.6The modular housing programme has progressed to planning submission on three sites, and the Council is currently in the process of selecting a charity partner who will take on the ownership and housing management of the modular homes.
Recommendations
The Executive Councillor is recommended to:
2.1Note the continued progress on the delivery of the Combined Authority programme.
2.2Note the funding structure for the Combined Authority programme.
Background
3.1This is a quarterly report showing progress against the Combined Authority target of 500 Council rented homes.
4. Combined Authority
4.1The Council’s housing programme is part funded by a £70million grant to date this has been paid via the Cambridgeshire & Peterborough Combined Authority in arrears.
4.2Quarterly grant claims are made in arrears against the Devolution funding to the Combined Authority. There is £53,000,000 to be claimed from the Combined Authority with £30,434,354 claimed to date. A further £17,000,000 has been paid directly to the City Council from MHCLG for 2020/21, with £956,695 of this invested to date. Cambridge City Council utilized £1,913,389 of funding in respect of the first quarter
Report page no. 2 Agenda page no. of 2020/21, with £5,477,048 anticipated to be drawn down/utilized in respect of the second quarter.
4.3To date Cambridge City Council has drawn down/ utilized £31,391,049 of Devolution funding, with the remaining £38,608,951 due to be drawn down/utilized by financial year end 2022/23.
4.4A review with MHCLG and the Combined Authority to report progress was held on 8th September 2020.
5. Delivery Programme
5.1The delivery programme provided in June 2020 confirmed that the devolution programme consisted of 546 Council Homes- this figure has not changed.
5.2Appendix 1 shows the current programme, which shows the total market housing provided as well as the net gain of Council homes. Appendix 2 shows the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.
6. Profile of Start on Sites
6.1The start on site profile for the 500 devolution programme is shown in table 2. This is based on all the named schemes being delivered.
6.2The total starts on site stands at 323, or 65% of the total programme. For the current 2020/21 financial year, the first starts on site are currently scheduled for October 2020 (99 new dwellings over two schemes)
6.3As below, the overall programme shows an outturn of 546 new homes commencing construction by March 2022.
Report page no. 3 Agenda page no. Table 2: Start on Site Forecast Profile
Progress to 500 starts on site 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 Starts by year 2 132 189 193 28 0 Cumulative total 2 134 323 516 546 546
7. Scheme details
7.1Schemes Completed: Net gain 53 homes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.