Decision The Officer’s report brought forward proposals for 35 dwellings across five sites as a first step in delivering homes on Passivhaus principles. Decision of Executive Councillor for Housing i. Approved new build housing schemes a. at Ditton Walk. b. at 71-73 Fen Road. c. at Aragon Close. d. at Sackville Close. e. at Borrowdale. ii. Approved the capital budget as set out in the Officer’s report for the package of Passivhaus schemes noting that this will be reduced should any of the five sites not proceed. iii. Authorised the Strategic Director in consultation with the Executive Councillor for Housing to approve variations to the schemes, including the number of units and mix of property types and sizes outlined in the Officer’s report. iv. Subject to Council approval of the budget, approved the development to be carried out through the Cambridge Investment Partnership (CIP) subject to a value for money assessment to be carried out on behalf of the Council. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Senior Housing Development Manager. The Senior Housing Development Manager said the following in response to Members’ questions: i. Allocated disabled parking was available. ii. There was a lot of misinformation around what the City Council planned for the Fen Road site, it was hoped the Officer’s report addressed this. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1On 24 September 2020 the Executive Counsellor approved a new housing programme following scrutiny in public at Housing Scrutiny Committee. The proposed programme includes a strong commitment to increased sustainability standards in support of the Council’s commitment on climate change. The costs in the financial appraisal to support that decision were based on the introduction of Passivhaus principles in construction.
1.2This commitment to enhanced sustainability standards for the new programme is outlined in the previous Housing Scrutiny Committee report (Item 13) at this meeting. Following the recommendations of Buro Happold, the first step towards Net Zero Carbon is to undertake a Passivhaus pilot scheme to learn and develop the approach to sustainability in the new programme.
1.3This report brings forward proposals for 35 dwellings across five sites as a first step in delivering homes on Passivhaus principles. This is an
Report page no. 1 Agenda page no. important pilot project to further the Council’s understanding of Passivhaus development by bringing forward developments focussed on developing standard house types which have been informed from the outset by Passivhaus principles.
1.4The sites included in the package are:
o Ditton Walk - infill site at gardens of 129-131 Ditton Fields – the homes will face Ditton Walk and this will be the short scheme title (Abbey Ward) - 6 houses. o 71-73 Fen Road - replacing two existing buildings previously providing shared accommodation for people with learning disabilities) (East Chesterton Ward) - 12 houses including 2 larger wheelchair accessible houses. o Aragon Close – garage and parking site (Kings Hedges Ward) - 7 houses. o Sackville Close – garage and parking site (Kings Hedges Ward) - 7 houses. o Borrowdale - garage and parking site (Arbury Ward) – 3 houses.
1.5The schemes are indicative and subject to further review during pre- application planning consultation.
1.6The total indicative works cost is currently estimated at £10,151,413 including pre- and post-planning statutory fees, professional consultant fees, survey and site investigation costs, demolition and construction costs, other associated costs and HDA fees. (Land assembly costs of £761,972 have already been incurred at 71-73 Fen Road and 129 -131 Ditton Fields.)
1.7The breakdown of costs including land assembly across the sites is as follows:
Aragon Sackville HSC Budget Fen Road Ditton Walk Borrowdale TOTAL Close Close Design & Works £3,657,449 £1,918,233 £1,850,494 £1,850,494 £874,742 £10,151,413 Costs Land assembly £596,350 £169,650 £0 £0 £0 £761,972.46 TOTAL £4,253,799 £2,087,883 £1,850,494 £1,850,494 £874,742 £10,913,385
2.1To approve a new build housing scheme at Ditton Walk.
2.2To approve a new build housing scheme at 71-73 Fen Road.
2.3To approve a new build housing scheme at Aragon Close.
2.4To approve a new build housing scheme at Sackville Close.
2.5To approve a new build housing scheme at Borrowdale.
2.6To approve the capital budget as set out in this report for the package of Passivhaus schemes noting that this will be reduced should any of the five sites not proceed.
2.7Authorise the Strategic Director in consultation with the Executive Councillor for Housing to approve variations to the schemes, including the number of units and mix of property types and sizes outlined in this report.
2.8Subject to Council approval of the budget, approve the development to be carried out through the Cambridge Investment Partnership (CIP) subject to a value for money assessment to be carried out on behalf of the Council.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.