Housing Scrutiny Committee, Tuesday 19 January 2021 at 5.00pm

Structural Repairs and Associated Works to Council-Owned Blocks of Flats

Approved Scrutiny 1 paper

Housing Scrutiny Committee approved this item on Tuesday 19 January 2021. Below is the council's own wording, with the papers it was decided on.

Item21/6/HSC

Resolved

Decision The Council owns a number of blocks of flats built in the 1950s and 1960s. Many of these flats have structural concrete elements. Further to a report submitted to Housing Scrutiny Committee in January 2020, Estates and Facilities have been surveying blocks of flats that have three stories or more and a further list of properties where structural repair work is required has been identified. Detail designs were underway, and the work needed to be tendered in order to award a contract(s) to a building contractor. Decision of Executive Councillor for Housing Approved the issue of tenders and, following evaluation of tenders, authorised the Strategic Director (following consultation with Executive Councillor, Chair, Vice Chair and Spokes of the Committee) to award a contract(s) to a contractor(s) to carry out structural repairs and associated repair works to Council housing flats. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Asset Manager. The Asset Manager said the following in response to Members’ questions: i. There would be no climate change impact from the repair work, it was making good what was already in place. ii. Other programs of work in the housing capital program may have a more positive impact in reducing climate change. Councillor Todd-Jones said work would lead to more energy efficient buildings. iii. Stakeholders were being consulted about repairs, the council would listen to resident’s wishes about whether they would like repairs to be undertaken or not. Officers would be mindful of the impact of repairs (eg noise) as people stayed at home due to covid lockdown. iv. The budget provision for work was already set out in the Council’s 30 year plan. If committee members wished to scrutinise progress of the contract process then a report could be brought back to Housing Scrutiny Committee. Councillor Robertson said processes were in place for officers to oversee the contract process if/once delegation was given. The Strategic Director said a general capital program delivery report could be brought to committee, but not one for individual projects. Diane Best requested a change to the recommendation in the Officer’s report (amendment shown as bold text): Approved the issue of tenders and, following evaluation of tenders, authorised the Strategic Director (following consultation with Executive Councillor, Chair, Vice Chair and Spokes of the Committee) to award a contract(s) to a contractor(s) to carry out structural repairs and associated repair works to Council housing flats. The Committee unanimously approved this amended recommendation. The Committee unanimously resolved to endorse the recommendation as amended. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Item PROCUREMENT OF CONTRACT TO CARRY OUT STRUCTURAL REPAIRS TO COUNCIL BLOCKS OF FLATS - 2021

To: Councillor Richard Johnson, Executive Councillor for Housing Housing Scrutiny Committee 19/01/21 Report by: Lynn Thomas, Head of Housing Maintenance and Assets Tel: 01223 - 457831 Email: [email protected] Wards affected: Arbury, Trumpington, Coleridge

Key Decision 1. Executive Summary The Council owns a number of blocks of flats built in the 1950s and 1960s. Many of these flats have structural concrete elements. Further to a report submitted to Housing Scrutiny Committee in January 2020, Estates and Facilities have been surveying blocks of flats that have three stories or more and a further list of properties where structural repair work is required has been identified. Details designs are underway, and the work now needs to be tendered in order to award a contract(s) to a building contractor.

Report page no. 1 Agenda page no. 2. Recommendations The Executive Councillor is recommended to:

Approve the issue of tenders and, following evaluation of tenders, authorise the Strategic Director (following consultation with Executive Councillor, Chair and Spokes of the Committee) to award a contract(s) to a contractor(s) to carry out structural repairs and associated repair works to Council housing flats.

3. Background Estates and Facilities have been identifying and surveying blocks of flats built in the 1950s and 1960s to identify where repair work is required.

A report was submitted to committee in January 2020 covering works to maisonettes and flats at Hawkins Road, Ekin Road and flats above shops in Colville Road. This work has been procured and is due to be completed in summer 2021 (N.B. Colville Road has been omitted from the programme as it is to be redeveloped.)

A further programme of work is now being developed at blocks of flats including Hanover Court, Princess Court, Cockerel Road, Rutland Close, Brackley Close, Fordwich Close, Perse Way, Fanshaw Road, and Davy Road.

The Council has engaged design and project management consultants (Mace) to carry out detailed structural surveys and produce a specification for the works. This will include invasive surveys concrete testing and drainage surveys.

As the value of the proposed work is estimated to be more than £1,000,000 the tender and award of a contract is a key decision.

3.1Details of proposed work

Hanover Court and Princess Court The proposed work is:  Masonry repairs  Completion of concrete repairs to balcony beams  Replacement of metal screens to balconies  Re-routing of downpipes and alterations to drainage  Upgrade handrails and roof protection

Report page no. 2 Agenda page no.  Safety upgrades to communal staircases and landing balustrades  Drainage repairs  Minor roofing works and bin chute alterations  Fire compartment improvements between flats and service risers (potential)  Landlord electrical supply replacement (potential)

The masonry and concrete repairs are a continuation of work that was started in 2018/19. Due to the nature of this repair work and the fact the blocks are five and eight stories high, additional work came to light that had not been identified at the start of the last project. These repairs have been left in a safe condition but have not been fully completed.

3.2South Arbury Maisonettes and flats These maisonettes and flats were built in the early to mid-1960’s and consist various configurations for flats and maisonettes in three and four storey blocks.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Structural Repairs and Associated Works to Council-Owned Blocks of FlatsReport 244 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 15 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, present
GH
Councillor Grace HadleyCommittee Member, present
CM
Councillor Colin McGertyCommittee Member, present
AM
Councillor Anthony MartinelliCommittee Member, present
KP
Councillor Katie PorrerCommittee Member, present
RR
Councillor Richard RobertsonCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
RJ
Councillor Richard JohnsonExecutive Councillor, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
CA
Christabella Amiteye Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. Structural Repairs and Associated Works to Council-Owned Blocks of FlatsThis decision
  2. Structural repairs and associated works at Bermuda Terrace flats – 2025Approved
  3. Structural Repairs and Associated Works to Council-Owned Blocks of FlatsApproved

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies