Decision The report proposed a procurement to award a contract(s) for compliance-based activities. This includes gas servicing and maintenance, servicing including (but not limited to) electrical testing, fire safety asset servicing, water hygiene. The contracts are for up to four years, four months with an option to extend for one or more periods up to a maximum extension of three years. Decision of Executive Councillor for Strategy and External Partnerships Agreed to amalgamate the aforementioned contracts (paragraph 1, Executive Summary of the report) into a single procurement exercise and delegate authority to the Strategic Director (in consultation with Executive Councillor, Chair and Vice Chair of the Housing Scrutiny Committee and spokespersons) to award either a single contractor, or multiple contracts for Compliance Delivery areas. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee welcomed the report. The Committee resolved by 15 votes to 0 to endorse the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Item Procurement of Compliance Contractor 2022-2028 Update To: Councillor Mike Todd-Jones Executive Councillor for Housing Housing Scrutiny Committee 22nd June 2021 Report by: Lynn Thomas, Head of Housing Maintenance and Assets Tel: 01223 457831 Email: [email protected] Wards affected: All Wards
This report is for decision. 1. Executive Summary
The report seeks a decision to approve the issue of tenders and authorise the Strategic Director (following consultation with Executive Councillor, Chair and Spokes of the Committee and elected tenant spokes) to award a contract(s) to a contractor or multiple contractors to carry out Compliance-based activities. These activities include the re-procurement of the Gas Servicing and Maintenance Contract which is currently being delivered by Mears Group, as well as servicing areas currently incorporated in the TSG contract including (but not limited to) Electrical Testing, Fire Safety Asset Servicing and the Water Hygiene contract currently delivered by Veolia. The contracts are proposed to be for a period of up to 4 years and 4 months, with an option to extend for one or more periods up to a maximum extension of 3 years. 2. Recommendations
The Executive Councillor is recommended to approve the decision to amalgamate the aforementioned contracts into a single procurement exercise and authorise the Strategic Director (following consultation with Executive Councillor, Chair and Spokes of the Committee and elected tenant spokes) to award either a single contractor, or multiple contracts for Compliance Delivery areas.
Report page no. 1 Agenda page no. 3. A New Approach to Compliance
Following the E&F Service Review conducted in 2020 a new Risk Assurance and Compliance Team (RACT) was formed. This team is made up of a Risk Assurance and Compliance Manager (Interim), Asbestos Officer (FTC), M&E Compliance Programme Manager (Vacant), Fire Risk Assessor and Advisor, Assistant Surveyor, Compliance Officer.
The Mears contract was extended in March 2020 until 22nd November 2022 which is also the date that the TSG contract is expected to end, the Veolia contract has ended and the Council are currently operating this contract on a rolling monthly arrangement. The existing contracts were procured before the Service Review and the servicing contracts were previously delivered by the Operations Team (Gas Servicing) and Asset Team (TSG and Veolia); with the formation of the new Compliance and Risk Team the opportunity has arisen to rationalise the contracts and one part of that is amalgamating the compliance servicing and maintenance contracts into a single broad-scope contract which will allow the Compliance and Risk Team to manage the contract easier whilst also removing the burden of Contract Management from other teams within Estates and Facilities.
As part of the new contract it is proposed that “call-off” options will also be procured, these options will include services for future ‘greener’ heating systems such as air-source heat pumps, electric car charging point servicing and maintenance and battery storage technology provisions. Given the Council’s commitment to greener technologies, the ban on new gas boiler installations in new build properties by 2030, the ban on the sale of new petrol and diesel cars also by 2030, and Central Government’s carbon- neutral targets it is foreseen that these technologies will become increasingly prominent within the recommended life of the contract and therefore need to be included to ensure the Council is well placed to manage the transition from fossil fuels to electric and other more environmentally friendly alternatives.
4. Contract Services
The proposed works/services to be included within the new contracts are as follows:
Compliance Activity Domestic Gas Boiler Servicing & Maintenance Commercial Gas Boiler Servicing & Maintenance
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.