Decision This report provided an update on the housing development programme . Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the approved housing programme. ii. Noted the updated 2021 Sustainable Housing Design Guide, to include the recommendations approved in January’s 2021 Housing Scrutiny Committee meeting and Department for Levelling Up, Housing and Communities’ National Design Standards. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Development Agency . The Committee made the following comment in response to the report: i. Queried the colour of properties built as part of the regeneration programme as thought properties which were black on the outside absorbed 20% more heat than lighter coloured houses. The Head of Housing Development said the following in response to Members’ questions: i. Confirmed would liaise with the Tenant Representative outside of the meeting regarding the colour of properties built as part of the redevelopment programme as did not believe that any of the new council housing developments contained properties which were black. ii. Confirmed that there was a requirement to build homes to M42 standard and that 5% of homes would be accessible homes. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the housing development programme.
1.2196 Homes have been completed across 13 sites under the City Council programme, with 107 being net new Council homes. An additional 16 modular “pod” homes have been completed across 3 sites.
1.3The Council currently has 419 net new Council rented homes being built on site.
1.4The Council has been recognised for its success through the Cambridge Investment Partnership at the Inside Housing Development Awards in November where it won the Best Development Team (South).
1.5159 net new affordable with a total of 45 market sale homes and an overall total of 253 homes are currently approved as a first stage of the new 1000 homes housing programme. 1.6 The HDA continues to hold discussions with Homes England regarding funding for the new housing programme
1.7The updates to the councils Sustainable Housing Design Guide have now been completed with the guide now following the Department for Levelling Up, Housing and Communities (DLUHC, formerly the MHCLG) National Design Guide ten characteristics of a well-designed place. This design guide for council housing developments includes the sustainability targets as approved by the January 2021 meeting of this Committee on carbon, energy, water, biodiversity, car park ratios and EV charging.
This provides guidance on how sustainable design and good placemaking can help residents out of fuel and water poverty as well as ensuring affordable long term annual maintenance costs. The guide can be found in appendix 3 and will be on the council’s web site.
Recommendations
The Executive Councillor is recommended to:
2.1Note the continued progress on the delivery of the approved housing programme.
2.2Note the updated 2021 Sustainable Housing Design Guide, to include the recommendations approved in January’s 2021 HSC meeting and DLUHC’s National Design Standards.
3. Reporting
3.1This is a quarterly report showing progress on the City Councils new housing developments.
4. £70m funding programme DLUHC
4.1The Council’s housing programme is part funded by a £70 million grant, which to date has been paid via a combination of the Cambridgeshire & Peterborough Combined Authority and directly by DLUHC. All funding has been received. 4.2 As at 31 March 2021 £41,859,663.36 of the funding has been utilised in the delivery of new homes, with £28,140,336.64 held in balances to fund the completion of the programme from April 2021 onwards.
5. Delivery Programme
5.1The delivery programme update provided in June 2021 confirmed that the devolution programme consisted of 542 Council Homes with a further 104 homes identified for the new programme. Following approvals received at the September 2021 meeting of this committee the forecast home delivery under the new 1000 programme has been revised to 159 net affordable homes.
5.2The Council has been recognised for its success through the Cambridge Investment Partnership at the Inside Housing Development Awards in November where it won the Best Development Team (South).
5.3Appendix 1 shows the current programme, indicating total housing provided as well as the net gain of Council homes. Appendix 2 shows the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.
6. Profile of Start on Sites
6.1The start on site profile for the 500 devolution programme is shown in table 1. The total starts on site currently stand at 526, or 105.2% of the total programme target of 500 homes, ahead of the targeted deadline of 31 March 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.