Decision The report presented details of anticipated variances from budgets, where resources were requested to be carried forward into the 2023/24 financial year in order to undertake or complete activities anticipated to have taken place in 2022/23. Decision of Executive Councillor for Housing i. Agreed the provisional carry forward requests, totalling £440,840 as detailed in Appendix A, subject to the final outturn position. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Assistant Head of Finance and Business Manager . The Head of Housing Maintenance and Assets said the following in response to a Member’s question: i. The delay with the Water Conservation Project was due to a member of staff leaving and a procurement exercise being carried out. The request to carry forward funding was to allow the project to conclude. The Net Zero Retrofit Project Officer was now undertaking the work with consultants. An interim report was expected at Easter with a final report two weeks later. It was hoped that water conservation trialling measures would be started in May. The Committee resolved by 10 votes to 0 to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report presents details of any anticipated variances from budgets, where resources are requested to be carried forward into the 2023/24 financial year in order to undertake or complete activities anticipated to have taken place in 2022/23.
1.2The position in relation to rephasing of any investment as part of the Housing Capital Investment Plan will be reported to Housing Scrutiny Committee in the June 2023 committee cycle, alongside final revenue carry forward requests.
The Executive Councillor, is recommended, following scrutiny and debate at Housing Scrutiny Committee, to:
a) To agree the provisional carry forward requests, totalling £440,840 as detailed in Appendix A, are approved, subject to the final outturn position.
Background
Revenue Outturn
3.1Approval in principle is sought to carry forward unspent budget from 2022/23 into the next financial year, 2023/24. Provisional carry forward requests are being presented to the March 2023 Housing Scrutiny Committee, to ensure that officers have the appropriate authority to continue uninterrupted to deliver services and projects, from April 2023, that have been delayed for any reason.
3.2Final carry froward requests will be presented in the June 2023 committee cycle, where the sums involved may differ from the estimates provided in March 2023, which have been provided for approval in principle.
3.3Appendix A sets out the provisional list of items, for the Housing Revenue Account, for which approval is sought to carry forward unspent budget from 2022/23 to the next financial year, 2023/24.
4. Implications
(a) Financial Implications
4.1The financial implications of approving the provisional carry forwards of £440,840 budget from the current year into 2023/24, will result in a reduced requirement in the use of Housing Revenue Account reserves for the current financial year, from £9,146,980 to £8,706,140, with a corresponding increase in the use of reserves in 2023/24.
4.2A decision not to approve a carry forward request will impact on officers’ ability to deliver the service or scheme in question and this
Report page no. 2 Agenda page no. could have staffing, equal opportunities, environmental and / or community safety implications.
(b) Staffing Implications
Any direct staffing implications arising from the delay in delivery of workstreams, or the carry forward of resource, will be considered and addressed by officers as part of each individual carry forward approval.
(c) Equality and Poverty Implications
There are no direct equality and poverty implications associated with this report.
(d) Environmental Implications
There are no direct environmental implications associated with this report.
(e) Procurement Implications Any procurement implications arising from the delay in delivery of workstreams will be considered and addressed by officers as part of each individual carry forward approval.
(f) Consultation and Communication Consultation with tenant and leaseholder representatives is an integral part of the Housing Scrutiny Committee process.
(g) Community Safety There are no direct community safety implications associated with this report.
4. Background papers Background papers used in the preparation of this report:
Background information is held in the Council’s financial management system.
Appendices
• Appendix A – Provisional HRA Carry Forward Requests
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.