Decision The report provided an update on the housing development programme. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the approved housing programme. ii. Noted the inclusion into the new build delivery programme of housing to serve the needs of Afghan and Ukrainian Refugees, part funded through DLUHC, as per the out of cycle decision approved by the executive council in February 2023. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Development Agency . The Head of Housing Development Agency said the following in response to Members’ questions: i. In response to a query regarding the Mill Road development noted that there was a 12-month defect rectification period and the properties would also benefit from a 12 year NHBC guarantee. ii. In response to a query about the St Thomas Road scheme advised that the responses from the consultation were being reviewed and discussions were taking place with Planning Officers about Open Space requirements and how this land could be adapted and still delivered as a net zero carbon scheme. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the housing development programme. 1.2. 592 homes have been completed across 15 sites under the City Council programme, with 330 being net new Council homes
1.3Approval to add a DLUHC-funded refugee housing delivery to the new build housing programme was given by the Executive Councillor in February 2023 through an out of cycle Executive Decision. The total budget for this scheme has been incorporated into the HRA Budget Setting Report approved in February 2023, alongside the assumed receipt of grant funding. Final confirmation of funding allocation from DLUHC has been received and the Council is reviewing prior to formally entering into a Memorandum of Understanding.
1.4In parallel with this committee report quarterly update statistics for the Councils Affordable housing delivery will be published to the Councils website to facilitate public perusal. 2. Recommendations
The Executive Councillor is recommended to:
2.1Note the continued progress on the delivery of the approved housing programme. 2.2. Note the inclusion into the new build delivery programme of housing to serve the needs of Afghan and Ukrainian Refugees, part funded through DLUHC, as per the out of cycle decision approved by the executive council in February 2023.
3. Reporting 3.1 This is a regular quarterly report showing progress on the City Council’s new housing developments.
4 Homes for Ukrainian and Afghan Refugees 4.1. The Department of Levelling Up, Housing and Communities (DLUHC) have introduced a £500 million capital fund to support Local Authorities who have been assessed as facing the greatest challenges in providing move on and settled accommodation for recent humanitarian schemes (Afghan and Ukrainian refugees).
4.2Cambridge has been identified as eligible for capital grant funding (under section 31 of the Local Government Act 2003), with the following indicative allocation:
• A main element of £4,640,000 in funding to be used to provide a minimum of 29 homes.
• A bridging element of £328,683 in additional funding to allow the provision of at minimum 1 larger 4+ bed home to be allocated to households currently residing in bridging accommodation.
4.3Approval to add this refugee housing delivery to the new build housing programme was given by the Executive Councillor in February 2023 through an out of cycle Executive Decision. Delivery is required to be part funded by the local authority, with top up funding of £6,090,000 in respect of the main element and £308,683 in respect of the bridging element required. The total budget of £11,387,366 for this scheme has been incorporated into the HRA Budget Setting Report approved in February 2023, alongside the assumed receipt of grant funding towards the cost.
4.4Homes can be delivered either by the development of new homes or the acquisition of existing homes, with a proposed programme providing a mix of these, including re-purposing existing pipeline supply of new homes in order to meet the delivery deadline of the end-November 2023. Any re-purposed existing pipeline supply will be replaced in the later years of the new build programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.