Update on New Build Council Housing Delivery

Noted Scrutiny 2 papers

Housing Scrutiny Committee noted this item on Tuesday 20 June 2023. Below is the council's own wording, with the papers it was decided on.

Item23/32/HSC

Resolved

Decision The report provided an update on the housing development programme . Decision of Executive Councillor for Housing and Homelessness i. Noted the continued progress on the delivery of the approved housing programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Interim Assistant Director Development. The Committee made the following comments in response to the report: i. Welcomed the work done regarding the provision of homes for Ukrainian refugees. ii. Requested that future reports provided information on wheelchair accessible homes by bedroom size. The Interim Assistant Director Development said the following in response to Members’ questions: i. The tables within the report showed the different stages the various housing developments were at. Agreed to work with councillors to see if different descriptions of the stages of development could be used, so that this information was more user friendly. ii. Archaeological investigations (referred to on p123 paragraph 6.3 of the agenda) were sometimes required as part of a planning application approval. Officers worked with the County Council’s Archaeological Department and consultants to comply with any planning conditions regarding a site’s archaeology. The Committee unanimously resolved to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

HDA Delivery Programme 02/06/2023 Net Market Approval Planning Planning Practical Scheme Name Ward Total homes Delivery Committee Est. SOS Affordable homes date Submitted Resolution Completion BUILD COMPLETE Uphall Road Romsey 2 0 2 E&F HSC Mar-15 Aug-16 Dec-16 Jun-17 Jan-18 Nuns Way & Wiles Close Kings Hedges 10 0 10 Tender HSC Mar-15 Aug-16 Jul-17 Jan-19 Aug-19 Ditchburn Place Community Rooms Petersfield 2 0 2 Tender S&R Sep-18 Aug-18 Nov-18 Jan-19 Sep-19 Queens Meadow Cherry Hinton 2 0 2 CIP HSC Jun-17 Dec-17 Jul-18 May-19 Jun-20 Anstey Way Trumpington 29 0 56 CIP HSC Mar-17 Jan-18 Jul-18 Oct-18 Jun-20 Colville Garages Cherry Hinton 3 0 3 CIP HSC Sep-17 Sep-18 Nov-18 May-19 Jul-20 Gunhild Way Queen Ediths 2 0 2 CIP HSC Jan-18 Jul-18 Oct-18 May-19 Jul-20 Wulfstan Way Queen Ediths 3 0 3 CIP HSC Sep-17 Oct-18 Jan-19 May-19 Sep-20 Markham Close Kings Hedges 5 0 5 CIP HSC Jan-18 May-18 Oct-18 May-19 Sep-20 Ventress Close Queen Ediths 13 0 15 CIP HSC Mar-17 Sep-18 Mar-19 Oct-19 Feb-21 Akeman Street Arbury 12 0 14 CIP HSC Jun-18 Apr-19 Jul-19 Oct-19 May-21 Mill Road Petersfield 118 118 236 CIP S&R Nov-17 Dec-17 Jun-18 Aug-18 Mar-23 Cromwell Road Romsey 116 170 286 CIP S&R Mar-18 Mar-19 Jul-19 Dec-19 Jun-23 Colville Phase 2 Cherry Hinton 43 0 63 CIP HSC Mar-18 Mar-19 Jun-19 Nov-20 Aug-24 Meadows and Buchan Kings Hedges 22 0 22 CIP HSC Jan-19 Dec-19 Aug-20 Feb-21 Dec-24 Sub total 382 288 721 ON SITE Cromwell Road Romsey 2 7 9 CIP S&R Mar-18 Mar-19 Jun-19 Dec-19 Jun-23 Colville Phase 2 Cherry Hinton 4 0 4 CIP HSC Jan-19 Jul-19 Dec-19 Nov-20 Aug-24 Meadows and Buchan Kings Hedges 84 0 84 CIP HSC Jan-19 Dec-19 Aug-20 Feb-21 Dec-24 Campkin Road Kings Hedges 50 0 75 CIP HSC Jul-19 Nov-19 Mar-20 Mar-21 Jul-23 Clerk Maxwell Road Newnham 14 21 35 S106 HSC Jan-19 Dec-19 Jul-20 Feb-22 Jul-23 Sub total 154 28 207 PLANNING APPROVED Kendal Way East Chesterton 1 0 1 Tender HSC Jan-21 Feb-22 Jun-22 Jul-23 Apr-24 Tedder Way Arbury 1 0 1 Tender HSC Jan-21 Jan-22 Nov-22 Jul-23 Apr-24 Sub total 2 0 2 GRAND TOTAL 538 316 930 Progress to 500 starts on site 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Starts by year 2 159 158 203 14 0 2 Cumulative total 2 161 319 522 536 536 538 Progress to 500 Completions 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 Net Completions by year 2 0 17 58 70 188 117 2 Cumulative total 2 2 19 77 147 335 452 454 HSC Approved New programme schemes 02/06/2023

80% of Replacement Total Commttee Planning Planning Practical Scheme Name Ward Social Rent LHA/60% Market Delivery Committee Est. SOS market rent homes Homes Approved Submitted Resolution Completion L2 Orchard Park SCDC 30 0 45 0 0 75 CIP HSC Sep-20 Aug-20 May-21 Apr-22 Feb-24 Colville Road Phase 3 Cherry Hinton 32 0 16 16 0 48 CIP HSC Sep-20 Jun-21 Dec-21 Sep-22 Jul-24 S106 The Mews, Histon Road Arbury 0 10 0 0 0 10 HSC Sep-20 May-19 Feb-20 May-21 Jul-23 Laragh Fen Road East Chesterton 12 0 0 0 0 12 CIP HSC Jan-21 Feb-21 Jul-21 Aug-22 Nov-23 Ditton Fields Abbey 6 0 0 0 0 6 CIP HSC Jan-21 Feb-21 Oct-21 Sep-22 Oct-23 Borrowdale Arbury 3 0 0 0 0 3 CIP HSC Jan-21 Jul-21 Nov-21 Oct-22 Sep-23 Aragon Close Kings Hedges 0 0 7 0 0 7 CIP HSC Jan-21 Jan-22 Oct-22 Aug-23 Oct-24 Sackville Close Kings Hedges 0 0 7 0 0 7 CIP HSC Jan-21 Jan-22 Oct-22 Aug-23 Oct-24 Aylesborough Close Phase 2 Arbury 41 0 29 33 0 70 CIP HSC Sep-21 Apr-22 Oct-22 Jul-23 Jul-25 Paget Rd Trumpington 2 0 2 0 0 4 Tender HSC Sep-21 Jun-23 Oct-23 Apr-24 Apr-25 St thomas Rd Coleridge 0 8 0 0 0 8 Tender HSC Sep-21 Jul-23 Nov-23 May-24 May-25 Fanshawe Road Coleridge 44 0 49 22 0 93 CIP HSC Jun-22 Aug-23 Jan-24 Jul-24 Mar-26 East Road Petersfield 16 0 24 0 0 40 CIP HSC Jan-23 Sep-23 Feb-24 Jul-24 Jan-26 Hanover and Princess Market 0 82 0 82 56 138 CIP HSC Mar-23 Dec-23 Jul-24 Jan-25 Jan-27 Hills Avenue Roughsleeper Pods Queen Edith 4 0 0 0 0 4 ITAC HSC Mar-23 Apr-23 Oct-23 Nov-23 Feb-24

Total (Excluding Hanover and Princess TBC) 190 100 179 153 56 525

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HDA Outturn report /32/HSCReport 282 KB DownloadRead as text
PDF
Update on New Build Council Housing DeliveryReport 806 KB Download

At this meeting

Whole meeting

Who was there

14 of 16 attended
DP
Councillor Dinah PoundsChair, present
RR
Councillor Richard RobertsonVice-Chair, present
TG
Councillor Tim GriffinCommittee Member, present
CH
Councillor Cameron HollowayCommittee Member, present
DL
Councillor Daniel LeeCommittee Member, apologies
AM
Councillor Anthony Martinelli Lib Dem (Spokes) Housing and HomelessnessCommittee Member, present
ET
Councillor Elliot Tong Green & Independent (Spokes) Housing and HomelessnessCommittee Member, present
BT
Councillor Baiju Thittala VarkeyCommittee Member, present
RW
Councillor Rachel WadeCommittee Member, present
KP
Councillor Katie PorrerCommittee Member, present
GB
Councillor Gerri Bird Executive Councillor for Housing and HomelessnessExecutive Councillor, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present

All 16 on the meeting page

On this subject at Cambridge

Search all
  1. Update on New Build Council Housing DeliveryThis decision
  2. New Build Working Group – New Build Repairs and Maintenance After the Defects PeriodDecided
  3. New Build UpdateNoted
  4. Update on New Build Council Housing DeliveryNoted
  5. Update on New Build Council Housing DeliveryNoted
  6. Update on New Build Council Housing DeliveryNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open