Cambridge City Council
Housing Scrutiny Committee, Tuesday 23 January 2024 at 5.30pm

Compliance Report

Noted Scrutiny 5 papers

Housing Scrutiny Committee noted this item on Tuesday 23 January 2024. Below is the council's own wording, with the papers it was decided on.

Item24/5/HSC

Resolved

Decision The report provided an update on the compliance related activities delivered within the City Services Compliance Team, including a summary on gas, electrical, fire, lifts, legionella and asbestos. Decision of Executive Councillor for Housing and Homelessness i. Noted the progress of the compliance related work detailed within the Officer’s report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the City Services Director reference was also made to an updated report which had been published online and circulated to members in advance of the meeting and contained the most up to date information regarding compliance. The City Services Director said the following in response to Members’ questions: i. Agreed that a monthly report would be provided to the Committee regarding compliance information, and this could then be reduced once the council was in a more stable position. ii. A more formal Housing Leadership Board had been established which would meet monthly to review compliance standards. iii. With reference to the reports of damp, condensation, and mould (DCM), noted that the up-to-date figure of DCM cases was 408. Referred to the procedure officers followed for reports of DCM. Advised that information regarding the status of these cases would need to be provided outside of the meeting. iv. Plans for engagement with residents regarding DCM included the provision of information on the council’s YouTube channel and other social media channels, leaflet drops and briefing other council Departments who engaged with the public so that they had the information to refer residents to the DCM Team when questions / issues arose. v. The city had been mapped to identify properties believed to be at risk of DCM and these were prioritised, checked, and investigated. The Committee resolved by 8 votes to 0 with 3 abstentions to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Agenda Item

Item Compliance Update To: Housing Scrutiny Committee January 2024 Report by: Renier Barnard – Property Compliance and Risk Manager Tel: 01223 457485 Email: [email protected] Wards affected: All Wards

This report is for information and not for decision. 1. Executive Summary

The report provides an update on the compliance related activities delivered within the City Services Compliance Team, including a summary on gas, electrical, fire, lifts, legionella and asbestos. 2. Recommendations

The Executive Councillor is recommended to note the progress of the compliance related work detailed within the report.

3. Compliance Dashboard, Supplementary Data and Damp Condensation, Mould

The Compliance Dashboard is attached (Appendix A) Supplementary Data is attached (Appendix B) Damp Condensation and Mould is attached (Appendix C)

Report page no. 1 Page Agenda page no. 4. Compliance Update

The six key compliance areas are:

4.1Gas Safety Requirement - A gas safety check is to be completed every year on each gas appliance/flue and before any new tenure and annually for existing tenancies.

 As at 2nd January 2024 Cambridge City Council is 100% compliant on Gas Safety certification with 6610 properties with valid landlord gas safety certificates.

 Each property has a working Carbon Monoxide (CO) detector and is inspected with every gas service completed.

6371 Properties with 1 Carbon Dioxide detector 651 Properties with 2 Carbon Dioxide detectors 74 Properties with 3 Carbon Dioxide detectors 32 Properties with 4 Carbon Dioxide detectors 7128 Total

For note. All gas services have now been removed from Hanover Court and Princess Court.

4.2Electrical Safety Requirement - A residential premises is to be inspected and tested for electrical safety by a qualified person at intervals of no more than 10 years.

 As of 29th November 2023 Cambridge City Council is 76.95% compliant with legislation with 5897 properties with a valid satisfactory condition report.

See Appendix B for supplementary data.

4.3Fire Management Risk Assessment Requirement - A fire risk assessment is a legal requirement to assess the risk, identify fire hazards and allow landlords to take general precautions to reduce and manage fire risk

 As of 2nd January 2024, Cambridge City Council is 100% compliant with legislation where the requirement is to have a Fire Risk Assessment completing 447 Fire Risk Assessments.

However, while understanding that compliance primarily focuses on having a Fire Risk Assessment in place the objective is to achieve an overall risk rating of Report page no. 2 Page Agenda page no. tolerable addressing outstanding risks and actions through this process.

See Appendix B for supplementary data.

4.4Asbestos Management Requirement - The statutory requirement to be compliant with legislation is for all communal areas to have been inspected. For premises built after 2000, then the HSE states it is safe to assume that no asbestos containing materials are located within the fabric of a building as asbestos was prohibited from 1999, therefore a survey is not required.

 As of 29th December 2023, Cambridge City Council is 56% compliant. This was identified during the implementation of an asbestos compliance module, creating a new data structure for blocks and communal areas from the dataset. Following the implementation of the asbestos compliance module it became clear that there was a need to put in place a plan to achieve full compliance.

The inspections schedule will complete all outstanding inspections by March 31st 2024.

See Appendix B for supplementary data

4.5Legionella & Water Hygiene Requirements: The Approved Code of Practice (ACOP) L8, issued by the Health and Safety Executive (HSE), provides guidance on the control of Legionella bacteria in water systems.

The ACOP L8 recommends a risk-based approach to managing the risk of Legionella, which includes regular monitoring, inspection, and maintenance of water systems.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Compliance Dashboard /5/HSCAppendix A 486 KB Download
PDF
Supplementary Data: 0801 /5/HSCAppendix B 314 KB Download
PDF
DCM_ /5/HSCAppendix C 208 KB Download
PDF
Compliance ReportReport 177 KB DownloadRead as text
PDF
Supplementary Compliance Update /5/HSCSupplementary 167 KB Download

At this meeting

Whole meeting

Who was there

12 of 14 attended
DP
Councillor Dinah PoundsChair, present
RR
Councillor Richard RobertsonVice-Chair, present
TG
Councillor Tim GriffinCommittee Member, present
CH
Councillor Cameron HollowayCommittee Member, present
DL
Councillor Daniel LeeCommittee Member, present
KP
Councillor Katie PorrerCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
BT
Councillor Baiju Thittala VarkeyCommittee Member, present
ET
Councillor Elliot Tong Green (Spokes) Housing and HomelessnessCommittee Member, present
GB
Councillor Gerri Bird Executive Councillor for Housing and HomelessnessExecutive Councillor, present
CA
Christabella Amiteye Tenant RepresentativeCo-Optee, apologies
DB
Diane Best Leaseholder RepresentativeCo-Optee, apologies

All 14 on the meeting page

On this subject at Cambridge

Search all
  1. Compliance ReportThis decision
  2. Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance ContractsNoted
  3. Cabinet: Strategic Procurement Pipeline for Repairs, Maintenance, and Compliance ContractsNoted
  4. Policies: Regulatory Compliance and Tenant EngagementAgreed
  5. Compliance UpdateNoted
  6. Compliance UpdateNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies