Update on New Build Council Housing Delivery

Noted Scrutiny 2 papers

Housing Scrutiny Committee noted this item on Tuesday 12 March 2024. Below is the council's own wording, with the papers it was decided on.

Item24/17/HSC

Resolved

Decision The report provided a regular quarterly update on progress for the City Council’s new housing delivery and development programme. Decision of Executive Councillor for Housing and Homelessness i. Noted the continued progress on the delivery of the approved housing programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Assistant Director Development and a correction was made to section 5.3 on p38 of the agenda; the Fanshawe Road development should have included 39 market rent homes instead of 0. Post meeting note from the Assistant Director Development: The St Thomas's proposals were approved at the September 2021 Housing Scrutiny Committee and were brought back to Housing Scrutiny Committee in September 2022 with a further recommendation to ‘Note the further review of budget and housing mix required to be undertaken at St Thomas Road, with a further update to be brought to the Committee as design work progresses’. Following a regular briefing with the Executive Councillor for Housing and Homelessness on all development projects, including St Thomas's there was a clear steer to officers to review the St Thomas proposals because of residents’ concerns regarding open space and planning policy on open space. Officers will undertake a review of what development, if any, is possible, that keeps the current open space. This review will be brought back to Housing Scrutiny Committee in June or September for members to vote on the next steps in line with the recommendations stated in the June 2022 Housing Scrutiny Committee report. In the meantime, as stated in the March 2024 Housing Scrutiny Committee, the current proposals are on hold. The Assistant Director Development said the following in response to Members’ questions: i. The design proposals for Ekin Road which were currently being consulted on were for the full redevelopment of the area with a mixed tenure scheme. The JLL report explained that consideration needed to be given not only to financial considerations but also to other benefits. The partial redevelopment option did not meet the 11 ‘critical success factors’ that the full redevelopment option would. A report on Ekin Road would be brought back to the June Housing Scrutiny Committee. The Executive Councillor for Housing and Homelessness responded: i. In response to a question regarding whether it was possible to bring the consultation for Davy Road proposals forward; advised that it took time to review areas for redevelopment. Officers would contact residents to advise when the consultation would take place. The Committee resolved by 6 votes to 1 with 2 abstentions to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Item Update on new build council housing delivery

To: Councillor Gerri Bird, Executive Councillor for Housing Housing Scrutiny Committee 23/01/2024

Report by: Ben Binns, Head of Housing Development Agency Email: [email protected]

Wards affected: All 1 Executive Summary

1.1This is a regular quarterly report showing progress on the City Council’s new housing delivery and development programme. 1.2. 852 new build homes have been completed across 18 sites under the City Council programmes, with 458 being net new Council homes.

1.3As verbally reported to the January meeting of this committee Revised funding has now been allocated from Homes England: 1.3.1. £5,717,000 for Aylesborough Close for net new and replacement homes 1.3.2. £1,280,000 for Colville Road Phase 3 for replacement homes 1.4. One single housing acquisition remains to meet LAHF Round 2 by end March 2023, with this last purchase in process.

1.5The St Thomas Road development is now on hold pending officer review. 1.6. The East Barnwell development was submitted for planning in December 23 and further work is continuing with residents and commercial tenants. The council is working with commercial tenants to ensure there is continuity of service throughout the development programme. 1.7. On Ekin, the second stage report from JLL has now been published. The report will be presented to the Ekin Road Liaison Group on 4th March. The council does not believe that it is fair to residents’ wellbeing to create delay and uncertainty. Therefore, as advised by JLL, the council is proposing to consult on emerging designs. 1.8. In parallel with this committee report quarterly update statistics for the Councils Affordable housing delivery will be published to the Councils website to facilitate public perusal. 2. Recommendations

The Executive Councillor is recommended to:

2.1Note the continued progress on the delivery of the approved housing programme.

3. Delivery Programme 3.1. The current delivery programme confirms:  the 500 devolution programme consisting 931 (including market sale) homes in total and 537 net affordable homes.  the 10-year New Homes Programme consisting of 856 homes with scheme approval. This 856 is made up of: o 240 net new build Council rented HRA homes at Social rent or 60% of Market rent (Subject to Final Design ahead of formal planning submissions, and including market acquisitions funded by LAHF). o 4 modular homes to be held, let and funded as Roughsleeper accommodation by It Takes a City. o 228 net new homes to be let at 80% of Market rent and held within the HRA. (Subject to Final Design ahead of formal planning submissions). o 202 homes earmarked for market sale. o 21 market acquisitions into the HRA earmarked for refugee accommodation, funded through the Local Authority Housing Fund, to be let at 60% of market rent. o 161 Replacement rented homes on regeneration sites. 3.2 The acquisition of Section 106 homes from the CIP led scheme at Newbury Farm was approved in January 2024. Work remains ongoing toward finalising scheme design ahead of planning submission.

The tables below show the breakdown of homes and the stage they are at: 500 Homes Programme Completed On site Approved Totals Total Homes 842 88 1 931 Replacement homes 76 0 0 76 Market Sale 318 0 0 318 Net new Affordable HRA homes 448 88 1 537 % of target 108%

10 Yr New homes programme Completed On site Approved Totals Total Homes 30 226 600 856 Replacement homes 0 49 112 161 Intermediate (80% of market rents) 0 104 124 228 Acquisitions (LAHF) 20 1 0 21 Market Sale 0 8 194 202 Net new Build Social and 60%/LHA(CCC) 10 64 170 240 Net new 3rd Party Affordable Breakdown below - Modular 4 Total Net New held in HRA Includes all net HRA rental 489

Modular Homes Project Completed On site Approved Totals Total Homes 16 0 4 20 Replacement homes 0 0 0 0 Market Sale 0 0 0 0 Net new HRA homes 16 0 0 16 Net new 3rd party homes 0 0 4 4

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on New Build Council Housing Delivery Appendix 1 Outturn Report /17/HSCAppendix 251 KB Download
PDF
Update on New Build Council Housing DeliveryReport 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 15 attended
DP
Councillor Dinah PoundsChair, present
RR
Councillor Richard RobertsonVice-Chair, present
TG
Councillor Tim GriffinCommittee Member, present
CH
Councillor Cameron HollowayCommittee Member, present
DL
Councillor Daniel LeeCommittee Member, apologies
AM
Councillor Anthony MartinelliCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
BT
Councillor Baiju Thittala VarkeyCommittee Member, present
ET
Councillor Elliot Tong Green (Spokes) Housing and HomelessnessCommittee Member, present
KP
Councillor Katie PorrerCommittee Member, present
GB
Councillor Gerri Bird Executive Councillor for Housing and HomelessnessExecutive Councillor, present
CA
Christabella Amiteye Tenant RepresentativeCo-Optee, apologies

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. Update on New Build Council Housing DeliveryThis decision
  2. New Build Working Group – New Build Repairs and Maintenance After the Defects PeriodDecided
  3. New Build UpdateNoted
  4. Update on New Build Council Housing DeliveryNoted
  5. Update on New Build Council Housing DeliveryNoted
  6. Update on New Build Council Housing DeliveryNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies