24/01531/REM Land South of Worts Causeway - GB2 - Phase 3

Approved Planning 3 papers

Planning approved this item on Wednesday 2 October 2024. Below is the council's own wording, with the papers it was decided on.

Item24/98/Plan

Resolved

Resolved (by 7 votes to 0) to: i. approve reserved matters application reference 24/01531/REM subject to the planning conditions and informatives as set out in the Officer’s report and amendment sheet, with delegated authority to officers to carry through minor amendments to those conditions, informatives and the completion and approval of the Section 106A deed of variation under application reference 24/02159/S106A prior to the issuing of the planning permission; ii. approve/not approve the discharge of the following outline planning conditions (planning application reference 19/1168/NMA1) in so far as they relate to this reserved matters application site according to the recommendations for each condition set out in the table below: Condition Recommendation 9. Tree Planting and Landscape Strategy Approve 11. Residential Space Standards Approve 12. Surface Water Drainage Strategy Approve 13. Carbon Reduction Statement Approve 14. Water Conservation Strategy Approve 15. Sustainability Statement Approve 16. BREEAM Approve 17. Noise Assessment Approve 18. Commercial Noise Approve 19. Artificial Lighting Scheme Not Approved. 20. Ductwork Approve 29. Ecological Enhancement Approve 31. Bird Hazard Management Plan Approve 32. Ecological Design Strategy Approve 43. EV charging scheme Not Approved. 51. Travel Plan Approve iii. delegated authority to Officers, in consultation with the Chair, Vice Chair and Spokes, to amend the following: a. Condition 6 trigger point to be above ground ; b. Condition 8 provision of benches in play areas not open spaces; iv. informatives included on the planning permission in respect of: a. encouraging electric charging points for wheelchairs and bikes in cycle stores; and to encourage fire safety provisions for both; b. encouraging provision of water butts.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning

Planning Committee Date 2nd October 2024

Report to Cambridge City Council Planning Committee

Lead Officer Joint Director of Planning and Economic Development

Reference 24/01531/REM

Site Land at Newbury Farm, Babraham Road, Cambridge.

Ward / Parish Queen Edith’s

Proposal Reserved matters application for appearance, landscape, layout and scale for Phase 3 comprising the creation of 150 residential units, community/ commercial spaces, hard and soft landscaping including the creation of a central square and associated works. The related partial discharge of Outline Conditions pursuant to outline approval 19/1168/NMA1.

Applicant Cambridge Investment Partnership

Presenting Officer Aaron Coe

Reason Reported to The application is a Regulation 3 planning Committee application as Cambridge City Council has a direct interest in the application as part applicant.

Member Site Visit Date N/A

Key Issues 1.Compliance with the outline planning permission. 2.Design and layout. 3.Affordable Housing delivery. 4.Sustainability matters. Recommendation APPROVE this reserved matters application subject to:

-The conditions and informatives as detailed in this report with delegated authority to officers to carry through minor amendments to those conditions, informatives and the completion and approval of the Section 106A deed of variation under application reference 24/02159/S106A prior to the issuing of the planning permission.

-Partial discharge of the following planning conditions on the outline consent in relation to this reserved matters application only: Condition 9 – Tree Planting and Landscape Strategy Condition 12 – Surface Water Drainage Strategy Condition 13 – Carbon Reduction Statement Condition 14 – Water Conservation Strategy Condition 15 – Sustainability Statement Condition 16 – BREEAM Condition 17 – Noise Assessment Condition 18- Commercial Noise Condition 19 – Artificial Lighting Scheme Condition 20 – Ductwork Condition 29- Ecological Enhancement Condition 31 – Bird Hazard Management Plan Condition 32 – Ecological Design Strategy Condition 51 – Travel Plan 1.0 Executive Summary

1.1The application site lies within GB2, which is identified for residential development under Policy 27 of the Cambridge Local Plan 2018.

1.2The GB2 site lies between Babraham Road and Wort’s Causeway. The site has outline permission for up to 230 dwellings and up to 400m2 of non-residential floorspace within Use Classes A1/A3/A4/D1 (19/1169/OUT). The site has three phases agreed under Condition 4 of the outline planning permission. Phase 1 is for the spine road and has reserved matters approval (21/04186/REM), this will form a link between Babraham Road with Wort’s Causeway and the access and tertiary roads through the site will come off this route. Phase 2 (80 residential units) was approved by planning committee in June 2023 under application reference 22/02646/REM. This planning application is for Phase 3.

1.3Phase 3 lies to the west of the spine road and abuts the Cambridge Green Belt along the southern boundary only. The application seeks approval of the reserved matters for 150 dwellings, 400m2 of commercial/ community spaces and for the hard and soft landscaping. 40% of the dwellings are proposed to be affordable (60 units).

1.4The applicant has sought pre-application advice, including from the Cambridgeshire Quality Panel. A developer briefing to Members of the City Planning Committee took place in January 2024. Negotiations, at the pre- application stage and during the consideration of the application, have resulted in the current scheme. The scheme is considered by officers to have moved forward positively and consultee comments have been taken on board.

1.5The scheme would meet the design principles set out in Condition 6 of the outline planning permission and would comply with the approved Parameter Plans.

1.6These reserved matters build upon the design principles established at the outline stage, to ensure a co-ordinated development across the GB2 site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24.01531.REM Appendix A: Quality Panel: GB2 Phase 3 /98/PlanAppendix 487 KB Download
PDF
24.01531.REM Appendix B: Disability Panel Report: GB2 Phase 3 /98/PlanAppendix 267 KB Download
PDF
24/01531/REM Land South of Worts Causeway: GB2: Phase 3Report 513 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
MS
Councillor Martin SmartChair, present
DB
Councillor Dave BaigentVice-Chair, present
NB
Councillor Naomi Bennett Green (Spokes)Committee Member, apologies
RD
Councillor Robert DrydenCommittee Member, present
AG
Councillor Alice GilderdaleCommittee Member, present
TG
Councillor Tim GriffinCommittee Member, present
NL
Councillor Nadya LokhmotovaCommittee Member, present
KP
Councillor Katie Porrer Lib Dem (Spokes)Committee Member, apologies, sent representative
KT
Councillor Katie ThornburrowCommittee Member, present
MT
Councillor Mike Todd-JonesCommittee Member, apologies, sent representative
KY
Councillor Karen YoungCommittee Member, present

On this subject at Cambridge

Search all
  1. 24/01531/REM Land South of Worts Causeway - GB2 - Phase 3This decision
  2. 26/01691/REM Land North of Cambridge North StationApproved
  3. 24/01549/REM - B2 Land (Car Dealership development) Land North Of Newmarket Road (Marleigh)Decided
  4. S/1004/18/RM and 18/0459/REM - Land North of Newmarket RoadApproved
  5. 17/1461/REM: Cycleway/footway - Land Adjacent to Cambridge Guided Busway and Adjacent to existing plantation within abode 1 (Parcels 10, 11 and 12), Clay Farm, Trumpington, Cambridge.Decided
  6. 17/0285/REM - Plot M3 - Land between Madingley Road and Huntingdon JunctionApproved

More from Cambridge Planning

All decisions
MeetingDecisionOutcome
4 Nov 2026 26/02186/FUL Coldham's Common, Pool Way, Whitehill RoadResolved (by 7 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 25/04187/FUL Hanover Court and Princess CourtResolved (by 4 votes to 3) to grant the application for planning permission in accordance with the Officer recommenda... Agreed Open
24 Jun 2026 25/03323/FUL 73 Newmarket RoadResolved (4 votes to 4 – and on the Chair’s casting vote) to grant the application for planning permission in accorda... Agreed Open
24 Jun 2026 26/01081/FUL 9, 11, 15 and 17 Ashfield RoadResolved (by 6 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 26/01400/FUL 1, 2, 3, 4, 11, 12 The GreenResolved (by 5 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open