Environment and Community Scrutiny Committee, Thursday 16 January 2025 at 6.00pm

Update on the Costs Associated With the Material Recycling Facility Contract Budget

Noted Scrutiny 1 paper

Environment and Community Scrutiny Committee noted this item on Thursday 16 January 2025. Below is the council's own wording, with the papers it was decided on.

Item25/6/EnC

Resolved

Decision The Officer’s report provided an update on the financial impact of the joint procurement exercise undertaken by the RECAP partnership consisting of five Cambridgeshire Waste Collection Authorities and new contract options from March 2025. Decision of Executive Councillor for Climate Action and Environment Noted the additional MRF contract costs and options being pursued from March 2025 when the existing contract ends. Costs have already been accounted for in the MTFS. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected See Officer’s report. Scrutiny Considerations The Committee received a report from the Waste Policy, Change and Innovations Manager . Two Councillors made the following comments in response to the report: i. Councillor Ashton referred to P6 24/41/ EnC minutes and expressed concern regarding the Material Recycling Facility (MRF) contract process. Councillors needed to be informed at the earliest opportunity so options could be considered and debated. He had raised this point six months ago. ii. Councillor Tong expressed concern that Councillors were not given the opportunity to scrutinise the MRF contract and there was a lack of information about environmental impacts. The Executive Councillor for Climate Action and Environment responded: i. Reiterated details from her response in September 2024. The procurement process started two years ago. ii. The City Council had to follow procurement guidelines. The previous recycling contract ended in August 2024 so items for recycling needed to be sent somewhere since August 2024. iii. The South Cambs District Council Liberal Democrat Cabinet Member and Labour City Council Executive Councillor plus Officers had worked on contract options. The intention was to minimise the Waste Service / MRF contract carbon footprint but this could not be measured until action was taken. iv. There was no reduction in the number of items that could be recycled, but a number of items had been added, so more items could be put in residents’ blue bins for recycling. v. The new contract would last five years to allow time for the City Council and shared service to review further options. Councillor Ashton said the Scrutiny Committee should have been given more information to scrutinise options. The Executive Councillor undertook to send recycling information via officers after committee. The Waste Policy, Change and Innovations Manager said the following in response to Members’ questions: i. Sixteen other local authorities in Great Britain used the recycling facility in Northern Ireland which the City Council intended to use. ii. Undertook to liaise with the contractor in March 2025 to seek information requested such as the carbon footprint of operations. The Executive Councillor said: i. Was happy to bring a report back in future about recycling rates, off-setting waste lorry journey carbon footprint and MRF contract progress. ii. Recycling was better than landfill, but the preferred hierarchy was reduce , reuse, recycle. iii. Referred to information on the City Council website about recycling and asked Ward Councillors to signpost it to residents. Any specific queries could be directed to the Executive Councillor which could then be put on the website to be publicly available. Councillor Hauk proposed and Councillor Payne seconded an amendment to recommendation 1.1 from the Officer’s report (amendments shown as bold and struck through text): It is recommended that the Environment and Community Scrutiny Committee notes the additional MRF contract costs and options being pursued from March 2025 when the existing contract ends calls on Greater Cambridge Shared Waste Services to defer any new MRF contract until the carbon footprint of alternative suppliers can be fully assessed . Costs have already been accounted for in the MTFS . The amendment was lost by 3 votes to 5. The Committee resolved by 4 votes to 4 and on Chair’s casting vote to endorse the recommendation. The Executive Councillor approved the recommendation. Councillor Ashdon asked for clarification to be publicised that contract decisions were made in conjunction with South Cambs District Council and were not solely made by the City Council. The Executive Councillor invited suggestions on how to provide greater clarity. It was clear in press releases, webpages and stickers on bins that recycling was undertaken by a shared service. The City Council and South Cambs District Council were equal partners so both had to agree before a proposal could be taken forward. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment and Community Scrutiny Committee

Recommendations

1.1It is recommended that Environment and Community Scrutiny Committee notes the additional MRF contract costs and options being pursued from March 2025 when the existing contract ends. Costs have already been accounted for in the MTFS.

2. Purpose and reason for the report

2.1This report provides an update on the financial impact of the joint procurement exercise undertaken by the RECAP partnership consisting of five Cambridgeshire Waste Collection Authorities and new contract options from March 2025.

2.2NOT FOR PUBLICATION: the appendix relates to an item during which the public is likely to be excluded from the meeting by virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972 because it contains commercially sensitive information. The public interest test has been applied to the information contained within this exempt annex and it is considered that the need to retain the information as exempt outweighs the public interest in disclosing it. 3. Alternative options considered 3.1 Options being explored for a local bulking facility from March 2025:

A. Enter a new contract with Thalia for using their existing shed as a Waste Transfer Station (not the MRF) – the shed will need significant capital investment to enable them to operate safely, e.g. fire suppression etc. The remedial works to the shed are estimated to cost Thalia about £1M.

B. Enter a contract with another transfer station in the Service area. The only suitable facility identified to date is located at Haverhill – more than fifteen sites have been explored over the past nine months. Haverhill is quite a distance south of our district and would require a collection round reconfiguration as well as several additional vehicles (approximately eight) and subsequently costs to cover the extra distance travelled by the recycling crews. Costs would be circa £2M/year taking account of hiring vehicles, additional staff / operations crew resources, travel time and the gate fee (charge per tonne for taking material to the MRF.)

C. Build our own transfer station. This option has been explored in some detail over the last six months and potential sites in the vicinity of the Waterbeach Depot have been identified – this option hasn’t been outright discarded but it would require a large capital investment (circa. £3m - £5m), plus ongoing revenue / operational costs, and we don’t have sufficient time to get this in place for the start of March 2025.

The preferred option that is being actively pursued is Option A, as this is the most economically advantageous option and the only practical option that can be fully developed by the deadline of March 2025, when the current MRF contract extension (with Thalia) terminates.

Appendix A highlights the additional steps required to enter into new bulking and processing contracts. These are partly responsible for cost increases alongside changes to the market value of materials and higher specifications for material capture and recovery.

4. Background and key issues

4.1In June 24 an Executive Cllrs RoD was sought and approved for a budget of threshold (see Appendix B) for the new Materials Recycling Facility (MRF) and Bulking Station contracts for dry recyclables materials collected by the Greater Cambridge Shared Waste Service (GCSWS).

This report provides an update on the joint procurement exercise undertaken by the RECAP partnership consisting of five Cambridgeshire Waste Collection Authorities (WCA), the Waste Disposal Authority (WDA) and Peterborough City Council (PCC).

The proposed arrangements (to come into effect in March 2025) are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Costs Associated With the Material Recycling Facility Contract BudgetReport 654 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 15 attended
DP
Councillor Dinah PoundsChair, present
AN
Councillor Antoinette NestorVice-Chair, present
MA
Councillor Mark AshtonCommittee Member, present
ID
Councillor Iva DivkovicCommittee Member, apologies, sent representative
JG
Councillor Jean Glasberg Green (Spokes)Committee Member, apologies, sent representative
TG
Councillor Tim GriffinCommittee Member, present as substitute
OH
Councillor Olaf Hauk Lib Dem (Spokes) Climate Action and EnvironmentCommittee Member, present
CP
Councillor Cheney Payne Lib Dem (Spokes) Open Spaces and City Services; Communities, Community Wealth Building and Community SafetyCommittee Member, present
RS
Councillor Richard SwiftCommittee Member, present
ET
Councillor Elliot TongCommittee Member, present as substitute
AG
Councillor Alice Gilderdale Statutory Deputy Leader with Executive Responsibility for Economy and SkillsExecutive Councillor
CH
Councillor Cameron Holloway Executive Councillor for Community Safety, Homelessness and WellbeingExecutive Councillor, present

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. Update on the Costs Associated With the Material Recycling Facility Contract BudgetThis decision
  2. Employment (Senior Officer) Committee: Estates and Facilities Restructure: Associated Exit CostsAgreed

More from Cambridge Environment and Community Scrutiny Committee

All decisions
MeetingDecisionOutcome
20 Mar 2025 Folk FestivalDecision The Officer’s report was presented following a request for a special meeting of Environment and Community Sc... Noted Open
20 Mar 2025 Market Traders Terms and ConditionsDecision The Officer’s report provided details of the proposed changes to Cambridge General Market (General Market) T... Approved Open
20 Mar 2025 Weekly Food Waste CollectionsDecision The Environment Act 2021 required all councils to align their household waste and recycling services with ne... Approved Open
20 Mar 2025 Leisure Management Contract 2026Decision This report was being presented to update Members and conclude the on ongoing work to review the Council’s l... Agreed Open
20 Mar 2025 Equalities Objectives for 2025/26Decision The Officer’s report sought approval of new equalities objectives applicable from 1 April 2025 to 31 March 2... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies