Council, Thursday 9 October 2025 at 6.00pm

Cambridge Civic Quarter Project Update

Agreed Committee 3 papers

AI summaryCambridge City Council approves up to £4.4m capital budget for technical design work on the Civic Quarter project, with final approval due in September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedUp to £4.4m for design and cost work
Money£4.4m capital budgetFor technical design and cost finalisation
What happens nextFinal approval in September 2026Cabinet to refine design and funding
Who it affectsCity centre users and residentsGuildhall, Corn Exchange, Market Square

What was decided

Council approved a capital budget of up to £4.4m to fund technical design development, a detailed development programme and finalisation of total direct and indirect project costs. Report P8

Council asked Cabinet, ahead of final approval in September 2026, to rigorously review design, costings, phasing, funding strategy and business plans for the Guildhall and Corn Exchange to improve financial return.

Council accepted that the public realm and Market Square project should deliver a wide community benefit for residents and city centre workers, not necessarily a financial return, but should still undergo value engineering and a search for further external grant support.

Why

Cabinet had agreed unanimously on 25 September 2025 to recommend the capital budget to Full Council for approval. Report P1, P6, P7

Technical design work and finalisation of total direct and indirect costs are needed before the project can receive final approval. Report P8

What happens next

Cabinet to review design, costings, phasing, funding strategy and business plans for the Guildhall and Corn Exchange projects before seeking final approval in September 2026.

Officers to continue engaging with market traders and other stakeholders on the public realm and Market Square project, and to seek further external grant support.

The money

  • up to £4.4m Capital budget for technical design development, detailed development programme and finalising total direct and indirect project costs Report P8

Implications

  • Financial: The Guildhall and Corn Exchange projects are expected to deliver a better financial return on capital costs to support general council services, achieved through rigourous review of design, costings, phasing, funding and business plans.
  • Financial: The public realm and Market Square investment is accepted as primarily delivering community benefit rather than a direct financial return to the council, though it should still be refined and value engineered.
  • Other: The project team is to actively seek external grants as part of the funding strategy, in addition to reviewing the proposed funding approach.

Who and where

  • Residents of Cambridge and users of general council services
  • People who work in the city centre
  • Market traders and other city centre stakeholders

Timeline

  • 25 September 2025: Cabinet unanimously recommended the capital budget to Full Council Report P1, P7
  • 9 October 2025: Full Council approved the £4.4m capital budget and additional recommendations to Cabinet, by 30 votes to 6 with 2 abstentions
  • September 2026: Final approval of the project scheduled

Plain English for the jargon

  • Capital budget: Money set aside for major building or infrastructure projects rather than day-to-day spending.
  • Public realm: Publicly accessible spaces such as streets, squares and walkways between buildings.
  • Value engineering: A review process aimed at reducing costs or improving function without reducing quality.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/85/CNL

Resolved

Resolved (30 votes to 6, 2 abstention) to agree: 1. A capital budget of up to £4.4m to be allocated to fund the technical design development, detailed development programme and to finalise the total direct and indirect costs of the project. 2. In addition, recommends that in the run-up to final approval in September 2026 Cabinet is requested to: (a) Seek to improve the ongoing financial return from the Guildhall and Corn Exchange projects in relation to their capital costs, so that a better financial contribution to the protection and improvement of general council services to the public can be expected – as well as the other intrinsic benefits of the investment; and that this is achieved by rigorously reviewing the design & costings; the phasing; the proposed funding strategy (including the possibility of external grants) and the business plans for the operation of the refurbished facilities. (b) Accept that the investment in the public realm and Market Square project must produce a widely experienced enhancement of the city centre for the community at large including those who work there - and not necessarily a financial return to the council; , it should however still benefit from refinement as a result of ongoing input from market traders and other stakeholders and be subject to the normal discipline of value engineering and a search for further external grant support.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Council

CABINET 25 September 2025 5.00pm - 8.03pm

Present: Councillors Holloway (Chair), Wade (Vice-Chair), Bird, Moore, Nestor, Smart, S.Smith and Thornburrow

In attendance virtually: Councillors A. Smith and Todd-Jones

FOR ADOPTION BY THE COUNCIL

Civic Quarter Project - Update

Cabinet agreed the following recommendation that requires Full Council approval.

Resolved (Unanimous) to recommend that Council approves:

1. A capital budget of up to £4.4m to be allocated to fund the technical design development, detailed development programme and to finalise the total direct and indirect costs of the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
draft minutes September 2025 /85/CNLAppendix PAS 117 KB Download
PDF
Cambridge Civic Quarter Project UpdateReport 50 KB DownloadRead as text
PDF
Item 5. CQ Cabinet Report /85/CNLReport 406 KB Download

At this meeting

Whole meeting

Who was there

40 of 42 attended
MA
Councillor Mark AshtonCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
NB
Councillor Naomi BennettCommittee Member, present
TB
Councillor Tim BickCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
IB
Councillor Immy Blackburn-HorganCommittee Member, present
HC
Councillor Hugh CloughCommittee Member, present
JD
Councillor Jamie DalzellCommittee Member, present
MD
Councillor Mike DaveyCommittee Member, present
ID
Councillor Iva DivkovicCommittee Member, apologies
RD
Councillor Robert DrydenCommittee Member, present
IF
Councillor Ingrid FlaubertCommittee Member, present

All 42 on the meeting page

On this subject at Cambridge

Search all
  1. Cambridge Civic Quarter Project UpdateThis decision
  2. Civic Affairs Committee - Cambridge City Council ConstitutionApproved
  3. Civic Affairs Committee: Proposal to Increase the current Cambridge Weighting for Employees and Agency WorkersApproved
  4. Civic Affairs: Council submission to Local Government Boundary Commission for England on new warding arrangement for Cambridge City CouncilApproved

More from Cambridge Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Local Government ReviewFollowing a vote, 12 members voted to note the report, 16 voted against noting the report and 8 abstained. It was con... Noted Open
16 Jul 2026 Councillor Hauk:Improving Accountability and Transparency on Unadopted Residential DevelopmentsRESOLVED to adopt the following motion: Council notes: That many residents move into new developments expecting to be... Approved Open
16 Jul 2026 Councillor Toye Scott: Rights of the River Cam 2026RESOLVED to adopt the following motion: 1 Declaration of the Rights of the River Cam This council declares that the R... Approved Open
16 Jul 2026 Councillor Ashton: Darwin Nurseries and Farm ShopResolved (unanimous) to approve the Darwin Nurseries and Farm Shop Motion. Approved Open
16 Jul 2026 Councillor Baigent: Planning ArrangementsRESOLVED to adopt the following motion: This Council commits to keep building more council homes to the highest quali... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies