Establishment of new loan facilities for Cambridge Investment Partnership

Agreed Committee 2 papers

AI summaryCambridge City Council approves £18.5 million in development loans and £4.677 million in equity loans to Cambridge Investment Partnership LLP for three sites, with interest at 3.5% above the 5-year UK gilt rate.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedNew loan and equity facilities for Cambridge Investment Partnership LLP
Money£18.5 million and £4.677 millionCapital budget for loans and equity loans to the partnership
What happens nextChief Finance Officer to finalise termsDelegated authority to set detailed loan terms with professional advice
Who it affectsThree development sites in CambridgeNewbury Farm, ATS/Murketts Histon Road, and Fanshawe Road

What was decided

Council approved a capital budget of £18.5 million for three development loan facilities to Cambridge Investment Partnership LLP covering regeneration and new build at Newbury Farm, ATS/Murketts Histon Road, and Fanshawe Road. Report P8

Council set a fixed interest rate of 3.5% per annum above the prevailing 5-year UK gilt rate for the loans, set no later than each drawdown date. Report P8

Council approved a capital budget of £4.677 million for equity loan facilities for the same three schemes, with matched equal investment from Hill Investment Partnerships LLP, and delegated authority to the Chief Finance Officer to finalise the loan terms. Report P8

Why

Cabinet unanimously recommended the new loan and equity facilities to Full Council to support regeneration activities and new build development through the partnership. Report P6, P7, P8

The equity loan is structured to be matched by an equal investment from Hill Investment Partnerships LLP, the joint venture partner in Cambridge Investment Partnership. Report P8

What happens next

The Chief Finance Officer will agree the full and detailed terms of the loans with Cambridge Investment Partnership LLP, taking appropriate professional advice and having regard to relevant statutory requirements. Report P8

Interest rates will be set at each drawdown date based on the prevailing 5-year UK gilt rate plus 3.5% per annum. Report P8

The money

  • £18.5 million Capital budget for three development loan facilities to Cambridge Investment Partnership LLP Report P8
  • £4.677 million Capital budget for equity loan facilities to Cambridge Investment Partnership LLP, matched by Hill Investment Partnerships LLP Report P8
  • 3.5% per annum above the prevailing 5-year UK gilt rate Fixed interest rate applied to the development loans Report P8

Options considered

  • Chosen: Approve new loan and equity facilities for Cambridge Investment Partnership LLP. Recommended unanimously by Cabinet to support regeneration and new build at three sites Report P7, P8

Implications

  • Financial: Council commits significant capital to the partnership, with interest income linked to the 5-year UK gilt rate plus 3.5% per annum. Report P8
  • Risk: Council exposure to development risk on three sites through the loan and equity structures, with equity matched by Hill Investment Partnerships LLP. Report P8
  • Legal: Authority to finalise detailed loan terms is delegated to the Chief Finance Officer, who must take professional advice and have regard to relevant statutory requirements. Report P8

Who and where

  • Cambridge Investment Partnership LLP, the council's joint venture with Hill Investment Partnerships LLP Report P8
  • Future residents and users of new build and regeneration schemes at Newbury Farm, ATS/Murketts Histon Road, and Fanshawe Road Report P8

Timeline

  • 25 September 2025: Cabinet unanimously recommended approval of the new loan and equity facilities to Full Council. Report P1, P7
  • 9 October 2025: Full Council approved the recommendations (38 votes to 0, with 2 abstentions).

Plain English for the jargon

  • Cambridge Investment Partnership LLP: A joint venture between the council and Hill Investment Partnerships LLP carrying out regeneration and development in Cambridge.
  • UK gilt rate: The yield on UK government bonds; here the 5-year gilt is used as the benchmark for setting loan interest.
  • Drawdown: The point at which loan funds are actually drawn by the borrower, at which the interest rate is fixed.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/86/CNL

Resolved

Resolved (38 votes to 0, with 2 abstentions) to agree : i. A capital budget totalling £18.5 million for the provision of three new development loan facilities to Cambridge Investment Partnership LLP in respect of regeneration activities and new build development at Newbury Farm, ATS/Murketts Histon Road, and Fanshawe Road. ii. The setting of fixed interest rates applicable to the above loans at 3.5% per annum above the prevailing 5-year UK gilt rate (to be set no later than the date of each drawdown). iii. A capital budget totalling £4.677 million for the provision of equity loan facilities to Cambridge Investment Partnership LLP in respect of the same three schemes, noting that such equity will be matched by an equal investment by Hill Investment Partnerships LLP. iv. The delegation of authority to the Council’s Chief Finance Officer to agree the full and detailed terms of the loan with Cambridge Investment Partnership LLP, after taking appropriate professional advice and with due regard to relevant statutory requirements.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Council

CABINET 25 September 2025 5.00pm - 8.03pm

Present: Councillors Holloway (Chair), Wade (Vice-Chair), Bird, Moore, Nestor, Smart, S.Smith and Thornburrow

In attendance virtually: Councillors A. Smith and Todd-Jones

FOR ADOPTION BY THE COUNCIL

Establishment of new loan facilities for Cambridge Investment Partnership

Cabinet agreed the following recommendation that requires Full Council approval.

Resolved (Unanimous) to recommend that Council approves:

1. A capital budget totalling £18.5 million for the provision of three new development loan facilities to Cambridge Investment Partnership LLP in respect of regeneration activities and new build development at Newbury Farm, ATS/Murketts Histon Road, and Fanshawe Road. 2. The setting of fixed interest rates applicable to the above loans at 3.5% per annum above the prevailing 5 year UK gilt rate (to be set no later than the date of each drawdown). 3. A capital budget totalling £4.677 million for the provision of equity loan facilities to Cambridge Investment Partnership LLP in respect of the same three schemes, noting that such equity will be matched by an equal investment by Hill Investment Partnerships LLP. 4. The delegation of authority to the council’s Chief Finance Officer to agree the full and detailed terms of the loan with Cambridge Investment Partnership LLP, after taking appropriate professional advice and with due regard to relevant statutory requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Establishment of new loan facilities for Cambridge Investment PartnershipReport 102 KB DownloadRead as text
PDF
Loan Facilities for CIP /86/CNLReport 117 KB Download

At this meeting

Whole meeting

Who was there

40 of 42 attended
MA
Councillor Mark AshtonCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
NB
Councillor Naomi BennettCommittee Member, present
TB
Councillor Tim BickCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
IB
Councillor Immy Blackburn-HorganCommittee Member, present
HC
Councillor Hugh CloughCommittee Member, present
JD
Councillor Jamie DalzellCommittee Member, present
MD
Councillor Mike DaveyCommittee Member, present
ID
Councillor Iva DivkovicCommittee Member, apologies
RD
Councillor Robert DrydenCommittee Member, present
IF
Councillor Ingrid FlaubertCommittee Member, present

All 42 on the meeting page

More from Cambridge Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Local Government ReviewFollowing a vote, 12 members voted to note the report, 16 voted against noting the report and 8 abstained. It was con... Noted Open
16 Jul 2026 Councillor Hauk:Improving Accountability and Transparency on Unadopted Residential DevelopmentsRESOLVED to adopt the following motion: Council notes: That many residents move into new developments expecting to be... Approved Open
16 Jul 2026 Councillor Toye Scott: Rights of the River Cam 2026RESOLVED to adopt the following motion: 1 Declaration of the Rights of the River Cam This council declares that the R... Approved Open
16 Jul 2026 Councillor Ashton: Darwin Nurseries and Farm ShopResolved (unanimous) to approve the Darwin Nurseries and Farm Shop Motion. Approved Open
16 Jul 2026 Councillor Baigent: Planning ArrangementsRESOLVED to adopt the following motion: This Council commits to keep building more council homes to the highest quali... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies