Housing Improvement Plan Update

Noted Committee 2 papers

AI summaryCambridge City Council Housing Advisory Board notes an update on the Housing Improvement Plan, with foundational work underway and staffing pressures continuing to affect delivery timescales.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedHousing Advisory Board noted the progress update
MoneyNot stated
What happens nextNext quarter focus areasStock condition procurement, contractor performance, tenant engagement and census
Who it affectsCouncil housing serviceImprovement plan delivery and residents

What was decided

The Board noted the Housing Improvement Plan progress update.

The update was provided by the Business Development Manager for Housing. Report P4

Why

Work is progressing across all major improvement areas, with foundational compliance and asset management activities underway and several early actions completed. Report P1

Resourcing levels are affecting delivery timescales, with staffing changes and the embedding of new roles following the 2025 service transformation causing some actions to fall behind schedule. Report P2

Some actions have required adjustment where further work has been identified, and the Improvement Plan is treated as a live document that will continue to evolve. Report P3

What happens next

Procurement of the stock condition programme in the next quarter. Report P1

Strengthening contractor performance management in the next quarter. Report P1

Advancing tenant engagement and census workstreams in the next quarter. Report P1

Implications

  • Staffing: Staffing changes and the embedding of new roles after the 2025 service transformation have caused some actions to fall behind schedule, with some timeframes revised as a result. Report P2
  • Risk: The Improvement Plan is a live document and will continue to evolve as new information and requirements emerge, with some actions adjusted where further work is identified. Report P3

Who and where

  • Council tenants, through tenant engagement and census workstreams Report P1
  • Housing service staff, affected by ongoing resourcing pressures and new role embedding Report P2
  • Contractors, subject to strengthened performance management Report P1

Timeline

  • 2025: Major housing service transformation took place, with new roles still being embedded Report P2
  • Next quarter (from January 2026 update): Procurement of the stock condition programme, strengthening of contractor performance management, and advancement of tenant engagement and census workstreams Report P1

Plain English for the jargon

  • Stock condition programme: A programme assessing the condition of the council's housing stock, used to plan maintenance and investment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/7/HAB

Resolved

To note the report.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Advisory Board

HOUSING IMPROVEMENT PLAN 2025-26 onwards

A summary of activity and progress to date

Samantha Shimmon -Assistant Director Housing & Health [email protected] Table of Contents Introduction ..............................................................................................................................2 Progress Summary as at January 2026 ...............................................................................3 Completed ........................................................................................................................4 Underway – high priority ................................................................................................4 Still to be started but within timeframes .......................................................................5 Behind schedule / Not completed to timeframes .......................................................5 Summary ..........................................................................................................................6

1 Introduction

In June 2025, the Housing Service underwent an inspection by the Regulator. Prior to this, the service had carried out a self-assessment against the Consumer Standards and commissioned a mock inspection in March 2025 to identify areas for improvement. An Improvement Plan was developed based on these reviews.

The Regulator awarded a C2 grading, with key issues relating to stock condition survey coverage, outstanding medium-risk fire safety remedial actions, and concerns about the accuracy and storage of compliance data.

Following the inspection, the Housing Leadership Board updated the existing Improvement Plan to incorporate the Regulator’s recommendations. The plan is delivered by the Housing Improvement Group—comprised of operational and support service managers—and overseen by Housing Leadership Board, which receives quarterly progress and risk reports.

The Housing Advisory Board will also receive quarterly summary updates on delivery progress going forward.

2 Progress Summary as at January 2026

The Improvement Plan brings together actions identified through the service’s self-assessment, external reviews, and the Regulator’s inspection findings.

TYPE OF ACTIVITY

Task Process review 39% 22%

project 39%

These activities fall into three categories:

• Task – a one-off piece of work that can be delivered within current resource levels. • Process review – a planned piece of work requiring input from both service representatives and supporting teams to evaluate current workflows and deliver efficiencies. • Project – a piece of work that requires input from several services to deliver a specific goal.

with the current plan being weighted towards more complex, multi-service projects. Some of these projects are already underway, but a number still require scoping and resourcing. Progress is overseen by the Housing Leadership Board, with regular monitoring of risks and opportunities.

3 Completed

A number of key foundational actions have already been delivered, strengthening compliance, governance, reporting, and tenant involvement. Completed activities include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
7. Housing Improvement Plan: progress update to HAB: Jan2026 /7/HABReport 381 KB DownloadRead as text
PDF
Housing Improvement Plan UpdateReport 126 KB Download

At this meeting

Whole meeting

Who was there

9 of 12 attended
RR
Councillor Richard RobertsonCo-Chair, present
DM
Diana MinnsCo-Chair, present
GB
Councillor Gerri BirdCommittee Member, present
JG
Councillor Jenny Gawthrope WoodCommittee Member, present
TG
Councillor Tim GriffinCommittee Member, apologies
NL
Councillor Nadya LokhmotovaCommittee Member, present
AM
Councillor Anthony MartinelliCommittee Member, present
ET
Councillor Elliot TongCommittee Member, present
DB
Diane BestCommittee Member, present
MP
Mandy Powell-HardyCommittee Member, present
IM
Isabella-Jowita MiszkCommittee Member, expected
RW
Renata WaisCommittee Member, expected

On this subject at Cambridge

Search all
  1. Housing Improvement Plan UpdateThis decision
  2. Housing Improvement Plan - June UpdateNoted
  3. Housing Improvement PlanNoted
  4. Procurement of Contractor(s) to Deliver Energy Efficiency Improvements and Works to Reduce Carbon Emissions From Council HousingApproved
  5. Housing Repairs Improvement planRefused

More from Cambridge Housing Advisory Board

All decisions
MeetingDecisionOutcome
15 Jun 2026 Election of Co-Chair (Councillor)(i) That Councillor Haithcock be elected Co- Chair (Councillor Side) of the Housing Advisory Board for the ensuing Mu... Decided Open
15 Jun 2026 Appointment of Independent MemberThat the Assistant Director for Housing and Health be requested to submit a written report to the next meeting on the... Decided Open
15 Jun 2026 Housing Advisory Board Terms of ReferenceThat the Housing Advisory Board Terms of Reference be approved. Approved Open
15 Jun 2026 New Build Working Group – New Build Repairs and Maintenance After the Defects Period( i ) That the following Housing Advisory Board Members be appointed to the New Build Working Group: · Councillors: D... Decided Open
15 Jun 2026 Housing Improvement Plan - June UpdateResolved : ( i ) To note the report. (ii) That a Glossary of Acronyms and their meaning be included in future reports. Noted Open