AI summaryCambridge City Council Housing Advisory Board noted a report on lifts in council housing, recording 144 breakdowns in the past year, and asked for a detailed follow-up on repair times and supply issues.
Written from the decision and the officer reportPDF Pro
OutcomeNotedDetailed report on breakdowns, repair times, supply issues requested
MoneyNot stated
What happens nextNew Municipal YearDetailed report to come to Housing Advisory Board
Who it affectsCouncil housing tenantsResidents in HRA properties using lifting equipment
What was decided
The Board noted the officer report on lifts and lifting equipment in the council's housing stock. Report P3
The Board requested a further report with detailed information on lift breakdowns, average repair times, supply issues and Ironworks, to be submitted in the new Municipal Year.
Why
The original report was requested by the Board to increase knowledge and understanding of passenger lifts and other lifting equipment in the council's HRA properties. Report P3
Officers noted that long repair times and parts lead-ins can cause inconvenience and stress to residents, and the Board wanted more detail on this. Report P22, P21
What happens next
A further report covering breakdowns, average time to repair, supply issues and Ironworks is to be requested and submitted to the Housing Advisory Board in the new Municipal Year.
Options considered
Chosen: Note the report and request a more detailed follow-up. To get more detail on breakdowns, repair times, supply issues and Ironworks
Implications
Legal: Lifting equipment must comply with the Lifting Operations and Lifting Equipment Regulations 1988 (LOLER), with thorough examinations by HSB. Report P14, P15, P17
Risk: Not all LOLER inspections on through-floor lifts, hoists and other specialist equipment have been carried out in the past, though these are now being implemented via the HSB contract. Report P18
Other: A 24/7 emergency response is included in the lift servicing contract, with a maximum two-hour attendance for breakdowns and one hour for trapped-person calls. Report P20
Who and where
Tenants in the council's HRA properties who use passenger lifts, platform lifts, through-floor lifts, hoists, stairlifts and specialist bathing equipment Report P4, P5, P7
Residents who have used the emergency call-out service for lift breakdowns or entrapments Report P20, P21
Timeline
From January 2026: Orona Lifts will service and maintain lifts installed in recent new build housing schemes, replacing Direct Lift Company for new stock. Report P13
2026-02-02: Housing Advisory Board noted the lift report and requested a further detailed report for the new Municipal Year.
Next replacement due: 2027: Two Kingsway blocks (installed 1960) are the earliest passenger lifts due for replacement in the schedule. Report P27, P31
Plain English for the jargon
HRA: Housing Revenue Account, the account that holds income and spending on the council's own housing stock.
LOLER: Lifting Operations and Lifting Equipment Regulations 1988, the legal framework requiring thorough examinations of lifting equipment.
HAB: Housing Advisory Board, the Cambridge City Council committee considering this report.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/8/HAB
Resolved
Resolved : ( i ) To note the report. (ii) T hat a report with detailed information on lift breakdowns, the average time for repair, supply issues and Ironworks would need to be requested and submitted to the Housing Advisory Board in the new Municipal Year.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Purpose The report has been requested by Housing Advisory Board to increase the knowledge and understanding of the passenger lifts and other lifting equipment that are currently operational in the Council’s HRA properties.
Lift Assets The Council currently has a range of lifts and other lifting equipment in the housing asset portfolio. See table below for details:
Type of lift Number Passenger and platform lifts 69 Through floor lifts 9 Hoists 34 Stairlifts 91 Specialist baths / other lifting equipment tbc
The number of lifts in the housing stock has increased in recent years because of the new build housing programme. Planning regulations require new blocks of flats to have lifts installed to improve accessibility.
The Council also installs lifting equipment as part of the disability adaptations programme. This includes stairlifts, through floor lifts, hoists and other specialist equipment.
Condition and lifecycles Passenger lifts are expected to have a 30-year lifecycle. The current housing capital investment plan makes provision for lifts to be replaced when they are 30 years old. Most of the lifts in the housing portfolio are relatively new and in good condition.
1 Will Barfield –lift report for HAB – draft 16 1 26
Maintenance and servicing arrangements for lifts Lifts and lifting equipment on housing estates are subject to regular servicing and inspection. Contractual arrangements are in place so that lifts have planned servicing and maintnenace carried out on a regular basis.
Type of lift Contractor Passenger and platform lifts TSG Building Services / EMS lifts Through floor lifts EMS Lifts Hoists EMS lifts Stairlifts EMS Lifts / Stannah Specialist baths / other equipment Various
Lifts installed in new build housing are usually serviced and maintained by the housing developer for the first twelve months, before being added to the TSG Building Services contract.
TSG Building Services sub-contract lift servicing and maintnenace to specialist sub- contractors. Most lifts are serviced by Direct Lift Company. From January 2026 all lifts installed in recent new building housing schemes will be serviced and maintained by Orona Lifts. Most of our new building housing schemes are fitted with Orona lifts.
Lift Compliance Lifting equipment must comply with the Lifting Operations and Lifting Equipment Regulations 1988 (LOLER). These require that lifts are subject to “thorough examinations” carried out by specialist contractors. This happens alongside regular servicing contracts. The Council contracts “thorough examinations” to a company call HSB and these are procured via the Council’s insurance team.
a. Passenger lifts All LOLER inspections for passenger lifts are up to date and compliant with legislation. A Council Officer in the Risk and Compliance team in City Services
2 Will Barfield –lift report for HAB – draft 16 1 26
Group receives all thorough examination reports, and ensures that actions are followed up liaising with the planned maintenance contractor.
b. Through-floor lifts and hoists and other specialist equipment Through-floor lifts and hoists have an annual service and require regular LOLER inspections. Not all LOLER inspections have been carried out in the past, but these are now being implemented through the Council’s contract with HSB.
c. Stairlifts Stairlifts have an annual service only; a LOLOR inspection is not usually required.
Breakdowns / Complaints There is a 24/7 emergency response services for all lift breakdowns included in the lift servicing contract. The contract requires attendance to site within a maximum of two hours for lift breakdowns and repair, and within a maximum of 1 hour for all ‘person trapped’ calls.
In the past 12 months, TSG Building Services have responded to 144 callouts for lift breakdowns. In addition, there have been five emergency call outs relating to people trapped in lifts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of Co-Chair (Councillor)(i) That Councillor Haithcock be elected Co- Chair (Councillor Side) of the Housing Advisory Board for the ensuing Mu...
Appointment of Independent MemberThat the Assistant Director for Housing and Health be requested to submit a written report to the next meeting on the...
Housing Improvement Plan - June UpdateResolved : ( i ) To note the report. (ii) That a Glossary of Acronyms and their meaning be included in future reports.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.