City Centre Heat Network

Agreed Scrutiny 3 papers

AI summaryCambridge scrutiny committee backed the next stage of a city centre heat network, recommending Cabinet release £0.6m from the Climate Change Fund and bid for around £20m from the Green Heat Network Fund to develop a council-led 51% joint venture.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedRelease £0.6m, develop JV objectives, apply for grant
Money£0.6m and ~£20mClimate Change Fund release and GHNF grant bid
What happens nextCabinet 24 March 2026Final report targeted by March 2028
Who it affectsCity centre institutions and residentsColleges, universities, council buildings, future expansion

What was decided

The Committee supported the proposals to release £0.6m from the Council's Climate Change Fund reserve, develop strategic objectives for a council-led joint venture with 51% council ownership, and apply for approximately £20m from the Green Heat Network Fund. Report P3

The Chair will recommend to Cabinet that project risks be kept under review and regularly reported as the project progresses, with proactive communications highlighting the project's ambition and innovation, including to national or international audiences.

The Chair will also recommend learning lessons from previous local and national projects, having mitigation strategies for city centre disruption, and consistently engaging councillors representing affected wards if construction proceeds.

Why

The project would deliver an estimated 93% carbon emissions reduction (c. 506,000 tonnes of CO2) over a 40-year lifetime and cut gas use by c. 2.5 million m³, supporting the Council's net zero aim and improving city centre air quality. Report P6, 2.4, P59

A communal heat network is modelled as around 15 to 20% more cost effective than individual institutional decarbonisation over 40 years, and saves the Council about £1m in capital cost versus decarbonising four strategic assets on their own. Report 2.5, P27

Nineteen of the twenty academic partners have expressed in-principle support as customers, and seven have expressed interest in potential joint investment with the Council. Report P15

What happens next

Cabinet will consider the recommendations on 24 March 2026, including the £0.6m Climate Change Fund request which is subject to Net Zero Programme Board and Cabinet Member approval. Report 1.1, 7.8

Officers will apply to the next Green Heat Network Fund round, expected to open in March/April 2026, with outcomes anticipated in September/October 2026, and will start market testing and procurement of a specialist delivery and management contractor. Report 7.8, 2.11, 5.3

A further report will be brought to Cabinet and Full Council no later than March 2028 on final investment proposals, with the final proceed-or-not decision also needing Shadow Authority scrutiny if Local Government Reorganisation proceeds. Report 2.12

The money

  • £0.6m Release from Climate Change Fund reserve for pre-commercialisation next steps Report P3, 7.8
  • approximately £20m Targeted grant application to the Green Heat Network Fund Report P3, 7.3
  • c. £121m Total estimated cost of the Minimum Viable Product heat network Report 2.3, 7.1
  • £8.1m Council's direct capital cost in current proposals Report P7
  • £18.4m Council on-lending to finance the project Report P7, 2.6
  • £70.5m Connection costs (£4.1m Council, £66.4m other customers at current value) Report 2.6
  • £19.7m Grant element of the £121m cost Report 2.6
  • £7.9m Equity funding (£4m Council and £3.9m from other investors) Report 2.6
  • c£50-100,000 Expected underspend carried forward from the DPD Study to subsidise pre-commercialisation
  • £180,000 Original funding approved by Environment Scrutiny Committee in June 2023 to develop the Outline Business Case Report 3.1

Options considered

  • Chosen: Council-led Joint Venture with 51% council ownership and Academic Partners. Shares construction, delivery and reputational risk; allows lower-cost financing; balances reduced connection charges, return on investment, long-term control and expansion potential; modelled post-tax equity IRR of 12%. Report 2.8, P30, P31
  • Rejected: 100% council-owned Special Purpose Vehicle. All construction, operational and reputational risk would sit with the Council, which is not recommended for further consideration during the Commercialisation Stage.
  • Rejected: Private-sector Concession model. Expected to increase tariff costs over time and disincentivise connections; would reduce Council control. To be reconsidered as a viable alternative only if a Joint Venture is not progressed.

Implications

  • Climate: Estimated 93% carbon emissions reduction (c. 506,000 tonnes CO2) and c. 2.5 million m³ gas reduction over 40 years; linked biodiversity improvements targeted at 20%. Report P6, 2.4, P59
  • Financial: Project is fully reliant on a successful Green Heat Network Fund bid to be viable; sensitivity testing assumes a worst-case 30% cost overrun can still meet return hurdle rates. Report 7.3, 7.4
  • Risk: Key risks include construction and partner-engagement risk, financial and borrowing risk, planning and highways disruption, and high archaeological risk in the city centre, with early engagement and contingencies in place. Report P5, P61, P62, P63
  • Legal: Planning permissions will be required; specialist legal advice is appointed for project delivery and delivery vehicle establishment, and final investment decision is subject to formal legal agreements. Report P61, 8.1
  • Equalities: No direct equalities impacts arise at this commissioning stage; a full Equality Impact Assessment will be undertaken if the project moves to options or interventions, given the uneven distribution of health impacts from poor air quality and climate change. Report 9.8, P84, 9.7
  • Other: Social Internal Rate of Return modelled at 47.9% post-grant, well above the 3.5% target, with strategic added value planned through reinvestment into the network, fuel poverty work and education/training. Report 9.4, 9.5
  • Staffing: The currently procured specialist team (Sustainability Co, Buro Happold, Amberside Advisors, Sharpe Pritchard, National Wealth Fund) is proposed to be retained through pre-commercialisation under compliant procurement procedures. Report 3.2, 11.1

Who and where

  • Twenty Academic Partners (colleges, Cambridge University, ARU), of which 19 have expressed in-principle customer support and 7 interest in joint investment Report 3.2, P15
  • Cambridge City Council itself, particularly the four strategic assets: Guildhall, Corn Exchange, Parkside Swimming Pool and Kelsey Kerridge Report P27
  • Cambridgeshire County Council, which is a Partner to the project and has been significantly engaged Report 3.2
  • City centre businesses, commercial property owners and residents, including future infill residential connections once a core network is active Report P39, 9.9, P62
  • A future Shadow Authority, if Local Government Reorganisation proceeds, which will need to scrutinise and agree the final proceed-or-not decision by March 2028 Report 2.12

Timeline

  • June 2023: Environment Scrutiny Committee approved £180,000 to develop the Outline Business Case Report 3.1
  • 24 March 2026: Cabinet to consider the next-stage recommendations and the £0.6m Climate Change Fund request Report 1.1
  • March/April 2026: Next Green Heat Network Fund bidding round expected to open Report 7.8
  • September/October 2026: Expected outcome of Green Heat Network Fund application Report 7.8
  • 2030 to 2032: Phase 1 of network installation proposed Report P25, P50
  • 2032 to 2035: Phase 2 of network installation proposed Report P25, P50
  • no later than March 2028: Final report to Cabinet and Full Council on whether to proceed with council investment, subject to Shadow Authority scrutiny if Local Government Reorganisation proceeds Report 2.12

Plain English for the jargon

  • DPD: Detailed Project Development, the study stage following the Outline Business Case
  • MVP: Minimum Viable Product, the initial network configuration proposed at c. £121m covering key partner heat loads
  • JV: Joint Venture, here a council-led 51% council-owned vehicle with Academic Partners
  • SPV: Special Purpose Vehicle, a stand-alone company set up to deliver a specific project
  • GHNF: Green Heat Network Fund, the government grant source being applied to
  • BAU: Business As Usual, the counterfactual scenario of continued gas-based heating
  • IRR / SIRR: Internal Rate of Return / Social Internal Rate of Return, measures of financial and wider social returns
  • LGR / SCO: Local Government Reorganisation and the Structural Changes Order that would create a Shadow Authority
  • DBOM: Design, Build, Operate and Maintain, the type of specialist contractor being procured
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/11/P&A

Resolved

It was agreed that the Chair would recommend to Cabinet that these risks were kept under review and regularly reported on as the project progresses. vii. On Communications, members considered the current approach (focused on partner and stakeholder engagement) and discussed future plans . It was agreed that the Chair would recommend the following to Cabinet: · the need for a proactive and positive communications approach that clearly explains the project and its benefits to local residents , businesses and stakeholders · that the opportunity should not be missed to highlight the level of ambition and innovation of the project to a national or international audience. viii. On Construction , members noted that this was not yet a construction project but discussed possible issues should it move to that stage. It was agreed that the Chair would recommend the following to Cabinet: · the need to learn lessons from previous projects both locally (e.g. retrofit work) and nationally (e.g. other heat networks) · the importance of having mitigation strategies in place to manage disruption in the city centre · the need to consistently engage with councillors especially those representing affected wards. ix. On the recommendations going to Cabinet on 24 March 2026 , the Committee supported the proposals for: · the release of £0.6m from the Council’s Climate Change Fund reserve to fund the next steps · the project to develop the strategic objectives for a council led joint (51% ownership) venture; and for · an application for grant funding of approximately £20m from the Green Heat Network Fund. x. The Cabinet Member thanked the Committee for its considerations and said it was important to note that this was a City Council led project with the aim to decarbonise its own city centre buildings. Working with other city centre institutions made financial sense, could lead to increased carbon emissions savings, and there was an opportunity in the future to extend it to other organisations and potentially residents.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Performance, Assets and Strategy Overview and Scrutiny Committee

Recommendations

1.1Performance, Assets and Strategy Overview and Scrutiny Committee is invited to consider the report and provide feedback to officers and the Cabinet when they consider the matter on 24 March 2026.

1.2Performance, Assets and Strategy Overview and Scrutiny Committee are recommended to note:

1.2.1 Officers are recommending that Cabinet supports the release of £0.6m from the Councils Climate Change Fund reserve to fund the next stage of the project to develop the strategic objectives for a council led joint (51% ownership) venture, apply for grant funding of approximately £20m from the Green Heat Network Fund and to progress procurement to identify and appoint a specialist delivery and management contractor. 1.2.2 Officers are targeting a date of no later than March 2028 to present a final report on recommendations to proceed or not with council investment. With the planned Local Government Reorganisation (LGR), subject to the Structural Changes Order (SCO), it is recognised that this final decision to proceed or not will need scrutiny and agreement from the Shadow Authority. We note that the County Council is a Partner to the current project and has been significantly engaged to date.

1.2.3 The project will be governed through an updated memorandum of agreement in line with that agreed for Detailed Project Development (Appendix 1), including establishment of oversight and Steering groups with partner representation and led by the Council.

1.2.4 If this project is approved at the next stage, no later than March 2028, members should note: I. this is a large infrastructure project, and contains finance, partner engagement, and construction risks (See part 6)

II. This council led proposal, will deliver a rapid decarbonisation in the city centre and significantly improve local air quality by reducing an estimated c. 506,000 tonnes of CO2 (93%) against business as usual and a reduction of c2.5 million m3 of gas usage. Benefits are set out in Part 6.

III. The current proposals suggest that it will cost the council £8.1m of direct capital cost, with the council on lending £18.4m to finance the project. All costs are set out in part 7.

2 2 Executive Summary

2.1Since June 2023 officers have been working with experts and academic partners to develop an Outline Business Case for a Cambridge City Centre Heat Network.

2.2The Detailed Project Development (DPD) has now proposed a network using air source and river source heat pumps supported by a transition to electric boilers from gas boilers to generate energy.

2.3As part of this work, a Memorandum of Agreement was jointly signed with the County, and 19 Academic institutions with significant heating demand in the city centre. Connections to many of these partner heat loads forms the basis of a Minimum Viable Product identified for delivery at a cost of c. £121m.

2.4Compared to business as usual using gas boilers, the proposed district heating network could produce a 93% carbon emissions reduction over a 40 year project lifetime. A heat network would play a significant role in reducing the Council’s emissions as well as key anchor institutions in the centre of Cambridge.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
City Centre Heat NetworkReport 683 KB DownloadRead as text
PDF
Memorandum of Agreement /11/P&AReport 175 KB Download
PDF
Outline Business Case /11/P&AReport 31 MB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
KP
Councillor Katie PorrerChair, present
JG
Councillor Jenny Gawthrope WoodVice-Chair, present
HC
Councillor Hugh CloughCommittee Member, present
JD
Councillor Jamie DalzellCommittee Member, present
MD
Councillor Mike DaveyCommittee Member, present
TG
Councillor Tim GriffinCommittee Member, present
DP
Councillor Dinah PoundsCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present

On this subject at Cambridge

Search all
  1. City Centre Heat NetworkThis decision
  2. Councillor Bick : A Thriving City Centre For AllDecided
  3. City Centre Regeneration SitesApproved
  4. Cambridge City Centre Heat Network: Detailed Project DevelopmentApproved
  5. Councillor Bick: The future of Cambridge city centreDecided
  6. ROD Addressing the Implications for Businesses and the City Centre in the Context of the Coronavrius RestrictionsNoted

More from Cambridge Performance, Assets and Strategy Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Mar 2026 Members ICT UpdateIt was agreed that the Chief Operating Officer would consider with colleagues how best to take things forward particu... Agreed Open
4 Nov 2025 Greater Cambridge Local PlanTo feedback comments to Cabinet . [JG1] Are these a) and b) points relevant or can they be cut out? [JD2] I think the... Decided Open
9 Sep 2025 Minutesthat the minutes of the previous meeting held on 10 June 2025 were agreed as an accurate record. Agreed Open
9 Sep 2025 Cabinet: Update on Budget Setting Consultation 2025-26To note the progress towards the Council’s medium-term savings targets. 2. To request that Cabinet ensure Overview an... Noted Open
9 Sep 2025 Procurement at Cambridge City CouncilTo note the update on the new procurement regime. 2. To request that officers provide councillors with an overview of... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies