25/04383/LBC Market Square

Deferred Planning 1 paper

AI summaryCambridge Planning Committee unanimously defers Market Square listed building consent application, despite officers recommending approval subject to conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredListed building consent deferred to a later meeting
MoneyNot stated
What happens nextApplication to be reconsideredNo date specified in the papers
Who it affectsMarket Square, Peas Hill, Guildhall StreetGrade II listed setts, railings and fountain

What was decided

The committee unanimously agreed to defer the listed building consent application rather than follow the officer recommendation to approve. Report P125

Why

Officers had recommended approval subject to conditions, finding that public benefits outweighed the identified less than substantial harm to heritage assets. Report P125, 10.34, 12.8

Both the Conservation Officer and Historic England objected, with the Conservation Officer identifying a high level of less than substantial harm, particularly around the setts trials which they felt were undertaken too late in the process. Report P21, P59, 6.10, 10.7, 10.9

What happens next

The application will be brought back to a future Planning Committee meeting; the papers do not specify a date or any further work required before reconsideration.

Options considered

  • Rejected: Approve subject to conditions (officer recommendation). Committee chose to defer instead, though specific reasons for deferral are not recorded in the papers. Report P125
  • Chosen: Defer the application. Not stated in the supplied papers.

Implications

  • Legal: The deferral pauses consideration of listed building consent under Section 16 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Report 10.22
  • Equalities: Officers attached significant weight to improved accessibility for people with mobility impairments, a benefit that would be delayed by deferral. Report 10.30, 12.5
  • Other: The wider Civic Quarter project, aiming to reconnect the Guildhall, Market Square and Corn Exchange, is delayed by the deferral.

Who and where

  • Market traders in the existing stalls Report P72
  • Visitors and residents of Cambridge city centre Report P23
  • Users of the Grade II listed Market Square surface, railings and fountain Report 2.2, P76

Timeline

  • 23 March 2026: Member site visit took place Report P9
  • 25 March 2026: Planning Committee deferred the application

Plain English for the jargon

  • Listed Building Consent: Permission required for works that affect a listed building or structure, considered under the Planning (Listed Buildings and Conservation Areas) Act 1990.
  • Less than substantial harm: A category of harm to a heritage asset used in the National Planning Policy Framework, to be weighed against public benefits.
  • Setts: The small stone blocks forming the paved surface of Market Square, which is Grade II listed.
  • Nem con: No one dissenting; the committee agreed unanimously.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/31/Plan

Resolved

Resolved nem con to defer the application.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning

25/04383/LBC – Market Square, Market Hill, Wheeler Street, Guildhall Street and Corn Exchange Street

Report to: Planning Committee

Lead Officer: Joint Director of Planning and Economic Development

Ward/parish: Market

Proposal: Refurbishment of Market Square, Peas Hill and Guildhall Street, including: provision of cycle parking, erection and siting of replacement fixed and temporary market stalls, refurbishment of Grade II listed setts, works to listed fountain and railings, and additional landscaping, street furniture and associated works

Applicant: Cambridge City Council

Presenting officer: Charlotte Spencer

Reason presented to committee: Land within the ownership of the Council

Member site visit date: 23 March 2026

Key issues: 1. Impact on heritage assets

Recommendation: Approve subject to conditions Report contents Document Document heading section 1 Executive summary 2 Site description and context 3 The proposal 4 Relevant site history 5 Policy 6 Consultations 7 Third party representations 8 Member representations 9 Local groups / petition 10 Heritage assets 11 Planning balance 12 Recommendation 13 Planning conditions Table 1 Contents of report

1. Executive summary 1.1. The application forms part of the wider Civic Quarter project which aims to reconnect the Guildhall, Market Square, Corn Exchange and surrounding public realm. Importantly, the project aims to reimagine Market Square to create a more inclusive, pedestrian friendly environment that will enhance the civic heart of Cambridge. It includes several key interventions, including relaying listed setts to make them more accessible, the removal of one set of railings and repair works the fountain. In addition, works are required to facilitate the installation of fixed and demountable stalls. The Market Square surfacing and the two sets of railings are Grade II Listed. The fountain is also Grade II Listed under a separate listing.

1.2There is no dispute that the area is run down and is a poor reflection on the City and role of the Market Square as a focal point for its residents and visitors. In particular, the Market Square’s listed setts are unlevel, are not easily navigable for all users and become a slip hazard in wet weather. There is also little planting within Market Square itself, resulting in a predominantly hard surfaced environment.

1.3Improvements and significant investment into this important civic space environment are therefore acutely needed to future proof the space as a matter of civic pride, recreating and reinvigorating the Market Square and its surrounds into a more welcoming and inclusive destination. 1.4. The market area is within a heritage context of the highest significance in Cambridge. The proposal seeks to lift, treat and re-lay the listed setts within Market Square. The principle of this alone would result in harm to the heritage asset. Because of this, considerable discussions have taken place between the applicant, the Local Planning Authority and Historic England regarding this part of the proposal and the level of work done by the applicants is acknowledged. However, some of the investigative work, namely the trials of the setts, have been undertaken at a very late stage in the application process. Whilst not fully settled, the latest trial setts demonstrate to officers their heritage significance can be adequately respected whilst simultaneously performing a better role as a more accessible surface.

1.5Further trials will continue to ease the concerns of Historic England and Conservation Officers. Whilst Historic England feel they are in a position where they are unable to fully assess the level of harm, the Conservation Officer has identified a high level of ‘less than substantial harm’. It is recognised that further trials could reduce the perceived harm prior to any decision being made. However, officers are confident that a solution that is more agreeable to all parties can be found through a suitably worded condition.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/04383/LBC Market SquareReport 294 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
MS
Councillor Martin SmartChair, present
KT
Councillor Katie ThornburrowVice-Chair, apologies
RD
Councillor Robert DrydenCommittee Member, apologies
IF
Councillor Ingrid Flaubert Lib Dem (Spokes)Notify
TG
Councillor Tim GriffinCommittee Member, present
MH
Councillor Matthew Howard Green (Spokes)Committee Member, present
BI
Councillor Bob IllingworthVice-Chair, present
MT
Councillor Mike Todd-JonesCommittee Member, present

On this subject at Cambridge

Search all
  1. 25/04383/LBC Market SquareThis decision
  2. 21-00484-LBC, The Guildhall, Market St, Cambridge - 12:30pmDecided

More from Cambridge Planning

All decisions
MeetingDecisionOutcome
4 Nov 2026 26/02186/FUL Coldham's Common, Pool Way, Whitehill RoadResolved (by 7 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 25/04187/FUL Hanover Court and Princess CourtResolved (by 4 votes to 3) to grant the application for planning permission in accordance with the Officer recommenda... Agreed Open
24 Jun 2026 25/03323/FUL 73 Newmarket RoadResolved (4 votes to 4 – and on the Chair’s casting vote) to grant the application for planning permission in accorda... Agreed Open
24 Jun 2026 26/01081/FUL 9, 11, 15 and 17 Ashfield RoadResolved (by 6 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 26/01400/FUL 1, 2, 3, 4, 11, 12 The GreenResolved (by 5 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open