Planning, Wednesday 25 March 2026 at 10.00am

25/04385/LBC Guildhall

Decided Planning 1 paper

AI summaryCambridge City Council's Planning Committee has granted listed building consent for major refurbishment of the Guildhall, including a fourth floor extension, rooftop plant, and solar panels, against an objection from Historic England.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedListed Building Consent granted by 4 votes to 0 with 1 abstention
Money£103,100 estimated annual rentFrom the new fourth floor extension, per Planning Statement table 3
What happens nextNot stated
Who it affectsThe Guildhall, Market HillGrade II listed building in the Market ward

What was decided

The Planning Committee approved listed building consent for installation of roof plant and screening, refurbishment of internal and external fabric, installation of PV panels, alterations to rooms and walls, and fourth floor and basement extensions of the Guildhall. Report P6, P12, 1.3

Approval was given subject to the recommended conditions, with delegated authority to officers to make minor amendments to the conditions as drafted, including the amendment to conditions. Report 12.2, P155

Why

Officers concluded that the overall harm to the listed buildings amounts to a moderate level of less than substantial harm, caused by the rooftop plant and screening, Council Chamber alterations, Strong Room changes and upper floor wall removals. Report 10.41, P134, 11.2

Officers considered that harm was justified and outweighed by public benefits, including a 65% reduction in energy use, a 55% reduction in water use, bringing the building back into council use, and improved accessibility. Report 1.6, 10.52, 10.53, 11.3

Officers rejected Historic England's objection on the rooftop plant layout, noting that spreading plant more widely would require removing the fourth floor extension, which would cut a potential 20% of surplus revenue and harm cashflow for frontline services. Report 6.15, 10.12, 10.43

What happens next

A photographic building record of the interior, including graffiti in basement court cells, must be provided to the Local Planning Authority and County Records Office before any works begin. Report P162, P163

No demolition or wall removals may take place until contracts for the construction and fitting-out works have been submitted to and approved by the Local Planning Authority. Report P160, P161

A series of detailed design submissions covering external works, cleaning methods, MEP plant, secondary glazing, chamber furniture, the new chamber floor, AV equipment, the Small Hall bar and platform lifts must be approved in writing before installation. Report P164, P167, P169, P171, P174, P176, P178, P181, P183, P185

The money

  • £103,100 Estimated annual rent from the proposed fourth floor extension, per table 3 of the Planning Statement Report 10.12, 10.43

Options considered

  • Chosen: Approve subject to conditions, as recommended by officers. Officers considered the public benefits outweighed the moderate level of less than substantial harm identified Report P12, 10.53, 11.4
  • Rejected: Spread the rooftop plant over a wider roof area to reduce bulk, as suggested by Historic England. Would require removing the fourth floor extension, cutting an estimated 20% of surplus revenue and not necessarily removing the need for screening Report 6.12, 10.12, 10.43

Implications

  • Climate: The scheme aims for a 65% reduction in energy use and is positioned as a pilot for the UK Net Zero Carbon Standard, with PV panels on the Large Hall roof and a fourth floor extension. Report 1.6, 10.14, 11.3
  • Legal: The works require compliance with conditions covering a building record, contracts in place, external works, cleaning methods, MEP plant, glazing, chamber fittings, AV, the Small Hall bar and platform lifts, to protect the Grade II listed building. Report P157, P160, P162, P164, P167, P169, P171, P173, P174, P176, P178, P181, P183, P185
  • Equalities: The scheme improves accessibility, including a platform lift at the Market Hill entrance hall, a height adjustable floor and dais lift in the Council Chamber, and a platform lift to the Large Hall stage. Report 1.6, P32, 3.3, 10.22, 10.52
  • Financial: Removing the fourth floor extension would reduce potential surplus revenue by an estimated 20%, with a negative impact on cashflow for frontline services and building improvements. Report 10.12, 10.43
  • Other: Officers assessed the net heritage impact as a moderate level of less than substantial harm, weighed against identified public benefits under NPPF paragraph 215. Report 10.41, 10.51, 10.52, P134

Who and where

  • Cambridge City Council as applicant, owner and future occupier of the building Report P7, P9
  • Current and future council staff using the building as offices Report 1.2, 2.2, P32
  • Members of the public using the Council Chamber, café, halls and Tourist Information Centre Report 2.2, P32, 10.52
  • Historic England, which objected to aspects of the scheme Report P22, 6.10, 6.15
  • The Conservation Officer, who raised no objection subject to conditions Report P21, 6.8, 6.9
  • Future commercial tenants of the upper floors, whose final layouts are yet to be determined Report 10.48, P116

Timeline

  • 2024: Pre-application engagement under Planning Performance Agreements began
  • 23 March 2026: Member site visit took place Report P10
  • 25 March 2026: Planning Committee considered and approved the application
  • Three years from the date of consent: Works must be begun before this date, under section 18 of the Planning (Listed Building & Conservation Areas) Act 1990 Report P157

Plain English for the jargon

  • Less than substantial harm: A category of harm to a heritage asset's significance, defined in NPPF paragraph 215, which must be weighed against the public benefits of a proposal.
  • Listed Building Consent: Permission required under the Planning (Listed Buildings and Conservation Areas) Act 1990 to carry out works that affect the special architectural or historic interest of a listed building.
  • EnerPhit: A retrofit standard for existing buildings derived from the Passivhaus energy efficiency standard, referenced in the report as the basis for the energy targets.
  • 5 Wat01 credits: A water efficiency credit benchmark under the BREEAM sustainability scheme, with 5 credits representing a 55% reduction in water use as cited in the report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/33/Plan

Resolved

Resolved (by 4 votes to 0 with 1 abstention) to grant the application for Listed Building Consent in accordance with the Officer recommendation, for the reasons set out in the Officer’s report, and subject to the conditions recommended by the Officer (with delegated authority to Officers to make minor amendments to the conditions as drafted) including the amendment to conditions.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning

25/04385/LBC – The Guildhall and Large Hall, Market Hill, Cambridge

Application details

Report to: Planning Committee

Lead Officer: Joint Director of Planning and Economic Development

Ward/parish: Market

Proposal: Installation of roof plant and screen, refurbishment and enhancement of internal and external fabric including installation of PV panels, alterations to internal fabric, rooms and wall positions, and fourth floor and basement extensions of the Guildhall

Applicant: Cambridge City Council

Presenting officer: Charlotte Spencer

Reason presented to committee: Land within the ownership of the Council

Member site visit date: 23 March 2026

Key issues: 1. Impact on Heritage Assets

Recommendation: Approve subject to conditions.

Report contents Document Document heading section 1 Executive summary 2 Site description and context 3 The proposal 4 Relevant site history 5 Policy 6 Consultations 7 Third party representations 8 Member representations 9 Local groups / petition 10 Heritage assets 11 Planning balance 12 Recommendation 13 Planning conditions Table 1 Contents of report

1. Executive summary 1.1 The application forms part of the wider Civic Quarter project which aims to reconnect the Guildhall, Market Square, Corn Exchange and surrounding public realm. The project aims to create an inclusive, attractive destination that enhances the civic heart of Cambridge. The applicants have engaged with the Local Planning Authority through numerous pre-applications under Planning Performance Agreements (PPAs) starting in 2024 and leading up to the formal submission of the application.

1.2The application aims to reinstate the Guildhall as the main civic and office space for Cambridge City Council whilst also future proofing the building in light of the Local Government Reform and proposed Unitary Authorities. The proposals aim to make the Guildhall an exemplar in sustainability with a Net Zero aspiration; to provide sufficient modern office desk space; to ensure the core civic functions can be met; and aim to provide a range of commercial income generating uses.

1.3The application seeks listed building consent for installation of roof plant and screen, refurbishment and enhancement of internal and external fabric including installation of PV panels, alterations to internal fabric, rooms and wall positions, and fourth floor and basement extensions of the Guildhall.

1.4Additional information has been submitted to the Local Planning Authority during the course of the application, including the removal of the ramp to the rear entrance, points of clarification added to the plans, alterations to the cycle access and End of Journey facilities and detailed responses to the consultees. Following the amendments, the scheme is broadly supported by consultee responses, however, there remains concern from Historic England in relation to the roof top plant and screening and alterations to the Strong Room, particularly in regard to a lack of justification for the harm created by these elements. 1.5 The Guildhall comprises two separate listed buildings, The Guildhall and the Victorian former Public Library and Town/Assembly Hall (‘the Large Hall’), both are Grade II listed. The proposals would result in a moderate level of less than substantial harm due to the roof top plant and screening, alterations to the Chamber, alterations to the strong room and removal of internal walls. Notwithstanding, the Historic England objection, Officers considered that this harm has been sufficiently justified.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/04385/LBC GuildhallReport 316 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
MS
Councillor Martin SmartChair, present
KT
Councillor Katie ThornburrowVice-Chair, apologies
RD
Councillor Robert DrydenCommittee Member, apologies
IF
Councillor Ingrid Flaubert Lib Dem (Spokes)Notify
TG
Councillor Tim GriffinCommittee Member, present
MH
Councillor Matthew Howard Green (Spokes)Committee Member, present
BI
Councillor Bob IllingworthVice-Chair, present
MT
Councillor Mike Todd-JonesCommittee Member, present

On this subject at Cambridge

Search all
  1. 25/04385/LBC GuildhallThis decision
  2. 21-00484-LBC, The Guildhall, Market St, Cambridge - 12:30pmDecided

More from Cambridge Planning

All decisions
MeetingDecisionOutcome
4 Nov 2026 26/02186/FUL Coldham's Common, Pool Way, Whitehill RoadResolved (by 7 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 25/04187/FUL Hanover Court and Princess CourtResolved (by 4 votes to 3) to grant the application for planning permission in accordance with the Officer recommenda... Agreed Open
24 Jun 2026 25/03323/FUL 73 Newmarket RoadResolved (4 votes to 4 – and on the Chair’s casting vote) to grant the application for planning permission in accorda... Agreed Open
24 Jun 2026 26/01081/FUL 9, 11, 15 and 17 Ashfield RoadResolved (by 6 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 26/01400/FUL 1, 2, 3, 4, 11, 12 The GreenResolved (by 5 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open