Gateway Review Mid-Term Report

Noted Committee 2 papers

Combined Authority Board noted this item on Wednesday 16 October 2024. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

It was resolved to: A Note the findings of the Ministry for Housing, Communities & Local Government (MHCLG) Gateway Review 2 (GR2) Mid-Term Report for the period 2020/21-2025/26. B Note how the Combined Authority is responding to themes from the Gateway Review 2 Mid-Term report. C Note planned next steps prior to submission of the GR2 Final Report in October 2025.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendations

A To note the findings of the Ministry for Housing, Communities & Local Government (MHCLG) Gateway Review 2 (GR2) Mid-Term Report for the period 2020/21-2025/26. B To note how the Combined Authority is responding to themes from the Gateway Review 2 Mid-Term report. C To note planned next steps prior to submission of the GR2 Final Report in October 2025.

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities

X Achieving good growth

X Increased connectivity

X Enabling resilient communities

X Achieving Best Value and High Performance

1. Purpose

1.1The Cambridgeshire and Peterborough Combined Authority Investment Fund (Investment Fund, known as ‘Gainshare’), is a 30-year, £600 million fund that began in 2016/17. It forms part of the Cambridgeshire and Peterborough Devolution Deal. The Combined Authority is required by MHCLG to commission a five-yearly, independent review of the impact that this core funding has made on economic growth in the Cambridgeshire and Peterborough (C&P) region. The current Gateway Review (GR2) covers the period 2020/21- 2025/26. 1.2 The Combined Authority is currently at the mid-way point of GR2, having completed the Mid Term Report. The Mid Term Report was prepared by an Independent Evaluation Panel (IEP) commissioned by the Department for Levelling Up, Housing and Communities (DLUHC, now MHCLG) and led by DLUHC’s consultants SQW. SQW submitted the Mid Term Report to DLUHC in May 2024 which: • provides an overview of progress to date • identifies progress and issues in the delivery of 23 agreed interventions • presents emerging findings from impact evaluations and capacity development research • updates plans for the final evaluation evidence 1.3 The Combined Authority’s timely completion of a comprehensive Mid Term Report will ensure that robust plans and data are in place to support effective, independent Final Report evaluations. 1.4 The paper presented today summarises the Mid Term Report. • Section 2 below explains what the Gateway Review comprises. • Section 3 summarises the key findings from the Mid Term Report. • Section 4 sets out how the Combined Authority is responding to these findings. • Section 5 sets out the next steps to the GR2 Final Report.

2. What the Gateway Review Covers

2.1The overall approach to evaluation for GR2 is set out in the National Evaluation Framework (NEF), finalised by DLUHC in January 2023. The specific approach for Cambridgeshire and Peterborough was then agreed in a Local Evaluation Framework (LEF) produced by the Combined Authority and submitted to DLUHC in July 2023. GR2 consists of a number of different phases of work as shown below: Final Report Local Evaluation Mid-Term Report Framework Due to be Submitted May submitted October Submitted July 2023 2024 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GR2 Mid Term ReportAppendix A 2.2 MB Download
PDF
Gateway Review Mid-Term ReportReport 211 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 23 attended
MC
Matthew CumberbatchCouncil Staff, expected
JG
Janice GottsCouncil Staff, expected
NJ
Dr Nik Johnson Cambridgeshire and Peterborough Combined AuthorityChair, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, present
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, present
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
DJ
Councillor Dennis Jones Peterborough City CouncilCommittee Member, apologies, sent representative
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
AS
Councillor Anna Smith Cambridge City CouncilCommittee Member, apologies, sent representative
BS
Councillor Bridget Smith South Cambridgeshire District CouncilCommittee Member, present
AK
Al Kingsley Business BoardCommittee Member, present
JO
John O'Brien Integrated Care BoardCo-Optee, present

All 23 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Gateway Review Mid-Term ReportThis decision
  2. Gateway Review 2 Final ReportNoted
  3. Strategic Gateway Review of the Ely to Cambridge Corridor StudyNoted

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies