It was resolved to: A Agree the Home Upgrade Grant Phase Two (HUG2) and the Local Net Zero Accelerator (LNZA) Revised Budgets for 2024/25 set out in Table 1 B Note the Revised Budgets for the projects set out in Table 2 agreed under the Executive Director of Place and Connectivity’s delegated authority at the GSENZ Board meeting on 3rd September 2024 C Agree the necessary revisions to the Combined Authority’s Medium-Term Financial Plan
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To agree the Home Upgrade Grant Phase Two (HUG2) and the Local Net Zero Accelerator (LNZA) Revised Budgets for 2024/25 set out in Table 1 B To note the Revised Budgets for the projects set out in Table 2 agreed under the Executive Director of Place and Connectivity’s delegated authority at the GSENZ Board meeting on 3rd September 2024 C To agree the necessary revisions to the Combined Authority’s Medium-Term Financial Plan
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): Enabling resilient communities The GSENZH provides technical assistance and grant administration to support decarbonisation and net zero. Objective 4, Place & Connectivity Business Plan is to deliver the Local Net Zero programmes of work to: i) achieve good growth ii) ambitious skills and employment opportunities and iii) resilient communities. Achieving ambitious skills and employment opportunities
1. Purpose
1.1This report sets out the required revised budgets for all GSENZH programmes and projects following changes to relevant Memorandum of Understandings (MoU’s) following Department of Energy Security & Net Zero (DESNZ) agreed change requests and/or additional grant funding received. 1.2 The expenditure detailed in the tables is fully covered by grant received either in previous years and treated as receipts in advance (RiA) in the accounts or grant funding received this financial year. Where expenditure is detailed for future years, it can be carried forward in line with the MoU or is specifically a grant spread over more than one financial year. 2. Proposal
2.1There is a need for the Board to agree the HUG2 and LNZA budgets as the overall project amounts are outside the Executive Director for Place and Connectivity’s delegated authority of £5 million. For HUG2 the budget is the agreed DESNZ amount for delivery of HUG2 in 2024/25 following the Change Request submitted earlier in the year. Table 1
Revise Original Transfe Revised d Draft Draft 24/25 r to Revised 24/25 24/25 25/26 26/27 Total 24/25 & Expenditur New Future 24/25 Income Net Expenditur Expenditur 25/26 & 26/27 Programme/ e Budget Fundin Years Expenditur Budget Budget e Budget e Budget Expenditure Spend Project £ g £ £ e £ £ £ £ £ £
Follow Combined Authority Board at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.