A. To note the update in this report. ACTIONS: 1. Officers to provide a written update on developer liability and Laragh Homes’ projects. 2. Further details on action steps for ongoing projects facing quality and completion challenges to be provided.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A The Environment and Sustainable Communities Committee is asked to note the update in this report
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s):
1 Achieving good growth – providing the 1400+ homes as agreed by the CPCA and providers, between 2017-2022, in the area of the CA.
2 Enabling resilient communities – providing suitable housing and ensuring communities are robust
1. Purpose
1.1This report is to update Environment & Sustainability Communities Committee members on the progress of the affordable housing programme. Completions are now anticipated by the end of 2025. 1.2 As of the 1 October 2024, 411 units are yet undelivered. 1,033 new homes over all sites have been successfully completed. 131 new units have occurred with the delivery of Block A Northminster, on the 30 September 2024. The current total of units to be delivered will be 1,444.
2. Proposal
2.1To update the members on the progress of the Affordable Housing Programme; providing them with the progress of the sites in the programme. All sites have been visited at least once by the Housing Programme Manager, as part of her monitoring of this programme. 3. Background
3.1The Affordable Housing programme started in 2017; the original objective of the programme was to deliver 2,000 houses by 31 March 2022. 3.2 At the time of drafting this report, 1,033 new homes have been completed with 411 still outstanding (from a total of 1,444 units). The first programme which ended on 31 March 2021 has completed 712 of its 719 total and the second part of the programme has completed 321 homes of its 725 total.
3.324 High Street, Wisbech.
This site is now due to complete in March 2025, as the site has had many issues, such as wall strengthening and weather problems, which has taken longer for the project to proceed to completion. The roofing is due to start in October/November 2024.
These photos are from August 2024, of new internal walls being constructed.
3.4Cross Keys Homes – British Sugar Way
British Sugar Way has been partially occupied, but still many homes require further snagging work before ready for handover. This is being done by a third party, which is taking longer than anticipated, and therefore will be completed by the end of October 2024.
British Sugar Way site. There are about 15 units remaining for completion, on this site.
2 Stanground
CPCA and Cross Keys Homes are near finalising the Stanground grant funding agreement update which states the grant from the Garages site goes to Stanground to help fund the site completion.
Completion is anticipated between late October and early November 2024.
3.5Northminster
This site is proceeding well; here is a sample of the internal décor with open planned living arrangements. Many of the one bed flats have been acquired from the “Build to Rent” scheme. A further photo of the exterior of the building in September 2024. Block A - 131 units were handed over and are ready for occupation at the end of September 2024. Further parts of the site will be completed in stages with further units in Dec/Jan 2025 and then finally in March 2025.
Internal and external photos of Northminster.
3.7Great Haddon
This site is progressing well with a few of the shared ownership units being handed over at the end of September 2024.
3 Units that are completed at Great Haddon, Peterborough.
3.8Wisbech Road, March - Sage Housing.
This site has stated that they are likely to provide handovers to complete by December 2025. This site has suffered many slippages due to weather issues.
Wisbech Road, March site.
Appendices
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ...
Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.