Update on the Affordable Housing Programme

Noted Committee 3 papers

Growth Committee noted this item on Wednesday 29 January 2025. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

A. To note the update on the progress of the previous Affordable Housing Programme from 2017 – 2022. A. To note the update on the report.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Growth Committee

Recommendations

A The Environment and Sustainable Communities Committee is asked to note the update in this report

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s):

1 Achieving good growth – providing the 1400+ homes as agreed by the CPCA in the area of the Combined Authority.

2 Enabling resilient communities – providing suitable housing and ensuring communities are robust

1. Purpose

1.1This report is to update Environment & Sustainability Communities Committee members on the progress of the previous affordable housing programme from 2017-2022. Programme completion is now anticipated by the end of 2025. 1.2 380 units are yet to be delivered. 1066 new homes over all sites have been successfully completed and occupied. The current total of units to be delivered will now be 1446.

2. Proposal

2.1To update the members on the progress of the Affordable Housing Programme; providing them with the progress of the sites in the programme. 3. Background

3.1The Affordable Housing programme started in 2017; the objective of the programme was to deliver 2000 homes. All sites have been visited at least once by the Housing Programme Manager, as part of her monitoring of this programme. The majority of the remaining sites are expected to deliver units by March 2025. Assuming completion as per forecast the Programme is nearly fully allocated, with a small amount available from clawbacks/change in sites. A separate report on the Agenda has a proposal to commit that funding for delivery by March 2025.

3.2Cross Keys Homes, Peterborough

British Sugar Way, Peterborough: The last 15 homes of 70 units have completed at the end of November 2024. The grant has been paid accordingly. Stanground The site is near completion and will be handed over by March 2025. Northminster – Block A 131 properties have been completed and have been well received by the new tenants. Northminster Blocks B and C Are due to complete in the next few months.

3.3Wisbech Road, March with Sage Housing

This site progress is improving now, with services in - power such as electricity and with the heating on, drying doors, skirting board etc.14 shared ownership units at the entrance of the site completed in December and were occupied before Christmas. The anticipated time to complete the whole development is June/July 25.

3.4Heylo - Roman Fields, Peterborough Heylo have completed site sales on Roman Fields from the original Larkfleet sites. There is proposal for a final tranche of units to come in the Affordable Housing Programme. From Heylo. This is in a separate Agenda item.

Appendices

4.1Appendix 1: Affordable Housing Programme – Approved and Started on Site Schemes period up to March 2021. Appendix 2: Affordable Housing Programme – Approved and Started on Site Schemes period April 2021 to March 2022.

5. Implications

Financial Implications 5.1 All grant funding is allocated, with the exception of £231,150 arising from clawback and underspend.

2 Legal Implications 6.1 There are no direct legal implications arising from this report. Public Health Implications 7.1 There are no known public health implications. Environmental & Climate Change Implications 8.1 There are no new Environmental or Climate change implications. Other Significant Implications 9.1 None Background Papers 10.1 None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approved and Started on Site Schemes up to March 2021Appendix 1 170 KB Download
PDF
Approved and Started on Site Schemes period April 2021-March 2022Appendix 2 125 KB Download
PDF
Update on the Affordable Housing ProgrammeReport 147 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 30 attended
JC
Jim CunninghamCouncil Staff, expected
EC
Ed ColmanCouncil Staff, expected
MN
Maxine NarburghCouncil Staff, expected
BS
Councillor Bridget Smith South Cambridgeshire District CouncilChair, present
LD
Councillor Lara Davenport-Ray Huntingdonshire District CouncilVice-Chair, present
NJ
Dr Nik Johnson Mayor, Cambridgeshire and Peterborough Combined AuthorityCommittee Member, present
ND
Councillor Nicola Day Peterborough City CouncilCommittee Member, present, as expected, virtual
LD
Councillor Lorna Dupre Cambridgeshire County CouncilCommittee Member, present
MG
Councillor Martin Goodearl East Cambridgeshire District CouncilCommittee Member, present
ST
Councillor Steve Tierney Fenland District CouncilCommittee Member, present
MT
Councillor Mike Todd-Jones Cambridge City CouncilCommittee Member, present
EG
Emma Garfield Business BoardCo-Optee, apologies

All 30 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Update on the Affordable Housing ProgrammeThis decision
  2. Affordable Housing Programme - Update on ImplementationNoted
  3. Affordable Housing Programme - Update on ImplementationNoted
  4. Acquiring additional units for the Affordable Housing ProgrammeNoted

More from Cambridgeshire and Peterborough Combined Authority Growth Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ... Approved Open
15 Sep 2026 Director's Highlight ReportTo note the content of the report. Noted Open
15 Sep 2026 Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance... Agreed Open
15 Sep 2026 Sage Novation on properties at Wisbech Road, March(Unanimous) A. To recommend to the CA Board to agree to a novation requested by Sage Homes Limited to transfer all th... Agreed Open
15 Sep 2026 Regional Visitor Economy Branding and NarrativeA. To review and endorse the regional destination brand and narrative, developed in partnership with industry and loc... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies