Resolved
The Committee received the report which requested they review the Corporate Risk Register, the risk appetite approach and a deep dive into a specific risk. The Committee
Audit and Governance Committee decided this item on Friday 8 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee received the report which requested they review the Corporate Risk Register, the risk appetite approach and a deep dive into a specific risk. The Committee
A To endorse the Corporate Risk Register, Dashboard and Heatmap B To undertake a deep dive into Future Funding risk C To review the schedule of deep dives D To endorse the risk appetite approach and review the draft statement
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Increased connectivity X Enabling resilient communities X Achieving Best Value and High Performance
1. Purpose
1.1To endorse the Corporate Risk Register, Dashboard and Heatmap, Appendix A-C. 1.2 To undertake a deep dive into Future Funding risk, Appendix D. 1.3 To continue to review the schedule of deep dives in 2.3 1.4 To endorse the risk appetite approach and review the draft statement, Appendix E. 2. Proposal
2.1Risk Register, Risk Dashboard and Risk Heatmap (Appendix A-C) There are fourteen corporate risks on the register as of end of October. All risks have been reviewed with risk leads through our 4Risk software and are reviewed monthly at the Corporate Management Team meeting, most recently on 28 October. Since the previous A&G report there have been some changes to the Corporate Risk Register. These are set out below:
• Climate risk amendments: The risk has been substantially changed, with the risk description, cause and effects all being amended to focus on what CPCA can control. With this, the residual score has been reevaluated from a 12 to a 17. • Financial underspend risk reworked: The risk has been renamed to ‘Failure to deliver work programmes within budget and planned timeframes’. It was assessed that this is the risk that may then lead to failure to deliver timely and effective projects.
Appendix A details the risks in a register format. Appendix B is the risk dashboard which shows the risks by category, proximity and score (inherent, residual and target). Appendix C maps the risks on a heatmap including which are above appetite. There are 14 risks on the Corporate Risk Register. The residual risk scores (risks scores after controls are in place) are:
1 red very high risk 2 amber high risk 9 yellow medium risks 2 green low risks
The 1 very high risk is Future Funding, and this is the only risk above appetite. At the previous A&G meeting it was suggested we map each risk against our corporate objectives. Following this we identified that 9 risks are against Achieving Best Value and High Performance, 1 against Enabling Resilient Communities, 1 against Ambitious Skills and Employment Opportunities and 3 against Improving Connectivity. We will look to add this to appendix A or B for the next meeting.
2.2Risk Deep Dive – Future Funding (Appendix D) The schedule of Deep Dives was agreed at the September Committee, and for Future Funding to be the focus of the November meeting. Supporting documentation is in the appendix and the Risk Owners are available to respond to questions. The Future Funding risk was first identified and added to the register in March 2022. The inherent risk score is Very High with a 5/5 critical impact and 5/5 likely likelihood. The residual score (now that controls are in place) is also Very High, with a 5/5 critical impact and a 3/5 possible likelihood. The target score is high with a 4/5 Major impact and a 2/5 unlikely likelihood. Therefore, due to the controls in place, the likelihood has reduced, but the risk remains above risk appetite. More information on this risk is in Appendix D.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk RegisterAppendix A | 1.7 MB | Download |
PDF |
Corporate Risk DashboardAppendix B | 287 KB | Download |
PDF |
Corporate Risk HeapmapAppendix C | 761 KB | Download |
PDF |
Risk Deep Dive: Future FundingAppendix D | 99 KB | Download |
PDF |
CPCA Draft Risk Appetite StatementAppendix E | 351 KB | Download |
PDF |
Corporate Risk ReportReport | 162 KB | DownloadRead as text |
Follow Audit and Governance Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... | Noted | Open |
| 10 Sep 2026 | Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... | Decided | Open |
| 10 Sep 2026 | Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. | Decided | Open |
| 10 Sep 2026 | Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... | Noted | Open |
| 10 Sep 2026 | CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.