Resolved
The Committee received the report which provided the progress report from the Internal Auditors, RSM. The Committee RESOLVED to note the report.
Audit and Governance Committee noted this item on Friday 8 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee received the report which provided the progress report from the Internal Auditors, RSM. The Committee RESOLVED to note the report.
STRICTLY PRIVATE AND CONFIDENTIAL
CAMBRIDGESHIRE & PETERBOROUGH COMBINED AUTHORITY Internal Audit Progress Report Presented at the Audit and Governance Committee on 8 November 2024 This report is solely for the use of the persons to whom it is addressed. To the fullest extent permitted by law, RSM UK Risk Assurance Services LLP will accept no responsibility or liability in respect of this report to any other party. CONTENTS Key messages ....................................................................................................................................................................................... 3
1 Progress against the internal audit plan 2024/25........................................................................................................................ 5
2 KEY MESSAGES The internal audit plan for 2024/25 was approved by the Audit and Governance Committee at the March 2024 meeting. This report provides an update on progress against the plan and summarises the results of our work to date.
2024/25 Work Programme [To discuss and note] Since the last Committee in September 2024, we have: • finalised one report (Workforce Planning); • one review within the RSM review process, and a draft report will be issued shortly; and • two further reviews in progress Scopes have been issued and dates agreed for the remainder of the 2024/25 internal audit plan.
The summary of 2024/25 programme is also outlined in Section 1 below. The table outlines progress against the internal audit plan and highlights in bold the report issued in final since the previous Audit Committee in September 2024. .
3 Audit Progress
01 4 1. PROGRESS AGAINST THE INTERNAL AUDIT PLAN 2024/25
Assignment Status / Opinion issued Actions agreed Target Committee meeting Actual Committee meeting
L M H
Final Data Quality and Performance 1.24/25 2 3 0 September 2024 September 2024 Reasonable Assurance
Final - Advisory – some significant GDPR 3.24/25 2 9 1 December 2024 September 2024 weaknesses
Final Improvement Plan 4.24/25 0 0 0 December 2024 September 2024 Substantial Assurance
Final Workforce Planning 2.24/25 3 3 0 November 2024 November 2024 Reasonable Assurance
Procurement In RSM QA Processs December 2024 -
Risk Management In Progress December 2024 -
Fraud Risk Assessment In Progress December 2024 -
Staff Mental Health and Wellbeing 2 December 2024 February 2025 -
Key Financial Controls - Creditors 16 December 2024 February 2025
Business Continuity* 8 January 2025 June 2025 -
Follow Up 10 February 2025 June 2025 -
Audit deferred to 2025/26 - IT Systems Development – Stage 1 Replacement audit being June 2025 Change Programme* discussed
5 Changes to the 2024/25 Internal Audit Plan
There has been one substantive change to the 2024/25 Internal Audit Plan. We provided a verbal update at the Audit and Governance Meeting in September 2024 as this was being discussed at that time. Management have requested a delay to the IT Systems Development – Stage 1 Change Programme review from to the 2025/26 Internal Audit Programme due to there being no significant IT systems changes in progress for the audit to review. We are in discussions with management over a replacement audit. We have also rescheduled the Business Continuity review to be undertaken in January 2025, having been originally scheduled in September 2024. This was requested as the Authority’s IT supplier, SOCITM’s contract is about to finish, and this will cause a pause in BCP exercises until a new supplier is in place. Officers confirmed the audit would provide more value once the new arrangements are in place and operating.
Annual Opinion 2024/25
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit: Progress ReportReport | 539 KB | DownloadRead as text |
Follow Audit and Governance Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... | Noted | Open |
| 10 Sep 2026 | Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... | Decided | Open |
| 10 Sep 2026 | Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. | Decided | Open |
| 10 Sep 2026 | Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... | Noted | Open |
| 10 Sep 2026 | CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.