It was agreed that there should be a risk update on bus reform around franchising but also the precept routes which were subject to ongoing legal issues. HUG2 Programme: This programme was delivered by the GSENZ Hub outside of CPCA area and faced challenges in delivery. The primary issues included eligibility criteria, investment caps, and data provision barriers within the terms of the programme. The target had been verbally agreed to be reduced to 925. The supply chain issues had been resolved, but other barriers remained. The shortage of skilled contractors for retrofitting was discussed as a potential reason for delays in the HUG2 programme. Although the supply chain had improved, other barriers such as investment caps, customer drop out and eligibility criteria continued to pose challenges Towns Fund: The towns fund was flagged green overall, but there were delays in three projects. A request was made for more detailed updates in the committee papers. The committee acknowledged the usefulness of the documents in managing risks but noted the difficulty in interpreting standard risk registers. Regular meetings were held to review risks, and there was a need to consider how these were presented publicly and in committee papers. A suggestion was made to include a rating system for progress assessment. The Committee emphasised the importance of clear communication, detailed updates, and ongoing risk management to ensure the success of these initiatives. RESOLVED A The Investment Committee resolved to note the performance report on major projects and risk.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note the Q2 performance report on the Most Complex Programmes and Projects including risks.
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Increased connectivity X Enabling resilient communities X Achieving Best Value and High Performance The SAF is a set of systems and processes designed to provide the CPCA with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes. It is focused on ensuring accountability, probity, transparency and legal compliance – and critically, value for money of investments. It covers the full end to end lifecycle of projects and programmes that place a financial liability on the CPCA.
1. Purpose
1.1To note major projects performance and risk data. 2. Proposal
2.1Most Complex major projects performance data and risks Programmes and Projects are classed as Most Complex when a Combined Authority Funded programme or project is considered most significant in terms of value, strategic fit and where there would be significant impact if there was a failure to deliver. There are six major projects listed: Peterborough Station Quarter University of Peterborough Net Zero Programme Bus Reform Programme Adult Education Provision Market Town Masterplans
Of the major projects three are rated as Green and on target, where there is a high level of confidence in successful delivery: University of Peterborough Adult Education Provision Market Town Masterplans
Two major projects are rated as Amber, where without action, successful delivery may be adversely impacted. For both areas actions have been highlighted within Appendix 1. Peterborough Station Quarter Bus Reform Programme
One major project is rated as Red, where without action, successful delivery is highly unlikely. The details for this and associated actions is set out in Appendix 1. Net Zero programme (Home Upgrade Grant 2)
Further details are available in Appendix A for all schemes listed above setting out the risks and mitigations.
Background
3.1The Combined Authority Single Assurance Management Framework and Procedure was reviewed at Audit and Governance Committee on 8 September and approved at the Combined Authority Board at its meeting on 20 September. Work continues to embed the Framework and Procedure, including through training for officers.
3.2The Framework notes that the Programme Management Office are responsible for ensuring that the SAF process is maintained, updated and that performance and risks are regularly reviewed with the Executive Director of Resources, Corporate Management Team, Investment Committee, Audit and Governance Committee and CPCA Board.
3.3The Investment Committee has the following key functions in support of the Performance Management Framework: to review the Major Projects performance including risk
Appendices
4.1Appendix A. Most Complex Programmes and Projects. 5. Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Funding Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.