Single Assurance Framework Business Case Approvals: Funding Committee Decisions
ApprovedCommittee6 papers
AI summaryFunding Committee to recommend approval of £1,522,000 Local Transport Grant for Peterborough City Council and £3,450,700 for Cambridgeshire County Council for 2026/27 transport improvement schemes.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to Combined Authority Board confirmation
Money£4,972,700 across two councilsDfT Local Transport Delivery Plan capital grant for 2026/27
What happens nextDelivery through eligible schemesMonitored under LTDP and DfT assurance requirements
Who it affectsPeterborough and CambridgeshireHighways authorities and local transport network users
What was decided
The Funding Committee will recommend approval of the 2026/27 Local Transport Grant capital allocations to Peterborough City Council (£1,522,000) and Cambridgeshire County Council (£3,450,700). Report P1
The funding forms part of the Department for Transport's Local Transport Delivery Plan allocation for 2026/27. Report 3.1
The proposal was considered by the Funding Panel on 01 July 2026 and falls within the Funding Committee's SAF delegation for project investments between £2m and £5m. Report 1.1
Why
The grant provides capital funding to highways authorities to deliver smaller-scale transport infrastructure improvements that address local priorities and support connectivity, safety, accessibility and network performance. Report 3.1
The programme responds to continued pressure on the transport network, a significant maintenance and improvement backlog, and the need to support safer, more sustainable and accessible travel choices in Peterborough and Cambridgeshire. Report 3.1
The Combined Authority's Single Assurance Framework provides the system for appraising, assuring and monitoring these project investments, supporting the Corporate Plan 2025-2029 and English Devolution Accountability Framework requirements. Report 2.1
What happens next
Delivery will be undertaken by Peterborough City Council and Cambridgeshire County Council in partnership with the Combined Authority, prioritising eligible schemes deliverable within one to two years. Report 3.1
A standard CPCA grant funding agreement or contract will be devised and issued to deliver the business case outcomes, with the business case progressed under Sections 5.5 and 5.6 of the SAF. Report P11
Programme performance will be monitored through delivery milestones, expenditure, infrastructure outputs, connectivity and accessibility improvements, road safety outcomes, and walking, wheeling and cycling uptake, with quarterly and annual reporting to DfT. Report 3.1
The money
£1,522,000 Local Transport Grant (capital) for Peterborough City Council, 2026/27 Report P1, 3.1
£3,450,700 Local Transport Grant (capital) for Cambridgeshire County Council, 2026/27 Report P1, 3.1
Options considered
Chosen: Approve the 2026/27 Local Transport Grant (capital) allocations for Peterborough City Council and Cambridgeshire County Council. Funded from DfT LTDP allocation, within Funding Committee SAF delegation, and supports the Combined Authority's connectivity strategic objective. Report P1, 1.1, 3.1
Implications
Financial: Financial implications are set out in the main body of the report and the associated business cases (Appendices A and F). Report P10
Legal: A standard CPCA grant funding agreement or contract will be issued to deliver the business case outcomes, in line with SAF Sections 5.5 and 5.6. Report P11
Other: No public health, environmental and climate change, or other significant implications were identified. Report 3.1, P11
Who and where
Peterborough City Council (delivery partner for its share of the grant) Report 3.1
Cambridgeshire County Council (delivery partner for its share of the grant) Report 3.1
Residents, businesses and communities across Peterborough and Cambridgeshire using the local transport network Report 3.1
Timeline
26 November 2025: Combined Authority Board approved the SAF arrangements delegating authority to the Funding Committee. Report 1.1
18 March 2026: Combined Authority Board paper on Local Transport Delivery Plan and Capital Transport Funding. Report 3.1
01 July: Funding Panel considered the proposal. Report 1.1
2026/27: Financial year covered by the Local Transport Grant (capital) allocation. Report 3.1
1 to 2 years: Target delivery timeframe for eligible schemes within the funding period. Report 3.1
Plain English for the jargon
SAF: Single Assurance Framework, the Combined Authority's system for appraisal, assurance, risk and performance across projects.
LTDP: Local Transport Delivery Plan, the Department for Transport's funding programme covering the 2026/27 allocation.
DfT: Department for Transport.
CPCA: Cambridgeshire and Peterborough Combined Authority.
EDAF: English Devolution Accountability Framework, the government standard the Combined Authority is required to meet.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
A. To recommend the approval of the 2026/27 Local Transport Grant (capital) allocations, forming part of the Department for Transport’s (DfT) Local Transport Delivery Plan (LTDP) funding, for delivery by Peterborough City Council (£1,522,000) and Cambridgeshire County Council (£3,450,700), noting that delivery will be progressed through eligible local transport improvement schemes and monitored in accordance with the LTDP and DfT assurance requirements.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To approve the 2026/27 Local Transport Grant (capital) allocations, forming part of the Department for Transport’s (DfT) Local Transport Delivery Plan (LTDP) funding, for delivery by Peterborough City Council (£1,522,000) and Cambridgeshire County Council (£3,450,700), noting that delivery will be progressed through eligible local transport improvement schemes and monitored in accordance with the LTDP and DfT assurance requirements.
1. Purpose
1.1Under the SAF arrangements approved by the Combined Authority Board at its meeting on 26 November 2025, the Funding Committee has delegated authority to approve project investments of between £2m - £5m in total for which the funding is within the approved Medium Term Financial Plan. Over this sum the Funding Committee is requested to make recommendations to the Combined Authority Board. 1.2 Following consideration by the Funding Panel held on 01 July, the Funding Committee is being asked to approve the following proposal: • Local Transport Grant (capital) for Peterborough City Council (£1,522,000) • Local Transport Grant (capital) for Cambridgeshire County Council (£3,450,700)
Background
2.1The CPCA Single Assurance Framework (SAF) is a set of systems and processes designed to provide the Authority with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes.
2.2A local assurance framework is integral to the operation of all Combined Authorities. Further to this, a Combined Authority must have a local assurance framework in place as part of the requirement for an established mayoral strategic authority and in so doing access wider and deeper devolution as well as an Integrated Settlement amongst other opportunities. 2.3 The SAF also offers assurance in the delivery of the Corporate Plan 2025-2029 which sets out the roadmap for the next four years. 2.4 The SAF is subject to annual review as part of good governance arrangements. 2.5 The Framework notes that the Programme Management Office are responsible for ensuring that the SAF process is maintained, updated and that performance and risks are regularly reviewed with the Executive Director of Resources, Corporate Management Team, Funding Committee, Audit and Governance Committee and CPCA Board. 2.6 Management of the Authority’s investment priorities, plans and processes is critical to the successful delivery of its strategic aims and maximising the benefits to the region. To help meet the standards set by Government – such as the English Devolution Accountability Framework (EDAF) – the Authority established a clear Assurance Framework (the SAF) that showed how it would meet best value requirements to ensure it is spending public money in the most effective way.
3. Approvals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Funding Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.