Resolved
The Committee noted the Internal Audit plan for 2025/26.
Audit and Governance Committee noted this item on Friday 21 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee noted the Internal Audit plan for 2025/26.
CAMBRIDGESHIRE & PETERBOROUGH COMBINED AUTHORITY Internal Audit Planning 2025/26
Presented at the Audit and Governance Committee meeting of: 21 February 2025 This report is solely for the use of the persons to whom it is addressed. To the fullest extent permitted by law, RSM UK Risk Assurance Services LLP will accept no responsibility or liability in respect of this report to any other party. Annual Planning Approach 2025/26 Our approach to developing your internal audit plan is based on analysing your organisational objectives, risk profile and assurance framework as well as other factors affecting Cambridgeshire & Peterborough Combined Authority (CPCA) in the year ahead, including changes within the sector. We will discuss audit priorities and coverage with management for 2025/26, and these meetings are being arranged.
Annual Planning Process We have held an initial discussion with Executive Director Resources (S73 Officer) and the Assistant Director Finance to discuss planning for the 2025/26 audit programme. The table below shows an overview of the audit coverage provided to date and also the forward-looking plan for 2025/26 and beyond, based upon the previously agreed 3-year strategy and consideration of the possible areas with management.
We note that we have identified two reviews that management have indicated as reviews that could be undertaken in Quarter 1, so to allow us to make an early start on 2025/26 delivery.
We present the paper today for information. Following the February Committee, we will liaise with the Management Team and the Mayor’s office and discuss areas for inclusion in the plan for 2025/26. Following these meetings exercise we will share and discuss with management a long list of audits, to further refine and prioritise 2025/26 audits. We will also reassess the Authorities risk profile and then bring back the full plan to the Committee in May 2025, for formal review, comments from the Committee and sign off.
Noting the timeframes mentioned above, if the Committee are happy for us to commence with the two proposed areas for Quarter 1 (Declarations of Interest and Climate Change Strategy), we will start to scope these reviews and commence these audits in April and May. We will also be updating the strategy below to align with the latest version of the Authorities Strategic Risk Register following the recent updates to this document.
2 CPCA INTERNAL AUDIT STRATEGY 2021/22 – 2027/28 (Including indicative areas for 2025/26 coverage)
Audit Area 2021/22 2022/23 2023/24 2024/25 2025/26 Future Years
Energy Hub Partial Assurance
Climate Change Strategy
Quarter 1 2025
Environment, Social and Governance (ESG Maturity)
Strategic Planning Reasonable Assurance
HR Digital Processes
Project Planning and Delivery – Reasonable Governance Assurance
Project Planning and Delivery – Reasonable Improvement Plan Assurance
Procurement – Improvement Plan Substantial Assurance
Improvement Plan Substantial Assurance
Local Industry Strategy
11 Audit Area 2021/22 2022/23 2023/24 2024/25 2025/26 Future Years
Local Transport Plan
Skills Strategy
Adult Education Budget Reasonable Assurance
Affordable Housing Programme Partial Assurance
IT Controls / Cyber / IT Systems Partial Advisory Development Assurance
Data Protection / GDPR Advisory Advisory
Declarations of Interest
Quarter 1 2025
Governance
CAM Project – Governance and Advisory Decision Making
Cross Charging of Corporate Services
Subsidiary Company Governance Minimal Reasonable Partial Assurance Assurance Assurance
12 Audit Area 2021/22 2022/23 2023/24 2024/25 2025/26 Future Years
Business Continuity and Disaster Minimal Recovery Assurance
Procurement and Contract Management Partial Assurance
Fraud Risk Assessment Advisory
Capital Programme Reasonable Assurance Budget Setting and Budgetary Control Reasonable Assurance Succession Planning
Staff Mental Health and Wellbeing Reasonable Assurance Equality Diversity and Inclusion
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit PlanReport | 269 KB | DownloadRead as text |
Follow Audit and Governance Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... | Noted | Open |
| 10 Sep 2026 | Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... | Decided | Open |
| 10 Sep 2026 | Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. | Decided | Open |
| 10 Sep 2026 | Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... | Noted | Open |
| 10 Sep 2026 | CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.