Internal Audit - Progress Report

Noted Finance 1 paper

Audit and Governance Committee noted this item on Thursday 19 June 2025. Below is the council's own wording, with the papers it was decided on.

Item10a

Resolved

The Committee noted the Internal Auditor’s progress report.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Audit and Governance Committee

STRICTLY PRIVATE AND CONFIDENTIAL

CAMBRIDGESHIRE & PETERBOROUGH COMBINED AUTHORITY Internal Audit Progress Report Presented at the Audit and Governance Committee on 19 June 2025 This report is solely for the use of the persons to whom it is addressed. To the fullest extent permitted by law, RSM UK Risk Assurance Services LLP will accept no responsibility or liability in respect of this report to any other party. KEY MESSAGES The internal audit plan for 2024/25 was approved by the Audit and Governance Committee (AGC) at the March 2024 meeting. This report provides an update on progress against the plan and summarises the results of our work to date.

2024/25 Work Programme [To discuss and note] Since the last Committee in February 2025, we have: • finalised the three further reports from the 2024/25 Programme • The two final reports remain in draft, awaiting management responses. The summary of 2024/25 programme is also outlined in Section 1 below. The table outlines the outcomes against the internal audit plan and highlights in bold the reports issued in final since the previous Audit Committee in February 2025. This concludes the 2024/25 Internal Audit Plan.

Client Briefings [To note] Five client briefings have been issued since the last meeting and will be circulated in the July 2025 AGC meeting agenda for information: • Failure to Prevent Fraud • Driving Value from AI • Employment Rights Bill • Emerging Risk Radar • Quality Assurance and Improvement Programme

2 Audit Progress 1. PROGRESS AGAINST THE INTERNAL AUDIT PLAN 2024/25 Assignment Status / Opinion issued Actions agreed Target Committee meeting Actual Committee meeting

L M H

Data Quality and Performance 1.24/25 Final - Reasonable Assurance 2 3 0 September 2024 September 2024

Final - Advisory – some GDPR 3.24/25 2 9 1 December 2024 September 2024 significant weaknesses

Improvement Plan 4.24/25 Final - Substantial Assurance 0 0 0 December 2024 September 2024

Workforce Planning 2.24/25 Final - Reasonable Assurance 3 3 0 November 2024 November 2024

Procurement and Contract Management Final - Partial Assurance 2 5 1 February 2025 February 2025 5.24/25

Risk Management 6.24/25 Final - Reasonable Assurance 2 3 0 February 2025 February 2025

Staff Mental Health and Wellbeing Final - Substantial Assurance 0 1 0 February 2025 February 2025 7.24/25

Fraud Risk Assessment Final - Advisory 2 4 0 June 2025 June 2025

Final - Reasonable Key Financial Controls - Creditors 2 3 0 June 2025 June 2025 Assurance

Business Continuity Final - Partial Assurance 2 6 3 June 2025 June 2025

Follow Up - GDPR Draft Report 2 2 0 June 2025 Now July 2025

Follow Up Draft Report 0 9 0 June 2025 Now July 2025

4 APPENDIX A: OTHER MATTERS Detailed below are the changes to the audit plan: There have been no changes to the audit plan since the last AGC meeting.

The previously agreed changes are below:

Note Auditable area Reason for change 1 IT Systems Development – Stage There has been one substantive change to the 2024/25 Internal Audit Plan. We previously provided an update at the Audit 1 Change Programme and Governance Meeting in September 2024 that management requested removal of the IT Systems Development – Stage 1 Change Programme review due to there being no significant IT systems changes in progress for the audit to review. We agreed with management to extend our follow up coverage and utilised this budget to undertake a full follow up of all actions agreed in the GPDR review, reported to the Committee, in September 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit: Progress ReportReport 931 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
DH
David HarwoodIndependent Person, present
MT
Councillor Mike Todd-Jones Cambridge City CouncilSubstitute
GC
Councillor Gary Christy Fenland District CouncilCommittee Member, apologies
PH
Councillor Paul Hodgson-Jones Huntingdonshire District CouncilCommittee Member, present
RM
Councillor Ross Martin Huntingdonshire District CouncilSubstitute
SW
Councillor Susan Wallwork Fenland District CouncilSubstitute, present as substitute
SH
Councillor Sunita Hansraj South Cambridgeshire District CouncilSubstitute
RJ
Rhys Jarvis Independent PersonChair, present
ID
Councillor Iva Divkovic Cambridge City CouncilCommittee Member, apologies
CP
Councillor Chris Poulton Cambridgeshire County CouncilCommittee Member, apologies
MI
Councillor Mark Inskip East Cambridgeshire District CouncilCommittee Member, apologies
RS
Councillor Richard Stobart South Cambridgeshire District CouncilCommittee Member, present

All 16 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Internal Audit - Progress ReportThis decision
  2. Internal Audit - Progress ReportNoted
  3. Internal Audit - Progress ReportNoted
  4. Internal Audit - Draft Annual Internal Report 2025/26Noted
  5. Internal Audit Strategy 2026/27 - 2028/29, including the 2026/27 Internal Audit PlanApproved
  6. Internal Audit Action Tracker ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Audit and Governance Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... Noted Open
10 Sep 2026 Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... Decided Open
10 Sep 2026 Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. Decided Open
10 Sep 2026 Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... Noted Open
10 Sep 2026 CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies