Resolved
The Committee noted the Internal Auditor’s Progress Report
Audit and Governance Committee noted this item on Tuesday 15 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee noted the Internal Auditor’s Progress Report
CAMBRIDGESHIRE & PETERBOROUGH COMBINED AUTHORITY Internal Audit Progress Report Presented at the Audit and Governance Committee on 15 July 2025 This report is solely for the use of the persons to whom it is addressed. To the fullest extent permitted by law, RSM UK Risk Assurance Services LLP will accept no responsibility or liability in respect of this report to any other party.
Page 1 of 37 KEY MESSAGES The internal audit plan for 2024/25 was approved by the Audit and Governance Committee (AGC) at the March 2024 meeting and the internal audit plan for 2025/26 was approved by the AGC at the June 2025. This report provides an update on progress against these plans and summarises the results of our work to date.
2024/25 Work Programme [To discuss and note] Since the last Committee in June 2025, we have: • finalised one further report from the 2024/25 Programme • The final report remains in draft, awaiting management responses. The summary of 2024/25 programme is also outlined in Section 1 below. The table outlines the outcomes against the internal audit plan and highlights in bold the reports issued in final since the previous Audit Committee in June 2025.
2025/26 Work Programme [To note] Since the last Committee in June 2025, we have: • Commenced the first review from the 2025/26 Programme, with fieldwork in progress. • The remainder of the plan is scheduled in line with the agreed Internal Audit Plan. The schedule for the 2025/26 programme is also outlined in Section 2 below.
Client Briefings [To note] Five client briefings have been attached: • Failure to Prevent Fraud • Driving Value from AI • Employment Rights Bill • Emerging Risk Radar • Quality Assurance and Improvement Programme
Page 2 of 37 Audit Progress
Page 3 of 37 1. PROGRESS AGAINST THE INTERNAL AUDIT PLAN 2024/25 Assignment Status / Opinion issued Actions agreed Target Committee meeting Actual Committee meeting
L M H
Data Quality and Performance 1.24/25 Final - Reasonable Assurance 2 3 0 September 2024 September 2024
Final - Advisory – some GDPR 3.24/25 2 9 1 December 2024 September 2024 significant weaknesses
Improvement Plan 4.24/25 Final - Substantial Assurance 0 0 0 December 2024 September 2024
Workforce Planning 2.24/25 Final - Reasonable Assurance 3 3 0 November 2024 November 2024
Procurement and Contract Management Final - Partial Assurance 2 5 1 February 2025 February 2025 5.24/25
Risk Management 6.24/25 Final - Reasonable Assurance 2 3 0 February 2025 February 2025
Staff Mental Health and Wellbeing Final - Substantial Assurance 0 1 0 February 2025 February 2025 7.24/25
Fraud Risk Assessment Final - Advisory 2 4 0 June 2025 June 2025
Key Financial Controls - Creditors Final - Reasonable Assurance 2 3 0 June 2025 June 2025
Business Continuity Final - Partial Assurance 2 6 3 June 2025 June 2025
Follow Up - GDPR Final - Reasonable Progress 1 3 0 July 2025 July 2025
Follow Up Draft Report 0 9 0 July 2025 Now September 2025
Page 4 of 37 4 2. PROGRESS AGAINST THE INTERNAL AUDIT PLAN 2025/26 Assignment Status / Opinion issued Actions agreed Target Committee meeting Actual Committee meeting
L M H
Declaration of Interest Review In Progress September 2025
Delivery of Skills Strategy 28 July 2025 September 2025
Delivery of Climate Strategy 11 August 2025 September 2025
Business Continuity 17 September 2025 November 2025
Delivery of Equality Policy 30 September 2025 January 2026
Contract Management 3 November 2025 January 2026
Delivery of Transport Plan 17 November 2025 January 2026
Contract Management 15 December 2025 March 2026
Payroll 15 December 2025 March 2026
Follow Up 2 February 2026 March 2026
Page 5 of 37 5 APPENDIX A: OTHER MATTERS Detailed below are the changes to the audit plans: There have been no changes to the audit plans since the last AGC meeting.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit: Progress ReportReport | 2.9 MB | DownloadRead as text |
Follow Audit and Governance Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... | Noted | Open |
| 10 Sep 2026 | Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... | Decided | Open |
| 10 Sep 2026 | Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. | Decided | Open |
| 10 Sep 2026 | Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... | Noted | Open |
| 10 Sep 2026 | CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.