Single Assurance Framework: Reporting of Most Complex Programmes and Projects

Noted Committee 2 papers

AI summaryCambridgeshire and Peterborough Combined Authority Funding Committee noted performance data on its most complex projects. Four of the seven originally listed projects remain active, all rated Amber, while Homes Upgrade Grant 2 has completed delivery to 1,013 homes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPerformance report on most complex projects and programmes noted by Funding Committee
Moneyc. £620kPark Homes over-delivery liability risk mitigated on HUG 2
What happens nextNot stated
Who it affectsMost complex project teams and partnersFour live projects still Amber rated, one completed

What was decided

The Funding Committee noted the performance report on the Most Complex Projects and Programmes. Report P1, 1.1

Why

The Single Assurance Framework requires the Funding Committee to review the most complex projects' performance including risk, as part of ensuring accountability, probity, transparency, legal compliance and value for money. Report P4, 3.2, 3.3

The SAF was a key objective of the Combined Authority's Improvement Programme and responds to concerns raised by Government through the Best Value Notice. Report 2.1

What happens next

A review of the most complex projects will be undertaken as part of the Performance Management refresh now that the Corporate Plan has been approved at Combined Authority Board on 24 September. Report 2.2

An independent Chair for the Bus Reform review has been approved by the Mayor, with tendering for supporting consultants underway; the review aims to start in October and take three months. Report 2.2

The money

  • c. £620k Park Homes over-delivery liability risk on Homes Upgrade Grant 2, mitigated as DESNZ/HMT are allowing over-delivery Report 2.2

Implications

  • Financial: No direct financial implications arising from this report. Report P14
  • Legal: No significant legal implications arising from this report; the SAF sets out requirements for performance management of projects including risk management and governance. Report P14
  • Risk: Four live most complex projects remain Amber rated, meaning successful delivery may be adversely impacted without action. Report 2.2
  • Other: No public health, environmental or climate change implications identified. Report P14

Who and where

  • Project teams delivering the four live Amber-rated most complex projects Report 2.2
  • Learners on the Adult Skills Fund and Free Courses for Jobs Report 2.2
  • Residents of homes upgraded under Homes Upgrade Grant 2 Report 2.2
  • Residents and businesses in Market Towns including Fenland and Ramsey Report 2.2

Timeline

  • 8 September: Audit and Governance Committee reviewed the Combined Authority Single Assurance Management Framework and Procedure. Report 3.1
  • 20 September: Combined Authority Board approved the Single Assurance Framework and Procedure. Report 3.1
  • 24 September: Corporate Plan approved at Combined Authority Board. Report 2.2
  • Q3 2024/25: Four projects first rated Amber; they have remained Amber for this report. Report 2.2
  • October: Bus Reform review aims to start, taking three months. Report 2.2
  • 2025-11-03: Funding Committee meeting noted the performance report.

Plain English for the jargon

  • SAF: Single Assurance Framework: a set of systems and processes providing a consistent approach to appraisal, assurance, risk and performance across CPCA projects and programmes.
  • CPCA: Cambridgeshire and Peterborough Combined Authority.
  • EDAF: English Devolution Accountability Framework, the Government standard the Combined Authority must meet.
  • HUG 2: Homes Upgrade Grant 2, a government-funded programme to upgrade homes; the CPCA programme has now reached successful completion.
  • DESNZ: Department for Energy Security and Net Zero.
  • HMT: HM Treasury.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED : A. To note the performance report on the Most Complex Projects and Programmes.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Funding Committee

Recommendations

A To note the performance report on the Most Complex Projects and Programmes.

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s):

☒ Connectivity ☒ Growth ☒ Jobs ☒ Homes ☒ Resilience ☒ Performance The SAF is a set of systems and processes designed to provide the CPCA with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes. It is focused on ensuring accountability, probity, transparency and legal compliance – and critically, value for money of investments. It covers the full end to end lifecycle of projects and programmes that place a financial liability on the CPCA.

1. Purpose

1.1To note the most complex projects’ performance data. 2. Proposal

2.1The CPCA are accountable for delivering in a complex and changing environment. How we manage the investment process is critical to the successful delivery of strategic aims. To meet the standards set by Government – such as the English Devolution Accountability Framework (EDAF) - we needed a specific Assurance Framework that shows how we will meet best value requirements and ensuring we are spending public money in the most effective way. In addition, the SAF was a key objective from the Improvement Programme and is a way of demonstrating that the CPCA has responded to concerns raised by Government through the Best Value Notice.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Most Complex Projects Performance DashboardAppendix A 137 KB Download
PDF
Single Assurance Framework: Reporting of Most Complex Programmes and ProjectsReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityChair, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilVice-Chair, present
SS
Councillor Simon Smith Cambridge City CouncilCommittee Member, apologies, sent representative
KY
Councillor Karen Young Cambridgeshire County CouncilCommittee Member, present
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, present
SC
Councillor Steve Count Fenland District CouncilCommittee Member, absent
MJ
Councillor Mohammed Jamil Peterborough City CouncilCommittee Member, present
JW
Councillor John Williams South Cambridgeshire District CouncilCommittee Member, present
RR
Councillor Richard Robertson Cambridge City CouncilCommittee Member, present as substitute
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilSubstitute
IB
Councillor Ian Bovingdon East Cambridgeshrie District CouncilSubstitute
SI
Councillor Sidney Imafidon Fenland District CouncilSubstitute

All 16 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Single Assurance Framework: Reporting of Most Complex Programmes and ProjectsThis decision
  2. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  3. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  4. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  5. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  6. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved

More from Cambridgeshire and Peterborough Combined Authority Funding Committee

All decisions
MeetingDecisionOutcome
7 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 3 August 2026 were approved. Approved Open
7 Sep 2026 Single Assurance Framework Business Case Approvals: Funding Committee Decisions(Unanimous) A. To recommend that the Combined Authority Board approve the Full Business Case and £24,465,000 for Acti... Approved Open
7 Sep 2026 Single Assurance Framework Business Case Approvals: Officer DecisionsA. To note the Officer Decisions for projects under the Single Assurance Framework delegation from Funding Panels hel... Noted Open
7 Sep 2026 Closure of Subsidiary Cambridgeshire and Peterborough Business Growth Company Limited(Unanimous) A. To recommend that the Combined Authority Board approve the Shareholder documentation as appended at Ap... Approved Open
7 Sep 2026 Work ProgrammeA. To note the Funding Committee’s . Noted Open