Single Assurance Framework Review

Approved Finance 4 papers

AI summaryAudit and Governance Committee unanimously backs updated Single Assurance Framework and sends it to the Combined Authority Board for approval on 26 November 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUnanimous endorsement of updated framework
MoneyNo material financial implicationsMore efficient framework expected to improve value for money
What happens nextCombined Authority Board, 26 November 2025Board to consider approval of updated framework
Who it affectsCPCA projects and programmesAffects how decisions are made across the authority

What was decided

The Committee unanimously recommended that the Combined Authority Board approve the updated Single Assurance Framework document at Appendix B. Report P1

The recommendation covers revised delegated approval levels, the inclusion of government business cases in SAF submissions, and cumulative change request totals.

Why

The framework has been in operation for over a year and an annual review is part of good governance, the Committee was told. Report 1.1

A local assurance framework is required before the Combined Authority can apply to become an established mayoral strategic authority with access to wider devolution.

Officers said the changes would speed up low-value project decisions and free up Board and Funding Committee time for larger projects.

What happens next

The updated framework will be presented to the Combined Authority Board on 26 November 2025 for approval. Report P12

A training schedule for CPCA and constituent council officers will be put in place after the decision.

The framework will be updated again once the Business Board arrangements review is complete. Report 2.2

Options considered

  • Chosen: Raise Executive Director business case approval threshold to £500k and CEX threshold from £1m to £2m, with cumulative change requests and ringfenced funding going straight to business case. Preferred proposal following consultation with Corporate Management Team and the Chief Executive Group, which called for higher delegation levels Report P12
  • Rejected: Lower Executive Director business case approval threshold of £100k as initially proposed internally. The Chief Executive Group and Public Service Board said the threshold should be increased to £500k to support swifter delivery

Implications

  • Legal: The SAF is embedded in the Combined Authority's Constitution, so any change needs Board approval.
  • Financial: Officers expect no material financial impact but say a more efficient framework should improve value for money.
  • Risk: Making change request totals cumulative is intended to help identify ongoing problems with a project.
  • Other: All concept, business case and change request papers will continue to go through the Funding Panel first, with CMT, shared services, S73 Officer and Monitoring Officer input.

Who and where

  • CPCA Executive Directors and senior officers making delegated decisions Report P12
  • CPCA and constituent council officers who will receive training on the updated framework
  • Project and programme sponsors bringing forward concept and business case papers Report P12
  • Members of the Funding Committee and Combined Authority Board

Timeline

  • November 2023: SAF originally approved by the Combined Authority Board and endorsed by MHCLG Report 3.1
  • July 2024 (formally notified September 2024): Best Value Notice removed following improved assurance arrangements Report 3.1
  • 30 July 2025: Draft proposals shared with the Corporate Management Team
  • 8 September: Review session held with the Combined Authority Chief Executive Group and Public Service Board
  • 26th November 2025: Updated SAF due to be presented to the Combined Authority Board for approval
  • Post decision: Training schedule to be implemented for CPCA and constituent council officers

Plain English for the jargon

  • SAF: Single Assurance Framework, the CPCA's local assurance framework for appraising, assuring and managing projects and programmes
  • CPCA: Cambridgeshire and Peterborough Combined Authority
  • MTFP: Medium Term Financial Plan, the authority's approved budget framework
  • S73 Officer: The officer with statutory Section 73 finance responsibilities, effectively the chief finance officer
  • MHCLG: Ministry of Housing, Communities and Local Government
  • ED: Executive Director
  • CEX: Chief Executive
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

(Unanimous) A. To consider and comment on the updated Single Assurance Framework document at Appendix B B. To recommend to the Combined Authority Board that the updated Single Assurance Framework (SAF) be approved. A. To consider and comment on the updated Single Assurance Framework document at Appendix B B. To recommend to the Combined Authority Board that the updated Single Assurance Framework (SAF) be approved. (At 12.30pm during the discussion on this item, Councillor I Ali left the meeting and did not return).
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Audit and Governance Committee

Recommendations

A To consider and comment on the updated Single Assurance Framework document attached at Appendix B. B To recommend to the Combined Authority Board that the updated Single Assurance Framework (SAF) be approved.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☒ Homes ☒ Performance

A strengthened framework and procedure align to all the CPCA’s strategic objectives, this is because robust assurance management supports the effective and efficient delivery of the 2025-29 Corporate Plan.

1. Purpose

1.1The primary purpose of this report is to present the updated Single Assurance Framework (SAF) document to the Audit and Governance Committee for consideration. It is good practice for Assurance Frameworks to be considered by a Combined Authority’s Audit Committee for endorsement prior to it being presented for approval to its Board.

2. Proposal 2.1 The CPCA Single Assurance Framework (SAF) is a set of systems and processes designed to provide the CPCA with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes. CPCA’s SAF has now been in operation for over a year and is intended to be subject to annual review as part of good governance arrangements. A local assurance framework, such as the SAF, is integral to the operation of all Combined Authorities. A Combined Authority must have a local assurance framework before it can apply to become an established mayoral strategic authority and in so doing access wider and deeper devolution as well as an Integrated Settlement amongst other opportunities. The assurance framework must satisfy MHCLG requirements in relation to robust governance and any review is subject to approval by MHCLG. The updated SAF will be presented to the Combined Authority Board at its meeting on 26th November 2025 for approval. This follows extensive consultation while developing the proposals. As part of the SAF review it is important to note that the CPCA has moved from an organisation that required improvement, to one with robust governance which supports the Authority, working alongside others, to deliver important and transformational projects across the Cambridgeshire and Peterborough region. The SAF also offers assurance in the delivery of the Corporate Plan 2025-2029 which sets out the roadmap for the next four years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Options Considered (inc Preferred Option)Appendix A 89 KB Download
PDF
Single Assurance Framework (Draft Nov25) CLEANAppendix B 1.2 MB Download
PDF
Single Assurance Framework ReviewReport 144 KB DownloadRead as text
PDF
Updated Section 7.2Report 86 KB Download

At this meeting

Whole meeting

Who was there

8 of 16 attended
RJ
Rhys Jarvis Independent PersonChair, apologies
DH
David HarwoodIndependent Person, present
ID
Councillor Iva Divkovic Cambridge City CouncilCommittee Member, present
CP
Councillor Chris Poulton Cambridgeshire County CouncilCommittee Member, present
MI
Councillor Mark Inskip East Cambridgeshire District CouncilCommittee Member, present
GC
Councillor Gary Christy Fenland District CouncilCommittee Member, present
PH
Councillor Paul Hodgson-Jones Huntingdonshire District CouncilVice-Chair, present
IA
Councillor Imtiaz Ali Peterborough City CouncilCommittee Member, present
RS
Councillor Richard Stobart South Cambridgeshire District CouncilCommittee Member, present
MT
Councillor Mike Todd-Jones Cambridge City CouncilSubstitute
PF
Councillor Peter Fane Cambridgeshire County CouncilSubstitute
CW
Councillor Christine Whelan East Cambridgeshire District CouncilSubstitute

All 16 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Single Assurance Framework ReviewThis decision
  2. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  3. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  4. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  5. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  6. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved

More from Cambridgeshire and Peterborough Combined Authority Audit and Governance Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... Noted Open
10 Sep 2026 Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... Decided Open
10 Sep 2026 Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. Decided Open
10 Sep 2026 Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... Noted Open
10 Sep 2026 CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies